9344-9346 N WHITE OAK AVE 91325

Certificate Information: 9344-9346 N WHITE OAK AVE 91325

Application / Permit
23010-20000-03026
Plan Check / Job No.
B23VN09839
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 25'-4" x 38'-9" TWO-STORY SINGLE FAMILY DWELLING PER SB9 (@ 1ST FLOOR) W/ ATT. ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e) AND ATT. OPEN TRELLIS (@ 2ND FLOOR); NFPA-13D THRU-OUT
Permit Issued
Issued on 1/16/2024
Issuing Office
Current Status
CofO Issued on 8/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/2/2023 APPLICANT
Assigned to Plan Check Engineer 8/17/2023 SEAN SHAHMIRI
Corrections Issued 8/24/2023 SEAN SHAHMIRI
Quality Review Completed 8/25/2023 OMID HEDAYAT
Applicant returned to address corrections 12/4/2023 SEAN SHAHMIRI
Plan Check Approved 1/11/2024 SEAN SHAHMIRI
Issued 1/16/2024 APPLICANT
CofO in Progress 8/18/2025 CHRISTOPHER ROJAS
Permit Finaled 8/20/2025 RUBEN SALAS
CofO Issued 8/20/2025 RUBEN SALAS
Permit Finaled 8/20/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/1/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 9/1/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 9/1/2023 DAGOVERTO GUERRERO
Senate Bill 9 Cleared 9/7/2023 MAXFIELD VERMY
Hydrant and Access approval Cleared 9/24/2023 JOHN CONNEALLY
Low Impact Development (LID) Cleared 11/8/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 11/9/2023 CARLOS AGUILERA
Green Code Cleared 12/4/2023 SEAN SHAHMIRI

Contact Information

Architect Maru,, Keyur N; Lic. No.: C38310 6169 ATHENA STREET      CHINO, CA 91710
Contractor Owner-Builder       ,
Engineer Pachunuri,, Nalin Kumar; Lic. No.: C78970 21126 INGOMAR CT      CANOGA PARK, CA 91304

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/19/2024 Partial Approval JAVIER RAMOS JR
Pre-Inspection 3/19/2024 Approved JAVIER RAMOS JR
Underground Mechanical 3/19/2024 Not Ready for Inspection JAVIER RAMOS JR
Footing/Foundation/Slab 3/20/2024 Approved JAVIER RAMOS JR
PLUMBING-Rough 3/20/2024 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 4/8/2024 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 4/19/2024 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 4/26/2024 Not Ready for Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 4/26/2024 Partial Approval JAVIER RAMOS JR
HVAC-Rough 4/26/2024 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Rough 4/26/2024 Not Ready for Inspection JAVIER RAMOS JR
BUILDING-Rough-Frame 5/6/2024 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 5/6/2024 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 5/6/2024 Approved JAVIER RAMOS JR
Green Building Rough 5/6/2024 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Rough 5/6/2024 Approved JAVIER RAMOS JR
PLUMBING-Rough 5/6/2024 Approved JAVIER RAMOS JR
Verify Sprinkler Sign Off 5/6/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 5/15/2024 Partial Inspection JAVIER RAMOS JR
Green Building Rough 5/15/2024 Approved JAVIER RAMOS JR
Insulation 5/15/2024 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 5/15/2024 Partial Approval JAVIER RAMOS JR
Shower Pan 5/15/2024 Approved JAVIER RAMOS JR
Verify Sprinkler Sign Off 5/15/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 6/11/2024 Partial Approval JAVIER RAMOS JR
Drywall Nailing 6/11/2024 Approved JAVIER RAMOS JR
Insulation 6/11/2024 Approved JAVIER RAMOS JR
Sewer 7/22/2024 Approved JAVIER RAMOS JR
Underground Mechanical 7/22/2024 Partial Approval JAVIER RAMOS JR
Underground Mechanical 7/29/2024 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 12/23/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Final 12/23/2024 Partial Inspection JAVIER RAMOS JR
Final 12/23/2024 Corrections Issued JAVIER RAMOS JR
Green Building Final 12/23/2024 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 12/23/2024 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 12/23/2024 SGSOV Not Required JAVIER RAMOS JR
Smoke Detectors 12/23/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Final 2/14/2025 Approved JAVIER RAMOS JR
Final 2/14/2025 Corrections Issued JAVIER RAMOS JR
Green Building Final 2/14/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 2/14/2025 Approved JAVIER RAMOS JR
Final 4/25/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Service/Power Release 4/25/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Final 8/18/2025 OK to Issue CofO CHRISTOPHER ROJAS
Service/Power Release 8/18/2025 Approved CHRISTOPHER ROJAS