8644 N CORBIN AVE 91324
Certificate Information: 8644 N CORBIN AVE 91324
- Application / Permit
- 23010-20000-03022
- Plan Check / Job No.
- B23VN09829
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan NEW 24' X 25' TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 10/27/2023
- Issuing Office
- Current Status
- CofO Issued on 11/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/10/2023 | SELLA BENYAMIN |
| Corrections Issued | 8/17/2023 | SELLA BENYAMIN |
| Quality Review Completed | 8/23/2023 | STEVEN KIM |
| Applicant returned to address corrections | 10/12/2023 | SELLA BENYAMIN |
| Plan Check Approved | 10/24/2023 | SELLA BENYAMIN |
| Issued | 10/27/2023 | APPLICANT |
| CofO in Progress | 10/25/2024 | JEFFREY HARTLINE |
| Permit Finaled | 11/4/2024 | JOHN JANSON |
| CofO Issued | 11/4/2024 | JOHN JANSON |
| Permit Finaled | 11/4/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/31/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 9/1/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 9/1/2023 | DAGOVERTO GUERRERO |
| Low Impact Development (LID) | Cleared | 9/6/2023 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 9/6/2023 | COLIN LOREDO |
Contact Information
| Contractor | Moallem Nabiollah N; Lic. No.: 643280-B | , |
| Contractor | Nabiollah N Moallem; Lic. No.: 643280-B | , |
| Engineer | Mirzadeh,, Amir; Lic. No.: NA58119 | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/1/2023 | Approved | JEFFREY HARTLINE |
| Underground Mechanical | 11/1/2023 | Approved | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2023 | No Access for Inspection | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2023 | Approved | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2023 | Corrections Issued | JEFFREY HARTLINE |
| HVAC-Rough | 12/29/2023 | Not Ready for Inspection | MORRIS JACKSON |
| Interior/Exterior Lathing | 12/29/2023 | Corrections Issued | MORRIS JACKSON |
| ELECTRICAL-Rough | 1/16/2024 | Approved | JEFFREY HARTLINE |
| HVAC-Rough | 1/16/2024 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 1/16/2024 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 1/16/2024 | Corrections Issued | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 1/19/2024 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 1/19/2024 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 1/19/2024 | Approved | JEFFREY HARTLINE |
| Verify Sprinkler Sign Off | 1/19/2024 | Approved | JEFFREY HARTLINE |
| Insulation | 1/23/2024 | Approved | JEFFREY HARTLINE |
| Shower Pan | 1/23/2024 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 1/31/2024 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 1/31/2024 | Approved | JEFFREY HARTLINE |
| Final | 10/24/2024 | OK to Issue CofO | JEFFREY HARTLINE |
| Green Building Final | 10/24/2024 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 10/24/2024 | SGSOV Not Required | JEFFREY HARTLINE |
| Service/Power Release | 10/24/2024 | Approved | JEFFREY HARTLINE |
| Smoke Detectors | 10/24/2024 | Approved | JEFFREY HARTLINE |