9517 N CORBIN AVE 91324

Certificate Information: 9517 N CORBIN AVE 91324

Application / Permit
23010-20000-02982
Plan Check / Job No.
B23VN09702
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 27'-8"x 42'-7 1/2" DETTACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 12/12/2023
Issuing Office
Valley
Current Status
CofO Issued on 3/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/21/2023 APPLICANT
Assigned to Plan Check Engineer 7/27/2023 KAMYAR EMAMI
Corrections Issued 7/27/2023 KAMYAR EMAMI
Building Plans Picked Up 8/4/2023 APPLICANT
Plan Check Approved 12/1/2023 LUISANGEL VALENZUELA
Issued 12/12/2023 APPLICANT
CofO in Progress 2/17/2025 KRISTEN BEVERIDGE
CofO Issued 3/6/2025 JOHN JANSON
Permit Finaled 3/6/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/5/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 9/6/2023 CARLOS AGUILERA
Sewer availability Cleared 9/6/2023 CARLOS AGUILERA
Construction near power lines Cleared 10/5/2023 RIDWAN HARDY
Low Impact Development (LID) Cleared 11/22/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 11/27/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Asprer,, Anjero; Lic. No.: C91126 2708 FOOTHILL BLVD. #1006      LA CRESCENTA, CA 91214

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/2/2024 Approved DAVID SCANTLIN
Excavation/Setback/Form/Re-Bar 4/10/2024 Approved DAVID SCANTLIN
Underground Mechanical 4/17/2024 Approved DAVID SCANTLIN
ELECTRICAL-Rough 6/7/2024 Not Ready for Inspection DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 6/7/2024 Approved DAVID SCANTLIN
Green Building Rough 6/7/2024 Not Ready for Inspection DAVID SCANTLIN
HVAC-Rough 6/7/2024 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Rough 6/7/2024 Not Ready for Inspection DAVID SCANTLIN
Verify Sprinkler Sign Off 6/7/2024 Not Ready for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 6/17/2024 Approved DAVID SCANTLIN
ELECTRICAL-Rough 6/17/2024 Approved DAVID SCANTLIN
Green Building Rough 6/17/2024 Approved DAVID SCANTLIN
HVAC-Rough 6/17/2024 Approved DAVID SCANTLIN
Interior/Exterior Lathing 6/17/2024 Partial Approval DAVID SCANTLIN
PLUMBING-Rough 6/17/2024 Approved DAVID SCANTLIN
Verify Sprinkler Sign Off 6/17/2024 Approved DAVID SCANTLIN
Drywall Nailing 7/10/2024 Approved DAVID SCANTLIN
Insulation 7/10/2024 Approved DAVID SCANTLIN
Shower Pan 7/22/2024 Approved HENRY KIM
Interior/Exterior Lathing 7/23/2024 Approved KRISTEN CAUSEY
ELECTRICAL-Final 12/24/2024 Approved DAVID SCANTLIN
Final 12/24/2024 Corrections Issued DAVID SCANTLIN
Footing/Foundation/Slab 12/24/2024 Approved DAVID SCANTLIN
Green Building Final 12/24/2024 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 12/24/2024 SGSOV Approved DAVID SCANTLIN
Service/Power Release 12/24/2024 Not Ready for Inspection DAVID SCANTLIN
Smoke Detectors 12/24/2024 Approved DAVID SCANTLIN
Final 2/5/2025 Not Ready for Inspection KRISTEN CAUSEY
Green Building Final 2/13/2025 Partial Inspection KRISTEN CAUSEY
Final 2/14/2025 OK to Issue CofO KRISTEN CAUSEY
Green Building Final 2/14/2025 Approved KRISTEN CAUSEY
Service/Power Release 2/14/2025 Approved KRISTEN CAUSEY