2718-2720 S MONTE MAR TER 90064

Certificate Information: 2718-2720 S MONTE MAR TER 90064

Application / Permit
23010-20000-02941
Plan Check / Job No.
B23VN09503
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
(N) 45'-2" X 20'-8" RECROOM WITH ATTACHED PATIO COVER AND FULL BATHROOM WITH EXTERIOR ACCESS ONLY ALL WORK PER ENGINEERING
Permit Issued
Issued on 10/5/2023
Issuing Office
Valley
Current Status
Issued on 10/5/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/17/2023 APPLICANT
Assigned to Plan Check Engineer 7/20/2023 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 7/25/2023 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 7/27/2023 OMID HEDAYAT
Building Plans Picked Up 7/27/2023 APPLICANT
Plan Check Approved 10/5/2023 LUSINE BABAYAN
Issued 10/5/2023 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/2/2023 ANTHONY MAINEZ
Sewer availability Cleared 8/2/2023 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 8/15/2023 ANTHONY MAINEZ
Specific Plan Cleared 9/13/2023 ROBERT SANCHEZ
Hydrant and Access approval Cleared 9/21/2023 JOHN CONNEALLY
GPI Written Notices Cleared 9/29/2023 SEWADA ZADOORAN MILAGARDI
Grading Pre-Inspection Cleared 9/29/2023 SEWADA ZADOORAN MILAGARDI

Contact Information

Architect Larkin,, Dean A; Lic. No.: C28277 8912 HOLLYWOOD HILLS RD      LOS ANGELES, CA 90046
Contractor Drexel Construction Management Llc; Lic. No.: 1014160-B 5168 W PICO BLVD      LOS ANGELES, CA 90019
Engineer Irvine,, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD STE 1      PASADENA, CA 91107
Engineer Naraghi-Arani,, Kamran; Lic. No.: C40985 30423 CANWOOD ST STE 223      AGOURA HILLS, CA 91301
Engineer Nester,, Melvin Russell; Lic. No.: C26324 2902 TYLER CT      SIMI VALLEY, CA 93063
Engineer Tran,, Quang Tai; Lic. No.: C70929 355 N LANTANA ST 333      CAMARILLO, CA 93010

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/8/2024 Corrections Issued ASHLEY THOMPSON
METHANE-Barrier 10/8/2024 Not Ready for Inspection ASHLEY THOMPSON
METHANE-Subgrade 10/8/2024 Not Ready for Inspection ASHLEY THOMPSON
Special/Order Compliance 10/8/2024 Partial Approval REGINA MENDEZ
Excavation/Setback/Form/Re-Bar 10/9/2024 Partial Approval ASHLEY THOMPSON
Footing/Foundation/Slab 10/22/2024 Partial Approval ASHLEY THOMPSON
METHANE-Barrier 10/22/2024 Not Ready for Inspection ASHLEY THOMPSON
METHANE-Subgrade 10/22/2024 Not Ready for Inspection ASHLEY THOMPSON
METHANE-Subgrade 11/22/2024 Approved ASHLEY THOMPSON
Footing/Foundation/Slab 12/9/2024 Partial Approval SEAN HAUPT
METHANE-Barrier 12/9/2024 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 1/24/2025 Corrections Issued ARAM AVEDISIAN
METHANE-Rough 1/28/2025 Approved ARAM AVEDISIAN
PLUMBING-Rough 1/28/2025 Approved ARAM AVEDISIAN
Footing/Foundation/Slab 2/24/2025 Partial Approval MEL KHACHATOURIAN
Excavation/Setback/Form/Re-Bar 3/6/2025 Partial Approval BOBBY KEY
Footing/Foundation/Slab 5/19/2025 Approved ASHLEY THOMPSON
ELECTRICAL-Rough 8/1/2025 Approved BOBBY KEY
HVAC-Rough 8/1/2025 Approved BOBBY KEY
PLUMBING-Rough 8/1/2025 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 8/18/2025 Partial Approval ASHLEY THOMPSON
BUILDING-Rough-Frame 8/26/2025 Corrections Issued ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 8/26/2025 Corrections Issued ASHLEY THOMPSON
Green Building Rough 8/26/2025 Not Ready for Inspection ASHLEY THOMPSON
Verify Sprinkler Sign Off 8/26/2025 Approved ASHLEY THOMPSON
BUILDING-Rough-Frame 10/23/2025 Not Ready for Inspection ASHLEY THOMPSON
Insulation 10/23/2025 Corrections Issued ASHLEY THOMPSON
Interior/Exterior Lathing 10/23/2025 Partial Approval ASHLEY THOMPSON
BUILDING-Rough-Frame 11/24/2025 Approved ASHLEY THOMPSON
Green Building Rough 11/24/2025 Approved ASHLEY THOMPSON
Insulation 11/24/2025 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 11/24/2025 Partial Inspection ASHLEY THOMPSON
Shower Pan 11/24/2025 Corrections Issued ASHLEY THOMPSON
Insulation 11/26/2025 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 11/26/2025 Not Ready for Inspection ASHLEY THOMPSON
Shower Pan 11/26/2025 Not Ready for Inspection ASHLEY THOMPSON
Shower Pan 12/4/2025 Approved EVAN COOPER
Drywall Nailing 12/10/2025 Approved ASHLEY THOMPSON
HVAC-Final 7/23/2026 Corrections Issued ASHLEY THOMPSON
ELECTRICAL-Final 7/27/2026 Approved ASHLEY THOMPSON
Final 7/27/2026 Corrections Issued ASHLEY THOMPSON
Green Building Final 7/27/2026 Approved ASHLEY THOMPSON
PLUMBING-Final 7/27/2026 Corrections Issued ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 7/27/2026 SGSOV Not Required ASHLEY THOMPSON
Service/Power Release 7/27/2026 Not Ready for Inspection ASHLEY THOMPSON
Smoke Detectors 7/27/2026 Approved ASHLEY THOMPSON
HVAC-Final 7/29/2026 Not Ready for Inspection ASHLEY THOMPSON