9009 N LAUREL CANYON BLVD 91352
Certificate Information: 9009 N LAUREL CANYON BLVD 91352
- Application / Permit
- 23010-20000-02926
- Plan Check / Job No.
- B23VN09035
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- (N) TRASH ENCLOSURE W/ TRELLIS ROOF FOR (N) RESTAURANT **ePlan**
- Permit Issued
- Issued on 12/18/2024
- Issuing Office
- Current Status
- Permit Finaled on 8/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/13/2023 | NILOOFAR MEHRAIN |
| Corrections Issued | 7/16/2023 | NILOOFAR MEHRAIN |
| Quality Review Completed | 7/18/2023 | STEVEN KIM |
| Applicant returned to address corrections | 1/18/2024 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 6/6/2024 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 12/16/2024 | NILOOFAR MEHRAIN |
| Plan Check Approved | 12/17/2024 | NILOOFAR MEHRAIN |
| Issued | 12/18/2024 | APPLICANT |
| Permit Finaled | 8/18/2025 | GREGORY POMISH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/6/2023 | NIKKI ZULUETA |
| Roof/Waste drainage to street | Cleared | 11/6/2023 | NIKKI ZULUETA |
| ZA Case | Cleared | 10/16/2024 | DALIA MOKAYED |
| ZA Case | Cleared | 10/16/2024 | DALIA MOKAYED |
Contact Information
| Architect | Bickel,, James S; Lic. No.: C20925 | 3600 BIRCH STREET SUITE 120 NEWPORT BEACH, CA 92660 |
| Contractor | C C K Builders Inc; Lic. No.: 855822-B | , |
| Engineer | Lee,, Jin Soo; Lic. No.: C49326 | 4249 WILEY LANE GLENDALE, CA 91214 |
| Engineer | Thompson,, Douglas Sevier; Lic. No.: S2578 | 21084 BAKE PARKWAY SUITE 100 LAKE FOREST, CA 92630 |
Inspector Information
| JOHN KITCKO, (818) 374-1109 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/25/2025 | Partial Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 2/27/2025 | Conditional Approval | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 2/28/2025 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 3/4/2025 | Partial Inspection | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 3/7/2025 | Partial Approval | DANNY RODRIGUEZ |
| Wood Frame | 3/26/2025 | Partial Approval | GREGORY POMISH |
| Excavation/Setback/Form/Re-Bar | 3/27/2025 | Partial Approval | GREGORY POMISH |
| Final | 8/18/2025 | Permit Finaled | GREGORY POMISH |
| Footing/Foundation/Slab | 8/18/2025 | Approved | GREGORY POMISH |
| SGSOV-Seismic Gas S/O Valve | 8/18/2025 | SGSOV No Gas | GREGORY POMISH |
| Smoke Detectors | 8/18/2025 | Approved | GREGORY POMISH |
| Verify Sprinkler Sign Off | 8/18/2025 | Approved | GREGORY POMISH |
| Wood Frame | 8/18/2025 | Approved | GREGORY POMISH |