8131 S LOYOLA BLVD 90045
Certificate Information: 8131 S LOYOLA BLVD 90045
- Application / Permit
- 23010-20000-02918
- Plan Check / Job No.
- B23LA08370
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Carport
- Work Description
- Eplan New detached 2 car carport at the rear of property
- Permit Issued
- Issued on 10/11/2023
- Issuing Office
- Current Status
- CofO Issued on 6/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/11/2023 | MARCELA FRANQUEZ |
| Corrections Issued | 5/13/2023 | MARCELA FRANQUEZ |
| Quality Review Completed | 5/19/2023 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 6/15/2023 | MARCELA FRANQUEZ |
| Plan Check Approved | 10/10/2023 | MARCELA FRANQUEZ |
| Issued | 10/11/2023 | APPLICANT |
| CofO in Progress | 5/30/2025 | JESUS PINEDA |
| Permit Finaled | 6/5/2025 | RICHARD STEINBACH |
| CofO Issued | 6/5/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/5/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Specific Plan | Cleared | 7/17/2023 | ALESSANDRO MERCURI |
| Roof/Waste drainage to street | Cleared | 8/2/2023 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2023 | DARIN LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Crook,, Barrett Cameron; Lic. No.: C57196 | 5306 MULHOLLAND DRIVE SUMMERVILLE, SC 29485 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/13/2023 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 11/13/2023 | Not Ready for Inspection | BOBBY KEY |
| Footing/Foundation/Slab | 11/21/2023 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2025 | Approved | BOBBY KEY |
| Green Building Rough | 1/27/2025 | Not Ready for Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 2/6/2025 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Rough | 2/6/2025 | Approved | MICHAEL ALLEN |
| Footing/Foundation/Slab | 2/6/2025 | Approved | MICHAEL ALLEN |
| Green Building Rough | 2/6/2025 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 2/26/2025 | Approved | TEMISTOCLES CAAL |
| Final | 4/3/2025 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 4/3/2025 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 4/3/2025 | SGSOV Not Required | JESUS PINEDA |
| Service/Power Release | 4/3/2025 | Not Required | JESUS PINEDA |
| Smoke Detectors | 4/3/2025 | Approved | JESUS PINEDA |
| Final | 5/13/2025 | Corrections Issued | JESUS PINEDA |
| Final | 5/30/2025 | OK to Issue CofO | JESUS PINEDA |