8622 N LUBAO AVE 91306
Certificate Information: 8622 N LUBAO AVE 91306
- Application / Permit
- 23010-20000-02917
- Plan Check / Job No.
- B23VN09371
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan NEW 1-story 1,200 SQ. FT. DETACHED A.D.U Per Ordinance and LAMC 12.22 A33 (c)&(d).
- Permit Issued
- Issued on 8/24/2023
- Issuing Office
- Current Status
- CofO Issued on 2/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2023 | ZAW HAN |
| Corrections Issued | 7/25/2023 | ZAW HAN |
| Applicant returned to address corrections | 8/15/2023 | WEIJIAN HUANG |
| Applicant returned to address corrections | 8/19/2023 | ZAW HAN |
| Plan Check Approved | 8/24/2023 | ZAW HAN |
| Issued | 8/24/2023 | APPLICANT |
| CofO in Progress | 1/24/2024 | JEFFREY HARTLINE |
| Permit Finaled | 2/14/2024 | JOHN JANSON |
| CofO Issued | 2/14/2024 | JOHN JANSON |
| Permit Finaled | 2/14/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/26/2023 | FERNANDO GIL |
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2023 | FERNANDO GIL |
| Sewer availability | Cleared | 7/26/2023 | FERNANDO GIL |
| Low Impact Development (LID) | Cleared | 8/10/2023 | VICTOR MENDOZA |
| Roof/Waste drainage to street | Cleared | 8/16/2023 | NIKKI ZULUETA |
Contact Information
| Contractor | Lush Remodeling Corporation; Lic. No.: 1073605-B | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: NA76828 | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/30/2023 | Approved | JEFFREY HARTLINE |
| Excavation/Setback/Form/Re-Bar | 9/6/2023 | Approved | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 9/6/2023 | Approved | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2023 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 10/18/2023 | Corrections Issued | JEFFREY HARTLINE |
| HVAC-Rough | 10/18/2023 | Partial Approval | JEFFREY HARTLINE |
| PLUMBING-Rough | 10/18/2023 | Corrections Issued | JEFFREY HARTLINE |
| Wood Frame | 10/18/2023 | Corrections Issued | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 10/23/2023 | Corrections Issued | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 10/26/2023 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 10/26/2023 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 10/26/2023 | Approved | JEFFREY HARTLINE |
| HVAC-Rough | 10/26/2023 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 10/26/2023 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 10/26/2023 | Approved | JEFFREY HARTLINE |
| Verify Sprinkler Sign Off | 10/26/2023 | Approved | JEFFREY HARTLINE |
| Insulation | 10/31/2023 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 10/31/2023 | Approved | JEFFREY HARTLINE |
| Shower Pan | 10/31/2023 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 11/6/2023 | Approved | JEFFREY HARTLINE |
| Final | 1/12/2024 | Corrections Issued | JEFFREY HARTLINE |
| Green Building Final | 1/12/2024 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 1/12/2024 | SGSOV No Gas | JEFFREY HARTLINE |
| Service/Power Release | 1/12/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| Smoke Detectors | 1/12/2024 | Approved | JEFFREY HARTLINE |
| Service/Power Release | 1/22/2024 | Approved | JEFFREY HARTLINE |
| Final | 1/23/2024 | OK to Issue CofO | JEFFREY HARTLINE |