8622 N LUBAO AVE 91306

Certificate Information: 8622 N LUBAO AVE 91306

Application / Permit
23010-20000-02917
Plan Check / Job No.
B23VN09371
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan NEW 1-story 1,200 SQ. FT. DETACHED A.D.U Per Ordinance and LAMC 12.22 A33 (c)&(d).
Permit Issued
Issued on 8/24/2023
Issuing Office
Current Status
CofO Issued on 2/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/14/2023 APPLICANT
Assigned to Plan Check Engineer 7/21/2023 ZAW HAN
Corrections Issued 7/25/2023 ZAW HAN
Applicant returned to address corrections 8/15/2023 WEIJIAN HUANG
Applicant returned to address corrections 8/19/2023 ZAW HAN
Plan Check Approved 8/24/2023 ZAW HAN
Issued 8/24/2023 APPLICANT
CofO in Progress 1/24/2024 JEFFREY HARTLINE
Permit Finaled 2/14/2024 JOHN JANSON
CofO Issued 2/14/2024 JOHN JANSON
Permit Finaled 2/14/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/26/2023 FERNANDO GIL
Eng Process Fee Ord 176,300 Cleared 7/26/2023 FERNANDO GIL
Sewer availability Cleared 7/26/2023 FERNANDO GIL
Low Impact Development (LID) Cleared 8/10/2023 VICTOR MENDOZA
Roof/Waste drainage to street Cleared 8/16/2023 NIKKI ZULUETA

Contact Information

Contractor Lush Remodeling Corporation; Lic. No.: 1073605-B       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364
Engineer Melchor,, Oscar Elias; Lic. No.: NA76828       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/30/2023 Approved JEFFREY HARTLINE
Excavation/Setback/Form/Re-Bar 9/6/2023 Approved JEFFREY HARTLINE
Footing/Foundation/Slab 9/6/2023 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 9/28/2023 Approved JEFFREY HARTLINE
ELECTRICAL-Rough 10/18/2023 Corrections Issued JEFFREY HARTLINE
HVAC-Rough 10/18/2023 Partial Approval JEFFREY HARTLINE
PLUMBING-Rough 10/18/2023 Corrections Issued JEFFREY HARTLINE
Wood Frame 10/18/2023 Corrections Issued JEFFREY HARTLINE
Interior/Exterior Lathing 10/23/2023 Corrections Issued JEFFREY HARTLINE
BUILDING-Rough-Frame 10/26/2023 Approved JEFFREY HARTLINE
ELECTRICAL-Rough 10/26/2023 Approved JEFFREY HARTLINE
Green Building Rough 10/26/2023 Approved JEFFREY HARTLINE
HVAC-Rough 10/26/2023 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 10/26/2023 Approved JEFFREY HARTLINE
PLUMBING-Rough 10/26/2023 Approved JEFFREY HARTLINE
Verify Sprinkler Sign Off 10/26/2023 Approved JEFFREY HARTLINE
Insulation 10/31/2023 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 10/31/2023 Approved JEFFREY HARTLINE
Shower Pan 10/31/2023 Approved JEFFREY HARTLINE
Drywall Nailing 11/6/2023 Approved JEFFREY HARTLINE
Final 1/12/2024 Corrections Issued JEFFREY HARTLINE
Green Building Final 1/12/2024 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 1/12/2024 SGSOV No Gas JEFFREY HARTLINE
Service/Power Release 1/12/2024 Not Ready for Inspection JEFFREY HARTLINE
Smoke Detectors 1/12/2024 Approved JEFFREY HARTLINE
Service/Power Release 1/22/2024 Approved JEFFREY HARTLINE
Final 1/23/2024 OK to Issue CofO JEFFREY HARTLINE