19153 W LEMAY ST 91335

Certificate Information: 19153 W LEMAY ST 91335

Application / Permit
23010-20000-02891
Plan Check / Job No.
B23VN09187
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan New detached adu, 1001 sf all work per WFPP
Permit Issued
Issued on 11/7/2023
Issuing Office
Current Status
CofO Issued on 6/11/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/26/2023 APPLICANT
Assigned to Plan Check Engineer 8/2/2023 JOSEPH RAFOLS
Corrections Issued 8/3/2023 JOSEPH RAFOLS
Plan Check Approved 10/30/2023 JOSEPH RAFOLS
Issued 11/7/2023 APPLICANT
CofO in Progress 4/30/2024 JEFFREY BULL
Permit Finaled 6/11/2024 JOHN JANSON
CofO Issued 6/11/2024 JOHN JANSON
Permit Finaled 6/11/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/8/2023 TAL SHEMEN
ZI Cleared 8/8/2023 MAXFIELD VERMY
Sewer availability Cleared 8/10/2023 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 9/19/2023 TAL SHEMEN
Low Impact Development (LID) Cleared 10/12/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 10/12/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 11/15/2023 Not Ready for Inspection JEFFREY BULL
Special/Order Compliance 11/15/2023 Corrections Issued JEFFREY BULL
Underground Mechanical 11/15/2023 Partial Approval JEFFREY BULL
Footing/Foundation/Slab 11/28/2023 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 12/21/2023 Approved JEFFREY BULL
Rough-Elec/Plmb/HVAC 12/21/2023 Approved JEFFREY BULL
Sewer 12/28/2023 Approved JEFFREY PARD
Interior/Exterior Lathing 1/5/2024 Partial Approval JEFFREY BULL
Shower Pan 1/5/2024 Approved JEFFREY BULL
BUILDING-Rough-Frame 1/22/2024 Not Ready for Inspection JEFFREY BULL
ELECTRICAL-Rough 1/22/2024 Approved JEFFREY BULL
Green Building Rough 1/22/2024 Not Ready for Inspection JEFFREY BULL
Verify Sprinkler Sign Off 1/22/2024 Approved JEFFREY BULL
BUILDING-Rough-Frame 1/29/2024 Approved JEFFREY BULL
Green Building Rough 1/29/2024 Approved JEFFREY BULL
Insulation 1/29/2024 Corrections Issued JEFFREY BULL
Drywall Nailing 2/7/2024 Approved JEFFREY BULL
Interior/Exterior Lathing 2/7/2024 Approved JEFFREY BULL
ELECTRICAL-Final 3/22/2024 Not Ready for Inspection KRISTEN CAUSEY
PLUMBING-Final 3/22/2024 Approved KRISTEN CAUSEY
Final 4/25/2024 OK to Issue CofO JEFFREY BULL
Green Building Final 4/25/2024 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 4/25/2024 SGSOV Approved JEFFREY BULL
Service/Power Release 4/25/2024 Approved JEFFREY BULL
Smoke Detectors 4/25/2024 Approved JEFFREY BULL