14472 W GREENLEAF ST 91423

Certificate Information: 14472 W GREENLEAF ST 91423

Application / Permit
23010-20000-02889
Plan Check / Job No.
B23VN09184
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
(N) 21'2"X12'8" IRREGULAR SHAPED RECREATION ROOM WITH A POOL BATHROOM THAT HAS EXTERIOR ACCESS ONLY. <2 OF 4>
Permit Issued
Issued on 10/3/2023
Issuing Office
Valley
Current Status
CofO Issued on 10/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/11/2023 APPLICANT
Assigned to Plan Check Engineer 7/20/2023 MARVEL DELACRUZ
Corrections Issued 7/27/2023 MARVEL DELACRUZ
Quality Review Completed 7/28/2023 OMID HEDAYAT
Building Plans Picked Up 8/1/2023 APPLICANT
Applicant returned to address corrections 9/11/2023 MARVEL DELACRUZ
Applicant returned to address corrections 9/21/2023 MARVEL DELACRUZ
Plan Check Approved 10/3/2023 MARVEL DELACRUZ
Issued 10/3/2023 APPLICANT
CofO in Progress 9/27/2024 JUAN VALENZUELA
CofO Issued 10/1/2024 DANIEL ORRANTE
Permit Finaled 10/1/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/11/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 8/11/2023 DAGOVERTO GUERRERO
Construction near power lines Cleared 8/22/2023 TINA MIRANDA
Low Impact Development (LID) Cleared 8/25/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 8/28/2023 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 9/1/2023 GILBERT URREA
GPI Written Notices Cleared 10/3/2023 MARVEL DELACRUZ
Grading Pre-Inspection Cleared 10/3/2023 MARVEL DELACRUZ
Hold Cleared 10/23/2023 CARMEN MERAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21757 DEVONSHIRE ST.   SUITE 3    CANOGA PARK, CA 91311
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

DANIEL ORRANTE, (818) 374-1157 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/7/2023 Not Ready for Inspection MISAEL ESPARZA
Underground Mechanical 11/7/2023 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 11/20/2023 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 12/6/2023 Corrections Issued MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 12/11/2023 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 1/22/2024 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 1/24/2024 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 1/31/2024 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 2/14/2024 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 2/20/2024 Partial Inspection JUAN VALENZUELA
Sewer 2/20/2024 Not Ready for Inspection JUAN VALENZUELA
Shower Pan 2/20/2024 Not Ready for Inspection JUAN VALENZUELA
HVAC-Rough 3/5/2024 Approved JUAN VALENZUELA
PLUMBING-Rough 3/5/2024 Approved JUAN VALENZUELA
Sewer 3/5/2024 Not Ready for Inspection JUAN VALENZUELA
Shower Pan 3/5/2024 Approved JUAN VALENZUELA
ELECTRICAL-Rough 3/18/2024 Corrections Issued JUAN VALENZUELA
BUILDING-Rough-Frame 4/9/2024 Not Ready for Inspection JUAN VALENZUELA
ELECTRICAL-Rough 4/9/2024 Partial Approval JUAN VALENZUELA
Green Building Rough 4/9/2024 Approved JUAN VALENZUELA
Interior/Exterior Lathing 4/9/2024 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 4/15/2024 Approved JUAN VALENZUELA
Drywall Nailing 4/15/2024 Approved JUAN VALENZUELA
ELECTRICAL-Rough 4/15/2024 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 4/15/2024 Approved JUAN VALENZUELA
Insulation 4/15/2024 Approved JUAN VALENZUELA
ELECTRICAL-Final 8/12/2024 Not Ready for Inspection JUAN VALENZUELA
Service/Power Release 8/12/2024 Not Ready for Inspection JUAN VALENZUELA
ELECTRICAL-Final 8/27/2024 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Final 8/27/2024 Not Ready for Inspection JUAN VALENZUELA
Final 9/13/2024 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 9/13/2024 Approved JUAN VALENZUELA
Green Building Final 9/13/2024 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 9/13/2024 SGSOV Not Required JUAN VALENZUELA
Smoke Detectors 9/13/2024 Approved JUAN VALENZUELA
ELECTRICAL-Final 9/19/2024 Approved JUAN VALENZUELA
Final 9/19/2024 OK to Issue CofO JUAN VALENZUELA
HVAC-Final 9/19/2024 Approved JUAN VALENZUELA
PLUMBING-Final 9/19/2024 Approved JUAN VALENZUELA