16747 W HALSTED ST 91343

Certificate Information: 16747 W HALSTED ST 91343

Application / Permit
23010-20000-02885
Plan Check / Job No.
B23VN09167
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 26' 6" X 26' 3" ADU PER LAMC 12.22 A.33 (c) AND (d) ALL WORK DONE PER ENGINEERING
Permit Issued
Issued on 2/2/2024
Issuing Office
Valley
Current Status
CofO Issued on 12/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/11/2023 APPLICANT
Assigned to Plan Check Engineer 7/20/2023 NAREG ATARIAN
Corrections Issued 7/21/2023 NAREG ATARIAN
Quality Review Completed 7/21/2023 OMID HEDAYAT
Building Plans Picked Up 7/25/2023 APPLICANT
Applicant returned to address corrections 12/20/2023 NAREG ATARIAN
Plan Check Approved 1/29/2024 NAREG ATARIAN
Issued 2/2/2024 APPLICANT
CofO in Progress 12/5/2024 RAUL OLAGI
Permit Finaled 12/15/2024 RUBEN SALAS
CofO Issued 12/15/2024 RUBEN SALAS
Permit Finaled 12/15/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/25/2023 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 7/26/2023 MEGAN GODINEZ
Low Impact Development (LID) Cleared 11/20/2023 SHAHIN KHAZEY
Roof/Waste drainage to street Cleared 11/28/2023 CARLOS RAMIREZ
Sewer availability Cleared 11/28/2023 CARLOS RAMIREZ
Construction near power lines Cleared 1/16/2024 RIDWAN HARDY
GPI Written Notices Cleared 1/29/2024 BRIAN MILLER
Grading Pre-Inspection Cleared 1/29/2024 BRIAN MILLER

Contact Information

Contractor Owner-Builder       ,
Engineer Mniarji,, Majd Sameer; Lic. No.: C93049 7812 VASSAR AVENUE      CANOGA PARK, CA 91304

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/6/2024 Not Ready for Inspection RAUL OLAGI
Pre-Inspection 2/6/2024 Not Ready for Inspection RAUL OLAGI
Excavation/Setback/Form/Re-Bar 2/8/2024 Corrections Issued RAUL OLAGI
PLUMBING-Rough 2/8/2024 Conditional Approval RAUL OLAGI
Deputy Other (see comments) 2/16/2024 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 2/16/2024 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 3/5/2024 Partial Approval DAVID ANDERSON
Green Building Rough 3/5/2024 Not Ready for Inspection DAVID ANDERSON
Verify Sprinkler Sign Off 3/5/2024 Approved DAVID ANDERSON
BUILDING-Rough-Frame 3/12/2024 Corrections Issued RAUL OLAGI
PLUMBING-Rough 3/12/2024 Not Ready for Inspection RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 3/29/2024 Partial Approval RAUL OLAGI
PLUMBING-Rough 3/29/2024 Approved RAUL OLAGI
Sewer 3/29/2024 Approved RAUL OLAGI
Underground Mechanical 3/29/2024 Approved RAUL OLAGI
ELECTRICAL-Rough 4/11/2024 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 4/11/2024 Approved RAUL OLAGI
HVAC-Rough 4/11/2024 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 5/2/2024 Conditional Approval RAUL OLAGI
Green Building Rough 5/2/2024 Approved RAUL OLAGI
HVAC-Rough 5/2/2024 Partial Approval RAUL OLAGI
Interior/Exterior Lathing 5/2/2024 Partial Approval RAUL OLAGI
HVAC-Rough 5/7/2024 Approved RAUL OLAGI
Insulation 5/7/2024 Approved RAUL OLAGI
Drywall Nailing 5/13/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 6/3/2024 Approved SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 9/30/2024 SGSOV Not Ready SALVADOR MARTINEZ
BUILDING-Rough-Frame 10/1/2024 Approved RAUL OLAGI
Final 10/1/2024 Corrections Issued RAUL OLAGI
Green Building Final 10/1/2024 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 10/1/2024 SGSOV Not Required RAUL OLAGI
Smoke Detectors 10/1/2024 Approved RAUL OLAGI
Final 12/5/2024 OK to Issue CofO RAUL OLAGI