8012 N SAUSALITO AVE 91304
Certificate Information: 8012 N SAUSALITO AVE 91304
- Application / Permit
- 23010-20000-02869
- Plan Check / Job No.
- B23VN09110
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN NEW DETACHED 2-STORY 1200 SQ.FT. SB9 UNIT ** NFPA 13d sprinkler is required **
- Permit Issued
- Issued on 9/21/2024
- Issuing Office
- Current Status
- CofO Issued on 9/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/13/2023 | YASHAR EMAMI |
| Corrections Issued | 7/27/2023 | YASHAR EMAMI |
| Quality Review Completed | 8/8/2023 | KAVIAN REFAHI |
| Applicant returned to address corrections | 5/22/2024 | YASHAR EMAMI |
| Applicant returned to address corrections | 7/17/2024 | YASHAR EMAMI |
| Applicant returned to address corrections | 8/30/2024 | YASHAR EMAMI |
| Plan Check Approved | 9/20/2024 | YASHAR EMAMI |
| Issued | 9/21/2024 | APPLICANT |
| CofO in Progress | 4/11/2025 | CHRIS CHRISTENSEN |
| No Progress | 9/10/2025 | HENRY KIM |
| CofO in Progress | 9/10/2025 | HENRY KIM |
| Permit Finaled | 9/19/2025 | JOHN JANSON |
| CofO Issued | 9/19/2025 | JOHN JANSON |
| Permit Finaled | 9/19/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/25/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/26/2023 | CARLOS AGUILERA |
| Highway dedication | Cleared | 9/18/2023 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 9/18/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 9/18/2023 | CARLOS AGUILERA |
| Tenant Habitability Plan | Cleared | 9/26/2023 | RICARDO BOHORQUEZ |
| Senate Bill 9 | Cleared | 12/14/2023 | ALEX VELA |
| Hydrant and Access approval | Cleared | 4/11/2024 | JOHN CONNEALLY |
| Construction within easement | Cleared | 5/30/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/26/2024 | Partial Approval | CHRIS CHRISTENSEN |
| Pre-Inspection | 9/26/2024 | Approved | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 9/30/2024 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2024 | Partial Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2024 | Conditional Approval | CHRIS CHRISTENSEN |
| Deputy Wood Construction | 11/8/2024 | Conditional Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 12/3/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 12/3/2024 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 12/3/2024 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 12/3/2024 | Approved | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 12/3/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 12/26/2024 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 12/26/2024 | Partial Approval | CHRIS CHRISTENSEN |
| HVAC-Rough | 12/26/2024 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 12/26/2024 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 12/30/2024 | Conditional Approval | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 12/30/2024 | Partial Approval | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 12/30/2024 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 1/3/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Insulation | 1/3/2025 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 1/3/2025 | Partial Approval | JEFFREY HARTLINE |
| Shower Pan | 1/3/2025 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 1/7/2025 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Final | 2/11/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| HVAC-Final | 2/11/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| PLUMBING-Final | 2/11/2025 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 2/24/2025 | No Access for Inspection | CHRIS CHRISTENSEN |
| Final | 2/24/2025 | No Access for Inspection | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 2/24/2025 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Service/Power Release | 2/24/2025 | No Access for Inspection | CHRIS CHRISTENSEN |
| Smoke Detectors | 2/24/2025 | No Access for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 3/6/2025 | Approved | CHRIS CHRISTENSEN |
| Final | 3/6/2025 | Corrections Issued | CHRIS CHRISTENSEN |
| HVAC-Final | 3/6/2025 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 3/6/2025 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 3/6/2025 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 3/11/2025 | Approved | CHRIS CHRISTENSEN |
| Final | 3/11/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Service/Power Release | 3/11/2025 | Approved | CHRIS CHRISTENSEN |
| Final | 4/10/2025 | OK to Issue CofO | CHRIS CHRISTENSEN |