6061 S RAYMOND AVE 90044

Certificate Information: 6061 S RAYMOND AVE 90044

Application / Permit
23010-20000-02853
Plan Check / Job No.
B23VN09042
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
****ePlan**** New 2-story Duplex w./ att. 2-car garage
Permit Issued
Issued on 12/18/2023
Issuing Office
Current Status
CofO Issued on 7/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/7/2023 APPLICANT
Assigned to Plan Check Engineer 7/13/2023 REZA HAGHIGHAT
Corrections Issued 7/15/2023 REZA HAGHIGHAT
Quality Review Completed 7/25/2023 KAVIAN REFAHI
Plan Check Approved 12/11/2023 REZA HAGHIGHAT
Issued 12/18/2023 APPLICANT
CofO in Progress 7/27/2024 ALEJANDRO DE ARTOLA
Permit Finaled 7/29/2024 DEROLD HAUFF
CofO Issued 7/29/2024 DEROLD HAUFF
Permit Finaled 7/29/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/5/2023 MSTAFA AL-MSARI
Eng Process Fee Ord 176,300 Cleared 8/9/2023 MSTAFA AL-MSARI
Hydrant and Access approval Cleared 9/7/2023 MATTHEW CRAIG
Low Impact Development (LID) Cleared 10/19/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 11/7/2023 ADRIAN SANCHEZ
Sewer availability Cleared 11/7/2023 ADRIAN SANCHEZ
SB8 RUD Cleared 11/13/2023 MARY ARCENA

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/19/2024 Conditional Approval RONNIE MINDANAO
Underground Mechanical 2/14/2024 Partial Approval RONNIE MINDANAO
Wood Frame 2/14/2024 Partial Approval RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 2/15/2024 Partial Approval RONNIE MINDANAO
Insulation 2/15/2024 Partial Approval RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 2/16/2024 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 2/20/2024 Not Ready for Inspection BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 2/21/2024 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/4/2024 Corrections Issued RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 3/22/2024 Approved CRAIG DAVIS
HVAC-Rough 4/10/2024 Approved JOSEPH MCGARRY
PLUMBING-Rough 4/10/2024 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 4/12/2024 Corrections Issued CRAIG DAVIS
ELECTRICAL-Rough 4/12/2024 Corrections Issued CRAIG DAVIS
Verify Sprinkler Sign Off 4/12/2024 Not Ready for Inspection CRAIG DAVIS
BUILDING-Rough-Frame 4/16/2024 Partial Approval CRAIG DAVIS
ELECTRICAL-Rough 4/16/2024 Partial Approval CRAIG DAVIS
Verify Sprinkler Sign Off 4/16/2024 Approved CRAIG DAVIS
Insulation 4/19/2024 Approved CRAIG DAVIS
ELECTRICAL-Rough 4/25/2024 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 5/2/2024 Approved CRAIG DAVIS
Interior/Exterior Lathing 5/2/2024 Approved CRAIG DAVIS
ELECTRICAL-Final 6/14/2024 Conditional Approval SABAS ALONSO
BUILDING-Rough-Frame 7/25/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 7/25/2024 Corrections Issued ALEJANDRO DE ARTOLA
Final 7/25/2024 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 7/25/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Final 7/25/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 7/25/2024 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 7/25/2024 SGSOV Not Required ALEJANDRO DE ARTOLA
Service/Power Release 7/25/2024 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 7/25/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 7/26/2024 Approved ALEJANDRO DE ARTOLA
Final 7/26/2024 OK to Issue CofO ALEJANDRO DE ARTOLA
HVAC-Final 7/26/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 7/26/2024 Approved ALEJANDRO DE ARTOLA
Service/Power Release 7/26/2024 Approved ALEJANDRO DE ARTOLA