6061 S RAYMOND AVE 90044
Certificate Information: 6061 S RAYMOND AVE 90044
- Application / Permit
- 23010-20000-02853
- Plan Check / Job No.
- B23VN09042
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ****ePlan**** New 2-story Duplex w./ att. 2-car garage
- Permit Issued
- Issued on 12/18/2023
- Issuing Office
- Current Status
- CofO Issued on 7/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/13/2023 | REZA HAGHIGHAT |
| Corrections Issued | 7/15/2023 | REZA HAGHIGHAT |
| Quality Review Completed | 7/25/2023 | KAVIAN REFAHI |
| Plan Check Approved | 12/11/2023 | REZA HAGHIGHAT |
| Issued | 12/18/2023 | APPLICANT |
| CofO in Progress | 7/27/2024 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 7/29/2024 | DEROLD HAUFF |
| CofO Issued | 7/29/2024 | DEROLD HAUFF |
| Permit Finaled | 7/29/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/5/2023 | MSTAFA AL-MSARI |
| Eng Process Fee Ord 176,300 | Cleared | 8/9/2023 | MSTAFA AL-MSARI |
| Hydrant and Access approval | Cleared | 9/7/2023 | MATTHEW CRAIG |
| Low Impact Development (LID) | Cleared | 10/19/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 11/7/2023 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 11/7/2023 | ADRIAN SANCHEZ |
| SB8 RUD | Cleared | 11/13/2023 | MARY ARCENA |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/19/2024 | Conditional Approval | RONNIE MINDANAO |
| Underground Mechanical | 2/14/2024 | Partial Approval | RONNIE MINDANAO |
| Wood Frame | 2/14/2024 | Partial Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2024 | Partial Approval | RONNIE MINDANAO |
| Insulation | 2/15/2024 | Partial Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2024 | Corrections Issued | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2024 | Approved | CRAIG DAVIS |
| HVAC-Rough | 4/10/2024 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 4/10/2024 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 4/12/2024 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Rough | 4/12/2024 | Corrections Issued | CRAIG DAVIS |
| Verify Sprinkler Sign Off | 4/12/2024 | Not Ready for Inspection | CRAIG DAVIS |
| BUILDING-Rough-Frame | 4/16/2024 | Partial Approval | CRAIG DAVIS |
| ELECTRICAL-Rough | 4/16/2024 | Partial Approval | CRAIG DAVIS |
| Verify Sprinkler Sign Off | 4/16/2024 | Approved | CRAIG DAVIS |
| Insulation | 4/19/2024 | Approved | CRAIG DAVIS |
| ELECTRICAL-Rough | 4/25/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 5/2/2024 | Approved | CRAIG DAVIS |
| Interior/Exterior Lathing | 5/2/2024 | Approved | CRAIG DAVIS |
| ELECTRICAL-Final | 6/14/2024 | Conditional Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 7/25/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 7/25/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 7/25/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 7/25/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 7/25/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 7/25/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 7/25/2024 | SGSOV Not Required | ALEJANDRO DE ARTOLA |
| Service/Power Release | 7/25/2024 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 7/25/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 7/26/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 7/26/2024 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| HVAC-Final | 7/26/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 7/26/2024 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 7/26/2024 | Approved | ALEJANDRO DE ARTOLA |