- Permit Issued
- Issued on 12/28/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/13/2023 | PETER MOSESIAN |
| Corrections Issued | 7/15/2023 | PETER MOSESIAN |
| Quality Review Completed | 7/21/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 7/25/2023 | APPLICANT |
| Plan Check Approved | 10/6/2023 | PETER MOSESIAN |
| Issued | 12/28/2023 | APPLICANT |
| CofO in Progress | 1/29/2025 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 2/11/2025 | DEROLD HAUFF |
| CofO Issued | 2/11/2025 | DEROLD HAUFF |
| Permit Finaled | 2/11/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| "Q" conditions | Cleared | 7/26/2023 | JASON CHAN |
| Address approval | Cleared | 7/26/2023 | WALLIE JONG |
| ZI | Cleared | 7/26/2023 | JASON CHAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/27/2023 | WALLIE JONG |
| Sewer availability | Cleared | 7/27/2023 | WALLIE JONG |
| Low Impact Development (LID) | Cleared | 9/5/2023 | SHAHIN KHAZEY |
| Roof/Waste drainage to street | Cleared | 9/8/2023 | AMBER CAMPBELL |
| HPOZ | Cleared | 9/26/2023 | MELISSA JONES |
| Historic monument | Cleared | 9/26/2023 | MELISSA JONES |
| ZI | Cleared | 9/26/2023 | MELISSA JONES |
Contact Information
| Architect | Nigosian,, Michael Nickolas; Lic. No.: C35308 | 75-572 PAINTED DESERT DRIVE INDIAN WELLS, CA 92210 |
| Contractor | Marcin Corporation; Lic. No.: 1023109-B | 4433 EAGLE ROCK BLVD #406 LOS ANGELES, CA 90041 |
| Engineer | Aboufadel,, Nicholas Fadlo; Lic. No.: C50588 | 4000 PARK NEWPORT SUITE 303 NEWPORT BEACH, CA 92660 |
| Engineer | Boranian,, Paul; Lic. No.: S5944 | 23261 BURBANK BL WOODLAND HILLS, CA 91367 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/21/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 2/21/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 2/22/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 2/22/2024 | Approved | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 2/24/2024 | Corrections Issued | WILLIAM WREN |
| PLUMBING-Rough | 2/24/2024 | Not Ready for Inspection | WILLIAM WREN |
| Underground Mechanical | 2/24/2024 | Not Ready for Inspection | WILLIAM WREN |
| Footing/Foundation/Slab | 2/27/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 3/1/2024 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 3/7/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 3/11/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| METHANE-Barrier | 3/11/2024 | Approved | ALEJANDRO DE ARTOLA |
| METHANE-Subgrade | 3/11/2024 | Approved | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 3/15/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 3/19/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 3/20/2024 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 3/20/2024 | Approved | ALEJANDRO DE ARTOLA |
| Deputy Reinf. Concrete | 3/22/2024 | Conditional Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 4/5/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 5/17/2024 | Conditional Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 5/28/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Green Building Rough | 5/28/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| METHANE-Rough | 5/28/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 5/28/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 5/28/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 5/30/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 5/30/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 5/31/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| ELECTRICAL-Rough | 6/3/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 6/14/2024 | Approved | BRENDAN MORELLI |
| HVAC-Rough | 6/14/2024 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 6/14/2024 | Partial Approval | BRENDAN MORELLI |
| METHANE-Rough | 6/14/2024 | Approved | BRENDAN MORELLI |
| PLUMBING-Rough | 6/14/2024 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 6/18/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 6/18/2024 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 6/28/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 6/28/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 7/1/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 7/1/2024 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 7/3/2024 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 7/5/2024 | Approved | JUSTIN HAWLEY |
| PLUMBING-Rough | 7/9/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Sewer | 7/9/2024 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 7/9/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 8/1/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 8/1/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 8/1/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 8/1/2024 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 8/1/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 8/6/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 8/7/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 8/22/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 8/22/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 10/21/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 10/21/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 10/21/2024 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 10/21/2024 | SGSOV Not Required | ALEJANDRO DE ARTOLA |
| Service/Power Release | 10/21/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 12/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| METHANE-Final | 12/23/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 12/23/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 1/29/2025 | OK to Issue CofO | ALEJANDRO DE ARTOLA |