372 1/2-3/4 E 52ND ST 90011

Certificate Information: 372 1/2-3/4 E 52ND ST 90011

Application / Permit
23010-20000-02795
Plan Check / Job No.
B23VN08856
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
eplan NEW 2-TWO STORY DUPLEX AT REAR LOT NFPA 13D SPRINKLERED THROUGH OUT
Permit Issued
Issued on 12/19/2024
Issuing Office
Current Status
Issued on 12/19/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/5/2023 APPLICANT
Assigned to Plan Check Engineer 7/6/2023 JAD BASMA
Corrections Issued 7/8/2023 JAD BASMA
Quality Review Completed 7/20/2023 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 11/3/2023 JAD BASMA
Plan Check Approved 12/16/2024 JAD BASMA
Issued 12/19/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/8/2023 WALLIE JONG
Highway dedication Cleared 8/8/2023 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 8/10/2023 WALLIE JONG
Sewer availability Cleared 8/10/2023 WALLIE JONG
Frnt yard landscape/Water mgmt Cleared 8/28/2023 DAVID URITA
Low Impact Development (LID) Cleared 10/4/2023 ERNEST TSE
Hydrant and Access approval Cleared 10/6/2023 KURT CORRAL
Roof/Waste drainage to street Cleared 10/26/2023 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/5/2025 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 2/24/2025 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/7/2025 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/21/2025 Partial Approval ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 4/1/2025 Approved MICHAEL LEWIS
Rough-Elec/Plmb/HVAC 4/1/2025 Corrections Issued MICHAEL LEWIS
Interior/Exterior Lathing 4/4/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 4/7/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 4/7/2025 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 4/8/2025 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 4/9/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 4/9/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 4/9/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 4/9/2025 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 4/18/2025 Approved MICHAEL LEWIS
Green Building Rough 4/18/2025 Approved MICHAEL LEWIS
HVAC-Rough 4/18/2025 Approved MICHAEL LEWIS
Insulation 4/18/2025 Approved MICHAEL LEWIS
Verify Sprinkler Sign Off 4/18/2025 Approved MICHAEL LEWIS
Drywall Nailing 4/28/2025 Approved ANTHONY RAMOS
Underground Mechanical 6/24/2025 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 6/27/2025 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 7/1/2025 Partial Approval LUIS CASTRO