8413-8413 1/2 N LIMERICK AVE 91306
Certificate Information: 8413-8413 1/2 N LIMERICK AVE 91306
- Application / Permit
- 23010-20000-02788
- Plan Check / Job No.
- B23VN08827
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- DETACHED (2) ACCESSORY DWELLING UNITS PER GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33(c), (d), and (g)
- Permit Issued
- Issued on 8/11/2023
- Issuing Office
- Current Status
- CofO Issued on 3/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/6/2023 | SELLA BENYAMIN |
| Corrections Issued | 7/11/2023 | SELLA BENYAMIN |
| Quality Review Completed | 7/13/2023 | STEVEN KIM |
| Building Plans Picked Up | 7/14/2023 | APPLICANT |
| Plan Check Approved | 8/11/2023 | SELLA BENYAMIN |
| Issued | 8/11/2023 | APPLICANT |
| CofO in Progress | 1/9/2024 | JEFFREY HARTLINE |
| CofO Issued | 3/21/2024 | JOHN JANSON |
| Permit Finaled | 3/21/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/25/2023 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/25/2023 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 7/25/2023 | ROMAN GUTIERREZ |
| Low Impact Development (LID) | Cleared | 7/28/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 7/28/2023 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 8/31/2023 | Approved | JEFFREY HARTLINE |
| Excavation/Setback/Form/Re-Bar | 9/7/2023 | Approved | JEFFREY HARTLINE |
| Special/Order Compliance | 9/21/2023 | Corrections Issued | JEFFREY HARTLINE |
| Special/Order Compliance | 10/11/2023 | Corrections Issued | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 10/13/2023 | Partial Approval | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2023 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 10/13/2023 | Not Ready for Inspection | JEFFREY HARTLINE |
| HVAC-Rough | 10/13/2023 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 10/13/2023 | Corrections Issued | JEFFREY HARTLINE |
| Verify Sprinkler Sign Off | 10/13/2023 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 10/18/2023 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 10/18/2023 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 10/18/2023 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 10/18/2023 | Approved | JEFFREY HARTLINE |
| Shower Pan | 10/18/2023 | Approved | JEFFREY HARTLINE |
| Insulation | 10/23/2023 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 10/23/2023 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 10/30/2023 | Corrections Issued | JEFFREY HARTLINE |
| ELECTRICAL-Final | 12/11/2023 | Corrections Issued | JEFFREY HARTLINE |
| Final | 12/11/2023 | Corrections Issued | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 12/11/2023 | Approved | JEFFREY HARTLINE |
| Green Building Final | 12/11/2023 | Corrections Issued | JEFFREY HARTLINE |
| HVAC-Final | 12/11/2023 | Corrections Issued | JEFFREY HARTLINE |
| PLUMBING-Final | 12/11/2023 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 12/11/2023 | SGSOV Approved | JEFFREY HARTLINE |
| Service/Power Release | 12/11/2023 | Not Ready for Inspection | JEFFREY HARTLINE |
| Smoke Detectors | 12/11/2023 | Corrections Issued | JEFFREY HARTLINE |
| Final | 12/18/2023 | Corrections Issued | JEFFREY HARTLINE |
| Green Building Final | 12/18/2023 | Approved | JEFFREY HARTLINE |
| Service/Power Release | 12/18/2023 | Not Ready for Inspection | JEFFREY HARTLINE |
| Smoke Detectors | 12/18/2023 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Final | 12/29/2023 | Not Ready for Inspection | MORRIS JACKSON |
| Final | 12/29/2023 | Corrections Issued | MORRIS JACKSON |
| Service/Power Release | 12/29/2023 | Not Ready for Inspection | MORRIS JACKSON |
| Final | 1/4/2024 | Corrections Issued | JEFFREY HARTLINE |
| Service/Power Release | 1/4/2024 | Approved | JEFFREY HARTLINE |
| Final | 1/8/2024 | OK to Issue CofO | JEFFREY HARTLINE |