8413-8413 1/2 N LIMERICK AVE 91306

Certificate Information: 8413-8413 1/2 N LIMERICK AVE 91306

Application / Permit
23010-20000-02788
Plan Check / Job No.
B23VN08827
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
DETACHED (2) ACCESSORY DWELLING UNITS PER GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33(c), (d), and (g)
Permit Issued
Issued on 8/11/2023
Issuing Office
Current Status
CofO Issued on 3/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/3/2023 APPLICANT
Assigned to Plan Check Engineer 7/6/2023 SELLA BENYAMIN
Corrections Issued 7/11/2023 SELLA BENYAMIN
Quality Review Completed 7/13/2023 STEVEN KIM
Building Plans Picked Up 7/14/2023 APPLICANT
Plan Check Approved 8/11/2023 SELLA BENYAMIN
Issued 8/11/2023 APPLICANT
CofO in Progress 1/9/2024 JEFFREY HARTLINE
CofO Issued 3/21/2024 JOHN JANSON
Permit Finaled 3/21/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/25/2023 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 7/25/2023 ROMAN GUTIERREZ
Sewer availability Cleared 7/25/2023 ROMAN GUTIERREZ
Low Impact Development (LID) Cleared 7/28/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 7/28/2023 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/31/2023 Approved JEFFREY HARTLINE
Excavation/Setback/Form/Re-Bar 9/7/2023 Approved JEFFREY HARTLINE
Special/Order Compliance 9/21/2023 Corrections Issued JEFFREY HARTLINE
Special/Order Compliance 10/11/2023 Corrections Issued JEFFREY HARTLINE
ELECTRICAL-Rough 10/13/2023 Partial Approval JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 10/13/2023 Approved JEFFREY HARTLINE
Green Building Rough 10/13/2023 Not Ready for Inspection JEFFREY HARTLINE
HVAC-Rough 10/13/2023 Approved JEFFREY HARTLINE
PLUMBING-Rough 10/13/2023 Corrections Issued JEFFREY HARTLINE
Verify Sprinkler Sign Off 10/13/2023 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 10/18/2023 Approved JEFFREY HARTLINE
ELECTRICAL-Rough 10/18/2023 Approved JEFFREY HARTLINE
Green Building Rough 10/18/2023 Approved JEFFREY HARTLINE
PLUMBING-Rough 10/18/2023 Approved JEFFREY HARTLINE
Shower Pan 10/18/2023 Approved JEFFREY HARTLINE
Insulation 10/23/2023 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 10/23/2023 Approved JEFFREY HARTLINE
Drywall Nailing 10/30/2023 Corrections Issued JEFFREY HARTLINE
ELECTRICAL-Final 12/11/2023 Corrections Issued JEFFREY HARTLINE
Final 12/11/2023 Corrections Issued JEFFREY HARTLINE
Footing/Foundation/Slab 12/11/2023 Approved JEFFREY HARTLINE
Green Building Final 12/11/2023 Corrections Issued JEFFREY HARTLINE
HVAC-Final 12/11/2023 Corrections Issued JEFFREY HARTLINE
PLUMBING-Final 12/11/2023 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 12/11/2023 SGSOV Approved JEFFREY HARTLINE
Service/Power Release 12/11/2023 Not Ready for Inspection JEFFREY HARTLINE
Smoke Detectors 12/11/2023 Corrections Issued JEFFREY HARTLINE
Final 12/18/2023 Corrections Issued JEFFREY HARTLINE
Green Building Final 12/18/2023 Approved JEFFREY HARTLINE
Service/Power Release 12/18/2023 Not Ready for Inspection JEFFREY HARTLINE
Smoke Detectors 12/18/2023 Approved JEFFREY HARTLINE
ELECTRICAL-Final 12/29/2023 Not Ready for Inspection MORRIS JACKSON
Final 12/29/2023 Corrections Issued MORRIS JACKSON
Service/Power Release 12/29/2023 Not Ready for Inspection MORRIS JACKSON
Final 1/4/2024 Corrections Issued JEFFREY HARTLINE
Service/Power Release 1/4/2024 Approved JEFFREY HARTLINE
Final 1/8/2024 OK to Issue CofO JEFFREY HARTLINE