16653 W BERMUDA ST 91344

Certificate Information: 16653 W BERMUDA ST 91344

Application / Permit
23010-20000-02779
Plan Check / Job No.
B23VN08809
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 29'6"X20'0" 2-STORY SFD PER SB9 TWO-UNIT DEVELOPMENT CA GOVT CODE 65852.21 NFPA 13 D FIRE SPRINKLERS REQUIRED THROUGHOUT {ALL ELECTRIC BUILDING}
Permit Issued
Issued on 5/16/2024
Issuing Office
Current Status
CofO Issued on 4/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/3/2023 APPLICANT
Assigned to Plan Check Engineer 7/6/2023 MARVEL DELACRUZ
Corrections Issued 7/8/2023 MARVEL DELACRUZ
Quality Review Completed 7/12/2023 OMID HEDAYAT
Building Plans Picked Up 7/14/2023 APPLICANT
Applicant returned to address corrections 5/14/2024 MARVEL DELACRUZ
Plan Check Approved 5/16/2024 MARVEL DELACRUZ
Issued 5/16/2024 APPLICANT
CofO in Progress 3/14/2025 JAVIER RAMOS JR
Permit Finaled 4/1/2025 RUBEN SALAS
CofO Issued 4/1/2025 RUBEN SALAS
Permit Finaled 4/1/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/19/2023 RYAN KIM
Eng Process Fee Ord 176,300 Cleared 7/21/2023 RYAN KIM
Sewer availability Cleared 7/21/2023 RYAN KIM
Low Impact Development (LID) Cleared 7/24/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 7/24/2023 RYAN KIM
Senate Bill 9 Cleared 12/28/2023 BRENNEN OBETO
Hydrant and Access approval Cleared 2/5/2024 KURT CORRAL

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/28/2024 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 9/9/2024 Partial Inspection MICHEL ABAJAN
Footing/Foundation/Slab 9/16/2024 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 9/25/2024 Approved LOUIS ESCOTO
Floor/Roof Diaphrgm/Shear Wall 10/8/2024 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 10/8/2024 Partial Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 11/6/2024 Partial Inspection JAVIER RAMOS JR
Footing/Foundation/Slab 11/6/2024 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Rough 11/6/2024 Partial Inspection JAVIER RAMOS JR
PLUMBING-Rough 11/6/2024 Partial Inspection JAVIER RAMOS JR
Verify Sprinkler Sign Off 11/6/2024 Approved JAVIER RAMOS JR
Insulation 11/14/2024 Corrections Issued JAVIER RAMOS JR
Drywall Nailing 11/25/2024 Partial Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 11/25/2024 Approved JAVIER RAMOS JR
Green Building Rough 11/25/2024 Approved JAVIER RAMOS JR
Insulation 11/25/2024 Approved JAVIER RAMOS JR
Gas Test 12/2/2024 Not Ready for Inspection MICHAEL CORTEZ
Interior/Exterior Lathing 12/2/2024 Not Ready for Inspection MICHAEL CORTEZ
Shower Pan 12/2/2024 Corrections Issued MICHAEL CORTEZ
Interior/Exterior Lathing 12/9/2024 Approved LOUIS ESCOTO
Shower Pan 12/9/2024 Approved LOUIS ESCOTO
Sewer 1/13/2025 Approved JAVIER RAMOS JR
Underground Mechanical 1/13/2025 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 2/28/2025 Approved JAVIER RAMOS JR
Drywall Nailing 2/28/2025 Approved JAVIER RAMOS JR
Final 2/28/2025 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 2/28/2025 Approved JAVIER RAMOS JR
Green Building Final 2/28/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 2/28/2025 SGSOV Not Required JAVIER RAMOS JR
Service/Power Release 2/28/2025 Approved JAVIER RAMOS JR
Smoke Detectors 2/28/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Final 3/14/2025 Approved JAVIER RAMOS JR
Final 3/14/2025 OK to Issue CofO JAVIER RAMOS JR
HVAC-Final 3/14/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 3/14/2025 Approved JAVIER RAMOS JR