6913 N LARAMIE AVE 91306
Certificate Information: 6913 N LARAMIE AVE 91306
- Application / Permit
- 23010-20000-02774
- Plan Check / Job No.
- B23VN08797
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW (30'-0"x20'-0"), 1180 SQFT 2-STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)(d)
- Permit Issued
- Issued on 1/8/2024
- Issuing Office
- Current Status
- CofO Issued on 6/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/20/2023 | PETER MOSESIAN |
| Corrections Issued | 7/23/2023 | PETER MOSESIAN |
| Quality Review Completed | 7/25/2023 | OMID HEDAYAT |
| Plan Check Approved | 1/3/2024 | PETER MOSESIAN |
| Issued | 1/8/2024 | APPLICANT |
| CofO in Progress | 4/29/2025 | ALEXANDER HANDY |
| CofO in Progress | 5/30/2025 | ROBERT GOLD |
| CofO in Progress | 5/30/2025 | ROBERT GOLD |
| Permit Finaled | 6/5/2025 | JOHN JANSON |
| CofO Issued | 6/5/2025 | JOHN JANSON |
| Permit Finaled | 6/5/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/26/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 7/26/2023 | DAGOVERTO GUERRERO |
| ZI | Cleared | 7/28/2023 | BRENNEN OBETO |
| Hydrant and Access approval | Cleared | 9/1/2023 | MATTHEW CRAIG |
| Low Impact Development (LID) | Cleared | 11/13/2023 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 11/15/2023 | BRYAN GODINEZ |
| Construction near power lines | Cleared | 12/19/2023 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Arakelyan,, Aram; Lic. No.: C82796 | 145 S GLENOAKS BI 328 BURBANK, CA 91502 |
| Engineer | Zhang,, Zhiqiang; Lic. No.: M34617 | 410 S SAN GABRIEL BLVD #8 SAN GABRIEL, CA 91776 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/19/2024 | Partial Approval | ARUTYUN MADATYAN |
| Excavation/Setback/Form/Re-Bar | 4/24/2024 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2024 | Partial Approval | ARUTYUN MADATYAN |
| Verify Sprinkler Sign Off | 5/6/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Deputy Wood Construction | 5/16/2024 | Conditional Approval | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2024 | Corrections Issued | ARUTYUN MADATYAN |
| Verify Sprinkler Sign Off | 5/16/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 5/20/2024 | Partial Approval | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 5/22/2024 | Partial Approval | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 6/27/2024 | Corrections Issued | ARUTYUN MADATYAN |
| PLUMBING-Rough | 6/27/2024 | Corrections Issued | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 7/1/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Insulation | 10/4/2024 | Corrections Issued | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 10/8/2024 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 10/8/2024 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 10/8/2024 | Approved | ARUTYUN MADATYAN |
| Insulation | 10/8/2024 | Conditional Approval | ARUTYUN MADATYAN |
| PLUMBING-Rough | 10/8/2024 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 10/9/2024 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 10/9/2024 | Partial Approval | ARUTYUN MADATYAN |
| Shower Pan | 10/9/2024 | Approved | ARUTYUN MADATYAN |
| Final | 1/27/2025 | Corrections Issued | ALEXANDER HANDY |
| Footing/Foundation/Slab | 1/27/2025 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 1/27/2025 | SGSOV Not Ready | ALEXANDER HANDY |
| Service/Power Release | 1/27/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Smoke Detectors | 1/27/2025 | Approved | ALEXANDER HANDY |
| Final | 2/3/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 2/3/2025 | SGSOV Approved | ALEXANDER HANDY |
| Service/Power Release | 2/3/2025 | Not Required | ALEXANDER HANDY |
| Final | 4/17/2025 | Corrections Issued | ALEXANDER HANDY |
| ELECTRICAL-Final | 4/28/2025 | Approved | ALEXANDER HANDY |
| Final | 4/28/2025 | OK to Issue CofO | ALEXANDER HANDY |
| HVAC-Final | 4/28/2025 | Approved | ALEXANDER HANDY |