18653 W COHASSET ST 91335
Certificate Information: 18653 W COHASSET ST 91335
- Application / Permit
- 23010-20000-02772
- Plan Check / Job No.
- B23VN08789
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. New 1-story detached accessory dwelling unit with entry Porch per LAMC 12.22 A.33(c)-(d). All work per WFPP.
- Permit Issued
- Issued on 11/2/2023
- Issuing Office
- Current Status
- CofO Issued on 8/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2023 | VICTOR CHEN |
| Corrections Issued | 7/9/2023 | VICTOR CHEN |
| Applicant returned to address corrections | 10/19/2023 | ZAW HAN |
| Plan Check Approved | 10/30/2023 | KEVIN MORALES |
| Issued | 11/2/2023 | APPLICANT |
| CofO in Progress | 7/10/2024 | JEFFREY BULL |
| Permit Finaled | 8/7/2024 | JOHN JANSON |
| CofO Issued | 8/7/2024 | JOHN JANSON |
| Permit Finaled | 8/7/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/19/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/1/2023 | MEGAN GODINEZ |
| Sewer availability | Cleared | 9/1/2023 | MEGAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 10/25/2023 | COLIN LOREDO |
Contact Information
| Contractor | Southeast Home Builders Inc; Lic. No.: 1055627-B | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/9/2023 | Approved | MORRIS JACKSON |
| Excavation/Setback/Form/Re-Bar | 11/29/2023 | Partial Approval | JEFFREY BULL |
| PLUMBING-Rough | 11/29/2023 | Partial Approval | JEFFREY BULL |
| Special/Order Compliance | 11/29/2023 | Corrections Issued | JEFFREY BULL |
| Sewer | 12/1/2023 | Not Ready for Inspection | JEFFREY BULL |
| Sewer | 12/11/2023 | Approved | HENRY KIM |
| Footing/Foundation/Slab | 12/13/2023 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2023 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 1/12/2024 | Not Ready for Inspection | JEFFREY BULL |
| ELECTRICAL-Rough | 1/12/2024 | Approved | JEFFREY BULL |
| Green Building Rough | 1/12/2024 | Approved | JEFFREY BULL |
| HVAC-Rough | 1/12/2024 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 1/12/2024 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 1/12/2024 | Approved | JEFFREY BULL |
| Shower Pan | 1/12/2024 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 1/19/2024 | Partial Approval | JEFFREY BULL |
| Insulation | 1/19/2024 | Approved | JEFFREY BULL |
| Drywall Nailing | 1/25/2024 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 4/25/2024 | Approved | JEFFREY BULL |
| ELECTRICAL-Final | 4/25/2024 | Approved | JEFFREY BULL |
| Final | 4/25/2024 | Corrections Issued | JEFFREY BULL |
| HVAC-Final | 4/25/2024 | Not Ready for Inspection | JEFFREY BULL |
| PLUMBING-Final | 4/25/2024 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 4/25/2024 | SGSOV Not Required | JEFFREY BULL |
| Service/Power Release | 4/25/2024 | Not Required | JEFFREY BULL |
| Smoke Detectors | 4/25/2024 | Approved | JEFFREY BULL |
| Verify Sprinkler Sign Off | 4/25/2024 | Approved | JEFFREY BULL |
| Final | 6/20/2024 | Not Ready for Inspection | JEFFREY BULL |
| Final | 7/10/2024 | OK to Issue CofO | JEFFREY BULL |