9700-9702 N RATHBURN AVE 91325

Certificate Information: 9700-9702 N RATHBURN AVE 91325

Application / Permit
23010-20000-02763
Plan Check / Job No.
B23VN08753
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Two one story detached ADUs per CA Govt. Code 65852.2(e)(1)(D) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g). work per Engineer """NFPA-13D FIRE SPRINKLERS THROUGHOUT""". SEE COMMENTS.
Permit Issued
Issued on 11/7/2023
Issuing Office
Current Status
CofO Issued on 5/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/30/2023 APPLICANT
Assigned to Plan Check Engineer 7/6/2023 RAMA DABADGE
Corrections Issued 7/10/2023 RAMA DABADGE
Building Plans Picked Up 7/12/2023 APPLICANT
Plan Check Approved 11/7/2023 SARKIS HARABEDIAN
Issued 11/7/2023 APPLICANT
CofO in Progress 5/6/2024 DAVID SCANTLIN
CofO Issued 5/17/2024 JOHN JANSON
Permit Finaled 5/17/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/24/2023 TAL SHEMEN
Permit Cleared 7/24/2023 TAL SHEMEN
Sewer availability Cleared 7/25/2023 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 7/26/2023 TAL SHEMEN
Hydrant and Access approval Cleared 8/25/2023 GILBERT URREA
Low Impact Development (LID) Cleared 8/30/2023 VICTOR MENDOZA
Roof/Waste drainage to street Cleared 9/1/2023 JOHN LIN
Trees in Parkway Cleared 9/20/2023 ADALBERTO VERA
Construction near power lines Cleared 11/4/2023 RIDWAN HARDY

Contact Information

Architect Lee,, Kenneth David; Lic. No.: C10141 16501 ACADEMIA DRIVE      ENCINO, CA 91436
Contractor Owner-Builder       ,
Engineer Adams,, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/27/2023 Approved DAVID SCANTLIN
Special/Order Compliance 11/27/2023 Partial Inspection HORACE FULTZ
PLUMBING-Rough 12/5/2023 Partial Approval DAVID SCANTLIN
Footing/Foundation/Slab 12/8/2023 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 1/18/2024 Approved DAVID SCANTLIN
Deputy Wood Construction 1/19/2024 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 2/8/2024 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 2/8/2024 Approved DAVID SCANTLIN
Green Building Rough 2/8/2024 Not Ready for Inspection DAVID SCANTLIN
HVAC-Rough 2/8/2024 Approved DAVID SCANTLIN
PLUMBING-Rough 2/8/2024 Approved DAVID SCANTLIN
Verify Sprinkler Sign Off 2/8/2024 Not Ready for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 2/15/2024 Approved KRISTEN CAUSEY
Green Building Rough 2/15/2024 Approved KRISTEN CAUSEY
Insulation 2/15/2024 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 2/15/2024 Partial Approval KRISTEN CAUSEY
Shower Pan 2/15/2024 Approved KRISTEN CAUSEY
Verify Sprinkler Sign Off 2/15/2024 Approved KRISTEN CAUSEY
Drywall Nailing 2/22/2024 Approved DAVID SCANTLIN
Interior/Exterior Lathing 2/22/2024 Approved DAVID SCANTLIN
Special/Order Compliance 3/12/2024 Approved DAVID SCANTLIN
ELECTRICAL-Final 4/29/2024 Not Ready for Inspection KRISTEN CAUSEY
HVAC-Final 4/29/2024 Approved KRISTEN CAUSEY
PLUMBING-Final 4/29/2024 Approved KRISTEN CAUSEY
Final 5/3/2024 OK to Issue CofO DAVID SCANTLIN
Green Building Final 5/3/2024 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 5/3/2024 SGSOV Approved DAVID SCANTLIN
Service/Power Release 5/3/2024 Approved DAVID SCANTLIN
Smoke Detectors 5/3/2024 Approved DAVID SCANTLIN