23247 W CALVERT ST 91367
Certificate Information: 23247 W CALVERT ST 91367
- Application / Permit
- 23010-20000-02752
- Plan Check / Job No.
- B23VN08706
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan PROPOSED 2-STORY DETACHED ADU ADU CHECKED PER LAMC 12.22 A.33 (C)-(D)
- Permit Issued
- Issued on 2/29/2024
- Issuing Office
- Current Status
- CofO Issued on 3/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/13/2023 | SUNMIN LEE |
| Corrections Issued | 7/14/2023 | SUNMIN LEE |
| Quality Review Completed | 7/14/2023 | GARO TELMI |
| Applicant returned to address corrections | 11/30/2023 | SUNMIN LEE |
| Applicant returned to address corrections | 12/15/2023 | SUNMIN LEE |
| Applicant returned to address corrections | 2/20/2024 | SUNMIN LEE |
| Plan Check Approved | 2/26/2024 | SUNMIN LEE |
| Issued | 2/29/2024 | APPLICANT |
| CofO in Progress | 12/17/2024 | TROY SANDERS |
| Permit Finaled | 3/17/2025 | JOHN JANSON |
| CofO Issued | 3/17/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/9/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 9/12/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 9/12/2023 | CARLOS AGUILERA |
| Trees in Parkway | Cleared | 12/27/2023 | ADALBERTO VERA |
| Low Impact Development (LID) | Cleared | 2/2/2024 | PATRICK LOPEZ |
| Roof/Waste drainage to street | Cleared | 2/2/2024 | BRYAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Torres,, Efren Santos; Lic. No.: S2340 | 16003 S INDIAN CREEK RD CERRITOS, CA 90701 |
| Engineer | Yogurtian,, Arpinee; Lic. No.: C49916 | 2529 FOOTHILL BLVD, STE 208 LA CRESCENTA, CA 91214 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/15/2024 | Not Ready for Inspection | TROY SANDERS |
| PLUMBING-Rough | 3/15/2024 | Partial Approval | TROY SANDERS |
| Footing/Foundation/Slab | 3/19/2024 | Approved | TROY SANDERS |
| PLUMBING-Rough | 3/19/2024 | Partial Approval | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2024 | Partial Approval | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2024 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 5/7/2024 | Partial Approval | TROY SANDERS |
| ELECTRICAL-Rough | 5/7/2024 | Approved | TROY SANDERS |
| HVAC-Rough | 5/7/2024 | Approved | TROY SANDERS |
| PLUMBING-Rough | 5/7/2024 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 5/13/2024 | Not Ready for Inspection | TROY SANDERS |
| ELECTRICAL-Rough | 5/13/2024 | Approved | TROY SANDERS |
| HVAC-Rough | 5/13/2024 | Approved | TROY SANDERS |
| Structural Steel Frame | 5/13/2024 | Approved | TROY SANDERS |
| Verify Sprinkler Sign Off | 5/13/2024 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 5/24/2024 | Approved | TROY SANDERS |
| Insulation | 5/24/2024 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 5/24/2024 | Partial Approval | TROY SANDERS |
| Drywall Nailing | 5/28/2024 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 5/28/2024 | Partial Approval | TROY SANDERS |
| Special/Order Compliance | 5/28/2024 | Approved | HORACE FULTZ |
| Final | 11/7/2024 | Not Ready for Inspection | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 11/7/2024 | SGSOV Approved | TROY SANDERS |
| Service/Power Release | 11/7/2024 | Approved | TROY SANDERS |
| Smoke Detectors | 11/7/2024 | Approved | TROY SANDERS |
| Final | 12/16/2024 | OK to Issue CofO | TROY SANDERS |
| Service/Power Release | 12/16/2024 | Approved | TROY SANDERS |