4625 N VESPER AVE 91403
Certificate Information: 4625 N VESPER AVE 91403
- Application / Permit
- 23010-20000-02713
- Plan Check / Job No.
- B23VN08569
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 63' 7" X 37' 4 " TWO STORY SFD. NFPA 13D SPRINKLER REQUIRED THRU-OUT (ALL ELECTRIC) W/ ATT GARAGE. ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 9/8/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/13/2023 | NAREG ATARIAN |
| Corrections Issued | 7/17/2023 | NAREG ATARIAN |
| Quality Review Completed | 7/18/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 7/19/2023 | APPLICANT |
| Plan Check Approved | 9/8/2023 | NAREG ATARIAN |
| Issued | 9/8/2023 | APPLICANT |
| CofO in Progress | 8/7/2024 | MISAEL ESPARZA |
| Permit Finaled | 8/26/2024 | DANIEL ORRANTE |
| CofO Issued | 8/26/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/26/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/26/2023 | CARLOS AGUILERA |
| ZI | Cleared | 7/31/2023 | STEVEN WECHSLER |
| Low Impact Development (LID) | Cleared | 8/11/2023 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 8/15/2023 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 9/1/2023 | MATTHEW CRAIG |
| ZI | Cleared | 9/8/2023 | STEVEN WECHSLER |
Contact Information
| Contractor | A-N-G Builders; Lic. No.: 988791-B | 22254 DUMETZ RD WOODLAND HILLS, CA 91364 |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 10/17/2023 | Partial Approval | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 10/19/2023 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 10/19/2023 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 10/26/2023 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2023 | Partial Approval | MISAEL ESPARZA |
| Deputy Wood Construction | 12/12/2023 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2023 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2023 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2023 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 1/2/2024 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 1/5/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 1/5/2024 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 1/11/2024 | Partial Approval | MISAEL ESPARZA |
| ELECTRICAL-Rough | 1/23/2024 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 2/2/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| MERV13>=Rough | 2/2/2024 | Approved | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 2/2/2024 | Approved | MISAEL ESPARZA |
| Wood Frame | 2/2/2024 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 2/26/2024 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 2/26/2024 | Partial Approval | MISAEL ESPARZA |
| Shower Pan | 2/26/2024 | Approved | MISAEL ESPARZA |
| Insulation | 3/1/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Insulation | 3/4/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 3/4/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 3/8/2024 | Approved | SALVADOR MARTINEZ |
| Drywall Nailing | 3/13/2024 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 7/11/2024 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Final | 7/11/2024 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 8/1/2024 | Approved | MISAEL ESPARZA |
| HVAC-Final | 8/1/2024 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 8/1/2024 | Approved | MISAEL ESPARZA |
| Final | 8/6/2024 | OK to Issue CofO | MISAEL ESPARZA |
| MERV13>=Final | 8/6/2024 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 8/6/2024 | SGSOV Not Required | MISAEL ESPARZA |
| Service/Power Release | 8/6/2024 | Approved | MISAEL ESPARZA |
| Smoke Detectors | 8/6/2024 | Approved | MISAEL ESPARZA |