4715 W ST ELMO DR 90019

Certificate Information: 4715 W ST ELMO DR 90019

Application / Permit
23010-20000-02708
Plan Check / Job No.
B23VN08541
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 20'x 24.5' SINGLE-FAMILY DWELLING
Permit Issued
Issued on 8/24/2023
Issuing Office
Valley
Current Status
CofO Issued on 10/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/27/2023 APPLICANT
Assigned to Plan Check Engineer 6/30/2023 JESSE ARELLANO
Corrections Issued 7/6/2023 JESSE ARELLANO
Building Plans Picked Up 7/6/2023 APPLICANT
Applicant returned to address corrections 8/14/2023 LUISANGEL VALENZUELA
Plan Check Approved 8/24/2023 ALEC MOUSAKHANIAN
Issued 8/24/2023 APPLICANT
CofO in Progress 10/18/2024 JUSTIN HAWLEY
Permit Finaled 10/25/2024 RUBEN SALAS
CofO Issued 10/25/2024 RUBEN SALAS
Permit Finaled 10/25/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/4/2023 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 8/4/2023 CHRISTINA BRACO
Low Impact Development (LID) Cleared 8/4/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 8/4/2023 CHRISTINA BRACO
Sewer availability Cleared 8/4/2023 CHRISTINA BRACO
Hydrant and Access approval Cleared 8/11/2023 GILBERT URREA

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21757 DEVONSHIRE ST.   SUITE 3    CANOGA PARK, CA 91311

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/18/2024 Approved JOAQUIN GREENOUGH
METHANE-Rough 7/18/2024 Approved JOAQUIN GREENOUGH
Deputy Wood Construction 8/5/2024 Conditional Approval JUSTIN HAWLEY
BUILDING-Rough-Frame 8/6/2024 Not Ready for Inspection JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 8/6/2024 Approved JUSTIN HAWLEY
Green Building Rough 8/6/2024 Not Ready for Inspection JUSTIN HAWLEY
Insulation 8/6/2024 Partial Approval JUSTIN HAWLEY
Rough-Elec/Plmb/HVAC 8/6/2024 Corrections Issued JUSTIN HAWLEY
Shower Pan 8/6/2024 Approved JUSTIN HAWLEY
HVAC-Rough 8/7/2024 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 8/7/2024 Partial Approval JUSTIN HAWLEY
PLUMBING-Rough 8/7/2024 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 8/12/2024 Approved JUSTIN HAWLEY
Green Building Rough 8/12/2024 Approved JUSTIN HAWLEY
Insulation 8/12/2024 Conditional Approval JUSTIN HAWLEY
Interior/Exterior Lathing 8/12/2024 Approved JUSTIN HAWLEY
Drywall Nailing 8/13/2024 Approved ENRIQUE MIRELES
Drywall Nailing 8/14/2024 Approved ENRIQUE MIRELES
ELECTRICAL-Final 10/7/2024 Approved JUSTIN HAWLEY
Final 10/7/2024 Not Ready for Inspection JUSTIN HAWLEY
Footing/Foundation/Slab 10/7/2024 Approved JUSTIN HAWLEY
Green Building Final 10/7/2024 Approved JUSTIN HAWLEY
HVAC-Final 10/7/2024 Approved JUSTIN HAWLEY
METHANE-Barrier 10/7/2024 Approved JUSTIN HAWLEY
METHANE-Subgrade 10/7/2024 Approved JUSTIN HAWLEY
PLUMBING-Final 10/7/2024 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 10/7/2024 SGSOV Not Required JUSTIN HAWLEY
Service/Power Release 10/7/2024 Approved JUSTIN HAWLEY
Smoke Detectors 10/7/2024 Approved JUSTIN HAWLEY
Final 10/18/2024 OK to Issue CofO JUSTIN HAWLEY