16605 W LOS ALIMOS ST 91344
Certificate Information: 16605 W LOS ALIMOS ST 91344
- Application / Permit
- 23010-20000-02669
- Plan Check / Job No.
- B23VN08460
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan CONVERT (E) GARAGE TO (N) ADU AND ADDITION (870 SF) FOR TOTAL ADU OF 1200 SF PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 7/13/2023
- Issuing Office
- Current Status
- CofO Issued on 2/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/30/2023 | JOHNPAUL ISIP |
| Corrections Issued | 7/3/2023 | JOHNPAUL ISIP |
| Plan Check Approved | 7/12/2023 | JOHNPAUL ISIP |
| Issued | 7/13/2023 | APPLICANT |
| CofO in Progress | 12/15/2023 | JAVIER RAMOS JR |
| Permit Finaled | 2/14/2024 | RUBEN SALAS |
| CofO Issued | 2/14/2024 | RUBEN SALAS |
| Permit Finaled | 2/14/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/3/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/3/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/3/2023 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 7/10/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 7/10/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
| Engineer | Burnazyan,, Gegam; Lic. No.: NA76761 | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/31/2023 | Partial Approval | MICHEL ABAJAN |
| Pre-Inspection | 8/31/2023 | Partial Inspection | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 9/6/2023 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 9/6/2023 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 9/26/2023 | Partial Inspection | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2023 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Rough | 9/26/2023 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 9/28/2023 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 9/28/2023 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2023 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 9/28/2023 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 9/28/2023 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 9/28/2023 | Approved | JAVIER RAMOS JR |
| Shower Pan | 9/28/2023 | Approved | JAVIER RAMOS JR |
| Insulation | 10/2/2023 | Partial Approval | JAVIER RAMOS JR |
| Drywall Nailing | 10/6/2023 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 10/6/2023 | Approved | JAVIER RAMOS JR |
| Sewer | 10/20/2023 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 10/20/2023 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Final | 11/15/2023 | Approved | JAVIER RAMOS JR |
| Final | 11/15/2023 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 11/15/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 11/15/2023 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 11/15/2023 | SGSOV Not Ready | JAVIER RAMOS JR |
| Smoke Detectors | 11/15/2023 | Approved | JAVIER RAMOS JR |
| Final | 12/14/2023 | OK to Issue CofO | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 12/14/2023 | SGSOV Approved | JAVIER RAMOS JR |