9910 N CABANAS AVE 91042
Certificate Information: 9910 N CABANAS AVE 91042
- Application / Permit
- 23010-20000-02654
- Plan Check / Job No.
- B23VN08392
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (22) Storage Building
- Work Description
- (N) DETACHED 1-STORY STORAGE BUILDING (9'X 15'-2", 117SF)
- Permit Issued
- Issued on 3/7/2025
- Issuing Office
- Valley
- Current Status
- Issued on 3/7/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/23/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/29/2023 | PETER MOSESIAN |
| Corrections Issued | 7/1/2023 | PETER MOSESIAN |
| Quality Review Completed | 7/6/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 7/19/2023 | APPLICANT |
| Plan Check Approved | 2/27/2025 | NILOOFAR MEHRAIN |
| Issued | 3/7/2025 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/31/2024 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 7/19/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/23/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Abedian,, Vanik; Lic. No.: S5323 | 2906 JOLLEY DR BURBANK, CA 91504 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/17/2025 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 11/20/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Footing/Foundation/Slab | 11/26/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 1/27/2026 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 1/27/2026 | Approved | NICHOLAS TROWBRIDGE |
| Verify Sprinkler Sign Off | 1/27/2026 | Approved | NICHOLAS TROWBRIDGE |
| Drywall Nailing | 2/9/2026 | Approved | MICHEL ABAJAN |
| Final | 3/27/2026 | Conditional Approval | DAVID ANDERSON |
| Footing/Foundation/Slab | 3/27/2026 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 3/27/2026 | SGSOV Not Required | DAVID ANDERSON |
| Service/Power Release | 3/27/2026 | Approved | DAVID ANDERSON |
| Smoke Detectors | 3/27/2026 | Approved | DAVID ANDERSON |