7447 N PENFIELD AVE 91306

Certificate Information: 7447 N PENFIELD AVE 91306

Application / Permit
23010-20000-02635
Plan Check / Job No.
B23VN08327
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 52'-0" X 22'-0" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK DONE PER WFPP. <ALL ELECTRIC BUILDING>
Permit Issued
Issued on 12/6/2024
Issuing Office
Valley
Current Status
CofO Issued on 8/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/23/2023 APPLICANT
Assigned to Plan Check Engineer 6/28/2023 JEROME MAGAT PALMA
Corrections Issued 6/28/2023 JEROME MAGAT PALMA
Building Plans Picked Up 6/29/2023 APPLICANT
Applicant returned to address corrections 11/7/2024 KAMYAR EMAMI
Applicant returned to address corrections 11/21/2024 HAYATO TSUCHIYA
Plan Check Approved 12/6/2024 ANGELICA MARTINEZ
Issued 12/6/2024 APPLICANT
CofO in Progress 7/23/2025 ALEXANDER HANDY
Permit Finaled 8/26/2025 JOHN JANSON
CofO Issued 8/26/2025 JOHN JANSON
Permit Finaled 8/26/2025 JOHN JANSON

Permit Application Clearance Information

Construction near power lines Cleared 3/26/2024 RIDWAN HARDY
Address approval Cleared 5/4/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 5/6/2024 CARLOS AGUILERA
Sewer availability Cleared 5/6/2024 CARLOS AGUILERA
Low Impact Development (LID) Cleared 10/31/2024 ERNEST TSE
Roof/Waste drainage to street Cleared 11/4/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Cristescu,, Barbu Dan; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/27/2024 Approved ALEXANDER HANDY
PLUMBING-Rough 1/14/2025 Partial Approval DAVID SCANTLIN
Sewer 1/14/2025 Approved DAVID SCANTLIN
Underground Mechanical 1/14/2025 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 2/4/2025 Approved ALEXANDER HANDY
Interior/Exterior Lathing 2/19/2025 Partial Approval ALEXANDER HANDY
Rough-Elec/Plmb/HVAC 2/19/2025 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 3/10/2025 Not Ready for Inspection ALEXANDER HANDY
Green Building Rough 3/10/2025 Approved ALEXANDER HANDY
Insulation 3/10/2025 Corrections Issued ALEXANDER HANDY
Verify Sprinkler Sign Off 3/10/2025 Approved ALEXANDER HANDY
Drywall Nailing 3/21/2025 Approved JEFFREY HARTLINE
ELECTRICAL-Final 6/26/2025 Approved JEFFREY PARD
Service/Power Release 6/26/2025 Not Ready for Inspection JEFFREY PARD
Final 7/2/2025 Not Ready for Inspection KRISTEN CAUSEY
BUILDING-Rough-Frame 7/22/2025 Approved ALEXANDER HANDY
Final 7/22/2025 OK to Issue CofO ALEXANDER HANDY
Footing/Foundation/Slab 7/22/2025 Approved ALEXANDER HANDY
Green Building Final 7/22/2025 Approved ALEXANDER HANDY
HVAC-Final 7/22/2025 Approved ALEXANDER HANDY
PLUMBING-Final 7/22/2025 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 7/22/2025 SGSOV No Gas ALEXANDER HANDY
Service/Power Release 7/22/2025 Approved ALEXANDER HANDY
Smoke Detectors 7/22/2025 Approved ALEXANDER HANDY