10443 N KEWEN AVE 91331
Certificate Information: 10443 N KEWEN AVE 91331
- Application / Permit
- 23010-20000-02581
- Plan Check / Job No.
- B23VN08153
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Detached single-family, one-story accessory dwelling unit ADU CHECKED PER LAMC 12.22 A.33 (C)-(D)
- Permit Issued
- Issued on 6/23/2025
- Issuing Office
- Current Status
- Issued on 6/23/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/6/2023 | SUNMIN LEE |
| Corrections Issued | 7/10/2023 | SUNMIN LEE |
| Quality Review Completed | 7/10/2023 | GARO TELMI |
| Applicant returned to address corrections | 11/6/2023 | SUNMIN LEE |
| Applicant returned to address corrections | 11/15/2023 | SUNMIN LEE |
| Applicant returned to address corrections | 7/17/2024 | SUNMIN LEE |
| Applicant returned to address corrections | 10/28/2024 | SUNMIN LEE |
| Applicant returned to address corrections | 2/4/2025 | SUNMIN LEE |
| Plan Check Approved | 2/18/2025 | SUNMIN LEE |
| Issued | 6/23/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/30/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 8/30/2023 | DAGOVERTO GUERRERO |
| Construction within easement | Cleared | 5/8/2024 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 6/24/2024 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 6/25/2024 | CARLOS RAMIREZ |
| Clean Up Green Up | Cleared | 6/27/2024 | NOAH MCCOY |
| ZI | Cleared | 6/27/2024 | NOAH MCCOY |
| Sewer availability | Cleared | 7/9/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Arakelyan,, Aram; Lic. No.: C82796 | 145 S GLENOAKS BI 328 BURBANK, CA 91502 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/3/2025 | Approved | NICHOLAS TROWBRIDGE |
| Pre-Inspection | 7/8/2025 | Partial Inspection | MICHEL ABAJAN |
| Footing/Foundation/Slab | 7/25/2025 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 7/25/2025 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 7/25/2025 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 8/15/2025 | Partial Approval | MICHEL ABAJAN |
| PLUMBING-Rough | 8/15/2025 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2025 | Partial Approval | MICHEL ABAJAN |
| Deputy Wood Construction | 9/22/2025 | Conditional Approval | RAUL OLAGI |
| Deputy Wood Construction | 9/23/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2025 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2025 | Partial Approval | KEVIN BERBERYAN |
| Rough-Elec/Plmb/HVAC | 10/3/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 10/8/2025 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 10/8/2025 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 10/8/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 10/8/2025 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 10/8/2025 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 10/22/2025 | Approved | MICHEL ABAJAN |
| Green Building Rough | 10/22/2025 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 10/22/2025 | Approved | MICHEL ABAJAN |
| Insulation | 10/24/2025 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 10/29/2025 | Approved | KEVIN BERBERYAN |
| Shower Pan | 11/12/2025 | Approved | CHRISTOPHER MORFIN |
| Interior/Exterior Lathing | 11/14/2025 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 6/3/2026 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 6/8/2026 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Final | 7/2/2026 | Approved | MICHEL ABAJAN |
| Final | 7/2/2026 | Corrections Issued | MICHEL ABAJAN |
| HVAC-Final | 7/2/2026 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 7/2/2026 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 7/2/2026 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 7/2/2026 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 7/2/2026 | Approved | MICHEL ABAJAN |