24035 W WELBY WAY 91307
Certificate Information: 24035 W WELBY WAY 91307
- Application / Permit
- 23010-20000-02580
- Plan Check / Job No.
- B23VN08149
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan PROPOSED DETACHED ADU AT REAR OF LOT . DETACHED NEW CONSTRUCTION ADU PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g)
- Permit Issued
- Issued on 10/6/2023
- Issuing Office
- Current Status
- CofO Issued on 6/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/6/2023 | ADRIANA LOPEZ |
| Corrections Issued | 7/17/2023 | ADRIANA LOPEZ |
| Quality Review Completed | 7/31/2023 | FARUK SEZER |
| Applicant returned to address corrections | 8/22/2023 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 9/6/2023 | ADRIANA LOPEZ |
| Plan Check Approved | 10/4/2023 | ADRIANA LOPEZ |
| Issued | 10/6/2023 | APPLICANT |
| CofO in Progress | 5/31/2024 | TROY SANDERS |
| Permit Finaled | 6/24/2024 | JOHN JANSON |
| CofO Issued | 6/24/2024 | JOHN JANSON |
| Permit Finaled | 6/24/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/18/2023 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 7/18/2023 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 7/18/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 7/18/2023 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 7/18/2023 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 8/3/2023 | TINA MIRANDA |
| Construction within easement | Cleared | 8/3/2023 | TINA MIRANDA |
Contact Information
| Architect | Song,, Michael; Lic. No.: NA32566 | , |
| Contractor | Owner-Builder | , |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: NA77737 | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/15/2023 | Approved | TROY SANDERS |
| PLUMBING-Rough | 12/15/2023 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 1/11/2024 | Approved | TROY SANDERS |
| Green Building Rough | 1/11/2024 | Not Ready for Inspection | TROY SANDERS |
| Verify Sprinkler Sign Off | 1/11/2024 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 2/1/2024 | Approved | TROY SANDERS |
| Green Building Rough | 2/1/2024 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 2/1/2024 | Partial Approval | TROY SANDERS |
| Rough-Elec/Plmb/HVAC | 2/1/2024 | Approved | TROY SANDERS |
| Deputy Drilled-In Anchors | 2/5/2024 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 3/26/2024 | Approved | TROY SANDERS |
| Sewer | 3/26/2024 | Approved | TROY SANDERS |
| Drywall Nailing | 5/2/2024 | Approved | TROY SANDERS |
| Final | 5/2/2024 | Not Ready for Inspection | TROY SANDERS |
| Green Building Final | 5/2/2024 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 5/2/2024 | SGSOV Approved | TROY SANDERS |
| Service/Power Release | 5/2/2024 | Approved | TROY SANDERS |
| Smoke Detectors | 5/2/2024 | Approved | TROY SANDERS |
| Final | 5/31/2024 | OK to Issue CofO | TROY SANDERS |