4931 N VARNA AVE 91423

Certificate Information: 4931 N VARNA AVE 91423

Application / Permit
23010-20000-02577
Plan Check / Job No.
B23VN08137
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW DETACHED 1-STORY (11'-0'x20'-0"), 195 SQFT RECREATION ROOM
Permit Issued
Issued on 10/6/2023
Issuing Office
Valley
Current Status
CofO Issued on 9/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/20/2023 APPLICANT
Assigned to Plan Check Engineer 6/22/2023 PETER MOSESIAN
Corrections Issued 6/27/2023 PETER MOSESIAN
Quality Review Completed 7/3/2023 OMID HEDAYAT
Building Plans Picked Up 7/3/2023 APPLICANT
Plan Check Approved 10/6/2023 PETER MOSESIAN
Issued 10/6/2023 APPLICANT
CofO in Progress 9/13/2024 MISAEL ESPARZA
Permit Finaled 9/25/2024 DANIEL ORRANTE
CofO Issued 9/25/2024 DANIEL ORRANTE
Permit Finaled 9/25/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/10/2023 DAGOVERTO GUERRERO
Low Impact Development (LID) Cleared 7/24/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 7/25/2023 DAGOVERTO GUERRERO
ZI Cleared 8/1/2023 BRENNEN OBETO
Construction near power lines Cleared 9/26/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Beck,, Charles Joseph; Lic. No.: C19289 129 WEST PONDERA STREET      LANCASTER, CA 93534
Engineer Wang,, Hongyu; Lic. No.: C72679 8887 W FALMINGO RD STE 101      LAS VEGAS, NV 89147

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/6/2023 Approved MISAEL ESPARZA
PLUMBING-Rough 11/6/2023 Partial Approval MISAEL ESPARZA
Underground Mechanical 11/6/2023 Partial Approval MISAEL ESPARZA
Deputy Reinf. Concrete 11/7/2023 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 1/24/2024 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 1/26/2024 Partial Approval MISAEL ESPARZA
Green Building Rough 1/26/2024 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 2/15/2024 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 2/22/2024 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 2/22/2024 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 3/13/2024 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 3/13/2024 SGSOV Not Required MISAEL ESPARZA
ELECTRICAL-Rough 3/27/2024 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 3/27/2024 Approved MISAEL ESPARZA
Wood Frame 3/27/2024 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 4/1/2024 Conditional Approval MISAEL ESPARZA
ELECTRICAL-Rough 4/1/2024 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 4/1/2024 Approved MISAEL ESPARZA
Green Building Rough 4/1/2024 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 4/1/2024 Approved MISAEL ESPARZA
Wood Frame 4/1/2024 Approved MISAEL ESPARZA
Interior/Exterior Lathing 4/22/2024 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 4/25/2024 Approved MISAEL ESPARZA
Green Building Rough 4/25/2024 Approved MISAEL ESPARZA
Insulation 5/2/2024 Approved JACK KARGODORIAN
Drywall Nailing 5/7/2024 Approved MISAEL ESPARZA
Shower Pan 5/30/2024 Approved JOHN COLEMAN
Interior/Exterior Lathing 6/3/2024 Approved STUART CHAPMAN
ELECTRICAL-Final 9/9/2024 Corrections Issued MISAEL ESPARZA
HVAC-Final 9/9/2024 Approved MISAEL ESPARZA
PLUMBING-Final 9/9/2024 Conditional Approval MISAEL ESPARZA
ELECTRICAL-Final 9/12/2024 Approved MISAEL ESPARZA
Final 9/12/2024 OK to Issue CofO MISAEL ESPARZA
Green Building Final 9/12/2024 Approved MISAEL ESPARZA
PLUMBING-Final 9/12/2024 Approved MISAEL ESPARZA
Service/Power Release 9/12/2024 Approved MISAEL ESPARZA
Smoke Detectors 9/12/2024 Approved MISAEL ESPARZA