10663 N ENCINO AVE 91344
Certificate Information: 10663 N ENCINO AVE 91344
- Application / Permit
- 23010-20000-02549
- Plan Check / Job No.
- B23VN08074
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: (N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
- Permit Issued
- Issued on 4/17/2024
- Issuing Office
- Current Status
- CofO Issued on 11/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/6/2023 | DANIEL YIP |
| Corrections Issued | 7/11/2023 | DANIEL YIP |
| Quality Review Completed | 7/11/2023 | GARO TELMI |
| Applicant returned to address corrections | 8/31/2023 | DANIEL YIP |
| Applicant returned to address corrections | 9/21/2023 | DANIEL YIP |
| Applicant returned to address corrections | 10/19/2023 | DANIEL YIP |
| Plan Check Approved | 11/28/2023 | DANIEL YIP |
| Issued | 4/17/2024 | APPLICANT |
| CofO in Progress | 11/5/2025 | NICHOLAS TROWBRIDGE |
| Permit Finaled | 11/18/2025 | RUBEN SALAS |
| CofO Issued | 11/18/2025 | RUBEN SALAS |
| Permit Finaled | 11/18/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/18/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 8/21/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 8/21/2023 | COLIN LOREDO |
| Specific Plan | Cleared | 9/6/2023 | OLGA AYALA |
| Low Impact Development (LID) | Cleared | 11/27/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 11/27/2023 | BRYAN GODINEZ |
Contact Information
| Contractor | Zen Builders & Consultants Inc; Lic. No.: 1102657-B | , |
| Engineer | Grigoryan,, Souren; Lic. No.: NA93320 | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/9/2024 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 8/21/2024 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 9/3/2024 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2024 | Partial Inspection | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2024 | Corrections Issued | JAVIER RAMOS JR |
| Wood Frame | 10/15/2024 | Partial Inspection | JAVIER RAMOS JR |
| Deputy Drilled-In Anchors | 10/30/2024 | Conditional Approval | ROBERT GOLD |
| Deputy Wood Construction | 10/30/2024 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 11/19/2024 | Partial Inspection | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2024 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 12/23/2024 | Partial Approval | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 12/23/2024 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 1/13/2025 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Rough | 1/13/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 1/13/2025 | Approved | JAVIER RAMOS JR |
| Insulation | 1/27/2025 | Not Ready for Inspection | MICHAEL CORTEZ |
| ELECTRICAL-Rough | 1/29/2025 | Approved | JAVIER RAMOS JR |
| Insulation | 1/29/2025 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 2/18/2025 | Approved | MICHEL ABAJAN |
| Green Building Rough | 2/18/2025 | Approved | MICHEL ABAJAN |
| Shower Pan | 3/4/2025 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 3/4/2025 | Partial Approval | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 3/13/2025 | Approved | JAVIER RAMOS JR |
| Pre-Inspection | 3/13/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 7/1/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 7/1/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 7/1/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 7/1/2025 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Service/Power Release | 7/1/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 7/1/2025 | Approved | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 7/1/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 7/29/2025 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 8/6/2025 | Approved | NICHOLAS TROWBRIDGE |
| Final | 8/6/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Final | 8/6/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 8/6/2025 | SGSOV Not Required | NICHOLAS TROWBRIDGE |
| Service/Power Release | 8/6/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Verify Sprinkler Sign Off | 8/6/2025 | Approved | NICHOLAS TROWBRIDGE |
| Final | 10/7/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Final | 10/7/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Service/Power Release | 10/7/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Final | 11/5/2025 | OK to Issue CofO | NICHOLAS TROWBRIDGE |
| Green Building Final | 11/5/2025 | Approved | NICHOLAS TROWBRIDGE |
| Service/Power Release | 11/5/2025 | Approved | NICHOLAS TROWBRIDGE |