10663 N ENCINO AVE 91344

Certificate Information: 10663 N ENCINO AVE 91344

Application / Permit
23010-20000-02549
Plan Check / Job No.
B23VN08074
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 4/17/2024
Issuing Office
Current Status
CofO Issued on 11/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/20/2023 APPLICANT
Assigned to Plan Check Engineer 7/6/2023 DANIEL YIP
Corrections Issued 7/11/2023 DANIEL YIP
Quality Review Completed 7/11/2023 GARO TELMI
Applicant returned to address corrections 8/31/2023 DANIEL YIP
Applicant returned to address corrections 9/21/2023 DANIEL YIP
Applicant returned to address corrections 10/19/2023 DANIEL YIP
Plan Check Approved 11/28/2023 DANIEL YIP
Issued 4/17/2024 APPLICANT
CofO in Progress 11/5/2025 NICHOLAS TROWBRIDGE
Permit Finaled 11/18/2025 RUBEN SALAS
CofO Issued 11/18/2025 RUBEN SALAS
Permit Finaled 11/18/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/18/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 8/21/2023 COLIN LOREDO
Sewer availability Cleared 8/21/2023 COLIN LOREDO
Specific Plan Cleared 9/6/2023 OLGA AYALA
Low Impact Development (LID) Cleared 11/27/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 11/27/2023 BRYAN GODINEZ

Contact Information

Contractor Zen Builders & Consultants Inc; Lic. No.: 1102657-B       ,
Engineer Grigoryan,, Souren; Lic. No.: NA93320       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/9/2024 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 8/21/2024 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 9/3/2024 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 9/25/2024 Partial Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 10/15/2024 Corrections Issued JAVIER RAMOS JR
Wood Frame 10/15/2024 Partial Inspection JAVIER RAMOS JR
Deputy Drilled-In Anchors 10/30/2024 Conditional Approval ROBERT GOLD
Deputy Wood Construction 10/30/2024 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 11/19/2024 Partial Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 11/19/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 12/23/2024 Partial Approval JAVIER RAMOS JR
Interior/Exterior Lathing 12/23/2024 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 1/13/2025 Corrections Issued JAVIER RAMOS JR
HVAC-Rough 1/13/2025 Approved JAVIER RAMOS JR
PLUMBING-Rough 1/13/2025 Approved JAVIER RAMOS JR
Insulation 1/27/2025 Not Ready for Inspection MICHAEL CORTEZ
ELECTRICAL-Rough 1/29/2025 Approved JAVIER RAMOS JR
Insulation 1/29/2025 Approved JAVIER RAMOS JR
Drywall Nailing 2/18/2025 Approved MICHEL ABAJAN
Green Building Rough 2/18/2025 Approved MICHEL ABAJAN
Shower Pan 3/4/2025 Approved JAVIER RAMOS JR
Underground Mechanical 3/4/2025 Partial Approval JAVIER RAMOS JR
Interior/Exterior Lathing 3/13/2025 Approved JAVIER RAMOS JR
Pre-Inspection 3/13/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 7/1/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Final 7/1/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 7/1/2025 Not Ready for Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 7/1/2025 SGSOV Not Ready CHRISTOPHER ROJAS
Service/Power Release 7/1/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Smoke Detectors 7/1/2025 Approved CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 7/1/2025 Not Ready for Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 7/29/2025 SGSOV Not Ready CHRISTOPHER ROJAS
BUILDING-Rough-Frame 8/6/2025 Approved NICHOLAS TROWBRIDGE
Final 8/6/2025 Corrections Issued NICHOLAS TROWBRIDGE
Green Building Final 8/6/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 8/6/2025 SGSOV Not Required NICHOLAS TROWBRIDGE
Service/Power Release 8/6/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Verify Sprinkler Sign Off 8/6/2025 Approved NICHOLAS TROWBRIDGE
Final 10/7/2025 Corrections Issued NICHOLAS TROWBRIDGE
Green Building Final 10/7/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Service/Power Release 10/7/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Final 11/5/2025 OK to Issue CofO NICHOLAS TROWBRIDGE
Green Building Final 11/5/2025 Approved NICHOLAS TROWBRIDGE
Service/Power Release 11/5/2025 Approved NICHOLAS TROWBRIDGE