232 S MEDIO DR 90049
Certificate Information: 232 S MEDIO DR 90049
- Application / Permit
- 23010-20000-02532
- Plan Check / Job No.
- B23VN07980
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW IRR. SHAPED 38' x 84'-7" TWO-STORY SINGLE FAMILY DWELLING W/ BASEMENT AND ATT. 2-CAR GARAGE; NFPA-13 THRU-OUT
- Permit Issued
- Issued on 9/8/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/15/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/22/2023 | SEAN SHAHMIRI |
| Corrections Issued | 6/26/2023 | SEAN SHAHMIRI |
| Quality Review Completed | 6/27/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 6/29/2023 | APPLICANT |
| Applicant returned to address corrections | 8/24/2023 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 8/31/2023 | SEAN SHAHMIRI |
| Plan Check Approved | 9/7/2023 | SEAN SHAHMIRI |
| Issued | 9/8/2023 | APPLICANT |
| CofO in Progress | 10/29/2025 | KENNETH NAGLE |
| Permit Finaled | 10/30/2025 | RICHARD STEINBACH |
| CofO Issued | 10/30/2025 | RICHARD STEINBACH |
| Permit Finaled | 10/30/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 7/17/2023 | JASON NG |
| Eng Process Fee Ord 176,300 | Cleared | 7/18/2023 | JASON NG |
| Sewer availability | Cleared | 7/18/2023 | JASON NG |
| Specific Plan | Cleared | 7/20/2023 | ALESSANDRO MERCURI |
| Low Impact Development (LID) | Cleared | 7/24/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 7/25/2023 | JASON NG |
| Hydrant and Access approval | Cleared | 8/26/2023 | JOHN CONNEALLY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/14/2023 | Approved | KENNETH NAGLE |
| Footing/Foundation/Slab | 1/16/2024 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 2/14/2024 | Partial Approval | CHRISTOPHER WILSON |
| PLUMBING-Rough | 3/6/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| Underground Mechanical | 3/6/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 3/7/2024 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 4/10/2024 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 4/18/2024 | Approved | ARAM AVEDISIAN |
| Deputy Wood Construction | 4/29/2024 | Conditional Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2024 | Corrections Issued | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2024 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2024 | Corrections Issued | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2024 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 7/29/2024 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 8/21/2024 | Conditional Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 8/21/2024 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 8/21/2024 | Approved | ARAM AVEDISIAN |
| Shower Pan | 8/21/2024 | Approved | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 8/21/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 11/13/2024 | Approved | ARAM AVEDISIAN |
| Insulation | 11/13/2024 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 11/13/2024 | Partial Approval | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 11/13/2024 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 11/15/2024 | Partial Approval | ARAM AVEDISIAN |
| Drywall Nailing | 11/20/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 9/30/2025 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Final | 9/30/2025 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Final | 10/1/2025 | Approved | ARAM AVEDISIAN |
| Final | 10/1/2025 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Final | 10/1/2025 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 10/1/2025 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 10/1/2025 | SGSOV Not Ready | ARAM AVEDISIAN |
| Smoke Detectors | 10/1/2025 | Approved | ARAM AVEDISIAN |
| Final | 10/3/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| Final | 10/29/2025 | OK to Issue CofO | KENNETH NAGLE |
| Service/Power Release | 10/29/2025 | Approved | KENNETH NAGLE |