7902 N ST CLAIR AVE 91605

Certificate Information: 7902 N ST CLAIR AVE 91605

Application / Permit
23010-20000-02522
Plan Check / Job No.
B23VN07918
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan - NEW ADU PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g) WITH ATTACHED REC. ROOM, AND 2-CAR GARAGE
Permit Issued
Issued on 1/26/2024
Issuing Office
Current Status
CofO Issued on 11/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2023 APPLICANT
Assigned to Plan Check Engineer 7/6/2023 MAHNAZ NOURHASHEMI
Corrections Issued 7/13/2023 MAHNAZ NOURHASHEMI
Quality Review Completed 7/20/2023 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 1/18/2024 MAHNAZ NOURHASHEMI
Issued 1/26/2024 APPLICANT
CofO in Progress 11/15/2024 MATTHEW NELSON
Permit Finaled 11/23/2024 DANIEL ORRANTE
CofO Issued 11/23/2024 DANIEL ORRANTE
Permit Finaled 11/23/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/7/2023 DAGOVERTO GUERRERO
Permit Cleared 8/7/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 8/9/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 8/9/2023 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 9/23/2023 KURT CORRAL
Construction near power lines Cleared 10/24/2023 WALTER RAMIREZ
Low Impact Development (LID) Cleared 1/10/2024 LUIS CRUZ
Roof/Waste drainage to street Cleared 1/11/2024 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Medina,, Armando; Lic. No.: C83911 2000 W LINCOLN AVE      MONTEBELLO, CA 90640

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/10/2024 Approved MATTHEW NELSON
BUILDING-Rough-Frame 5/8/2024 Partial Approval MATTHEW NELSON
PLUMBING-Rough 5/8/2024 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 6/27/2024 Partial Approval MATTHEW NELSON
Verify Sprinkler Sign Off 6/27/2024 Approved MATTHEW NELSON
BUILDING-Rough-Frame 7/16/2024 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 7/16/2024 Approved MATTHEW NELSON
PLUMBING-Rough 7/16/2024 Approved MATTHEW NELSON
ELECTRICAL-Rough 7/18/2024 Approved MATTHEW NELSON
HVAC-Rough 7/18/2024 Approved MATTHEW NELSON
BUILDING-Rough-Frame 7/23/2024 Approved LOUIS ESCOTO
Insulation 7/23/2024 Approved LOUIS ESCOTO
Interior/Exterior Lathing 7/23/2024 Approved LOUIS ESCOTO
Drywall Nailing 7/30/2024 Approved MATTHEW NELSON
Final 10/28/2024 Not Ready for Inspection MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 10/28/2024 SGSOV Not Required MATTHEW NELSON
Service/Power Release 10/28/2024 Not Ready for Inspection MATTHEW NELSON
Smoke Detectors 10/28/2024 Approved MATTHEW NELSON
Final 11/1/2024 Not Ready for Inspection MATTHEW NELSON
Service/Power Release 11/1/2024 Not Ready for Inspection MATTHEW NELSON
Final 11/15/2024 OK to Issue CofO MATTHEW NELSON
Service/Power Release 11/15/2024 Approved MATTHEW NELSON