7744 N OSTROM AVE 91406
Certificate Information: 7744 N OSTROM AVE 91406
- Application / Permit
- 23010-20000-02517
- Plan Check / Job No.
- B23VN07904
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 2-story (25' x 24'-6") Accessory Dwelling Unit per LAMC 12.22 A.33 (c) - (d)
- Permit Issued
- Issued on 1/18/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/6/2023 | VAHAN JIVALAGIAN |
| Corrections Issued | 7/10/2023 | VAHAN JIVALAGIAN |
| Quality Review Completed | 7/12/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 7/14/2023 | APPLICANT |
| Applicant returned to address corrections | 1/16/2024 | VAHAN JIVALAGIAN |
| Plan Check Approved | 1/18/2024 | VAHAN JIVALAGIAN |
| Issued | 1/18/2024 | APPLICANT |
| CofO in Progress | 11/24/2025 | GAREN HAYRAPETYAN |
| Permit Finaled | 12/4/2025 | RUBEN SALAS |
| CofO Issued | 12/4/2025 | RUBEN SALAS |
| Permit Finaled | 12/4/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/17/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 7/17/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2023 | DAGOVERTO GUERRERO |
| Low Impact Development (LID) | Cleared | 10/24/2023 | MELINEH AGHAKHABIAN |
| Construction near power lines | Cleared | 11/3/2023 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 11/7/2023 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Eddy Alexander; Lic. No.: S6159 | 17958 LULL ST RESEDA, CA 91335 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/27/2024 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 3/1/2024 | Not Ready for Inspection | RAUL OLAGI |
| Footing/Foundation/Slab | 3/6/2024 | Approved | RAUL OLAGI |
| Wood Frame | 3/13/2024 | Corrections Issued | RAUL OLAGI |
| Wood Frame | 3/14/2024 | Not Ready for Inspection | RAUL OLAGI |
| Wood Frame | 3/21/2024 | Not Ready for Inspection | RAUL OLAGI |
| Wood Frame | 3/22/2024 | No Access for Inspection | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2024 | Partial Approval | RAUL OLAGI |
| Rough-Elec/Plmb/HVAC | 4/17/2024 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 4/23/2024 | Corrections Issued | RAUL OLAGI |
| Interior/Exterior Lathing | 4/23/2024 | Corrections Issued | RAUL OLAGI |
| Rough-Elec/Plmb/HVAC | 4/23/2024 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 4/29/2024 | Approved | RAUL OLAGI |
| Green Building Rough | 4/29/2024 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 4/29/2024 | Partial Approval | RAUL OLAGI |
| Verify Sprinkler Sign Off | 4/29/2024 | Approved | RAUL OLAGI |
| Insulation | 5/6/2024 | Approved | SALVADOR MARTINEZ |
| Shower Pan | 5/6/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Drywall Nailing | 5/20/2024 | Approved | SALVADOR MARTINEZ |
| Shower Pan | 5/20/2024 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 6/10/2024 | Approved | RAUL OLAGI |
| Underground Mechanical | 7/15/2024 | Approved | SALVADOR MARTINEZ |
| Sewer | 7/17/2024 | Approved | RAUL OLAGI |
| Final | 10/14/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Final | 10/14/2025 | Approved | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 10/14/2025 | SGSOV Not Ready | GAREN HAYRAPETYAN |
| Service/Power Release | 10/14/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Smoke Detectors | 10/14/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 11/6/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 11/6/2025 | SGSOV Not Ready | GAREN HAYRAPETYAN |
| Service/Power Release | 11/6/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Final | 11/20/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 11/20/2025 | SGSOV Not Required | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 11/20/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 11/24/2025 | OK to Issue CofO | GAREN HAYRAPETYAN |
| Service/Power Release | 11/24/2025 | Approved | GAREN HAYRAPETYAN |