1800 N MICHELTORENA ST 90026

Certificate Information: 1800 N MICHELTORENA ST 90026

Application / Permit
23010-20000-02514
Plan Check / Job No.
B23VN07898
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 55' X 37'8" Two story sfd with habitable basement and attached two car garage, nfpa-13d fire sprinklerss required throughout, all work per engineering
Permit Issued
Issued on 7/11/2024
Issuing Office
Metro
Current Status
Issued on 7/11/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/14/2023 APPLICANT
Assigned to Plan Check Engineer 6/22/2023 RARES BODEA
Corrections Issued 7/7/2023 RARES BODEA
Quality Review Completed 7/10/2023 STEVEN KIM
Building Plans Picked Up 7/11/2023 APPLICANT
Applicant returned to address corrections 4/11/2024 RARES BODEA
Applicant returned to address corrections 6/4/2024 RARES BODEA
Plan Check Approved 6/18/2024 RARES BODEA
Issued 7/11/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/21/2023 TREVOR QUAN
BHO/Hillside ordinance Cleared 7/21/2023 TREVOR QUAN
BHO/Hillside ordinance Cleared 7/21/2023 TREVOR QUAN
BHO/Hillside ordinance Cleared 7/21/2023 TREVOR QUAN
BHO/Hillside ordinance Cleared 7/21/2023 TREVOR QUAN
BHO/Hillside ordinance Cleared 7/21/2023 TREVOR QUAN
Permit Cleared 7/21/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 7/26/2023 TREVOR QUAN
Sewer availability Cleared 7/26/2023 TREVOR QUAN
Trees in Parkway Cleared 9/12/2023 ADALBERTO VERA
Distance to fire station Cleared 9/22/2023 JOHN CONNEALLY
Hydrant and Access approval Cleared 9/22/2023 JOHN CONNEALLY
Low Impact Development Cleared 12/21/2023 TRISH PARAS
Roof/Waste drainage to street Cleared 1/6/2024 STEVEN JIN
Work Adjacent to Public Way Cleared 4/4/2024 LARRY LEE
Excavation more than 5-ft deep Cleared 4/11/2024 CALOSHA APPROVED
GPI Written Notices Cleared 4/11/2024 RARES BODEA
Grading Pre-Inspection Cleared 4/11/2024 RARES BODEA

Contact Information

Contractor Owner-Builder       ,
Engineer Oruncakciel,, Sayat; Lic. No.: C77182 15445 VENTURA BLVD 25      SHERMAN OAKS, CA 91403

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/18/2024 Partial Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 11/18/2024 Partial Approval HAMIK HARTOUNIAN
Piling/Pier/Caisson 11/18/2024 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 11/20/2024 Partial Approval LUIS CASTRO
Piling/Pier/Caisson 11/21/2024 Partial Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 12/23/2024 Corrections Issued HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 12/30/2024 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 12/30/2024 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 2/14/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 2/14/2025 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 2/18/2025 Not Ready for Inspection BRENDAN MORELLI
Excavation/Setback/Form/Re-Bar 2/18/2025 Not Ready for Inspection BRENDAN MORELLI
Masonry Wall/Backfill 3/6/2025 Partial Approval FREDDIE RIVERA
Reinforced Concrete Frame 3/6/2025 Partial Approval FREDDIE RIVERA
Gas Test 3/14/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Masonry Wall/Backfill 3/14/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Masonry Wall/Backfill 3/18/2025 Partial Approval HAMIK HARTOUNIAN
Underground Mechanical 4/1/2025 Partial Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 4/14/2025 Corrections Issued HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 4/16/2025 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 5/6/2025 Partial Approval FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 5/20/2025 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 5/27/2025 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 6/9/2025 Corrections Issued ALEX COLIN
Underground Mechanical 9/26/2025 Partial Approval HAMIK HARTOUNIAN
Deputy Wood Construction 10/27/2025 Conditional Approval OSVALDO PARAMO
PLUMBING-Rough 10/29/2025 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 10/30/2025 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 11/24/2025 Approved ALIZAH MAYAGOITIA
HVAC-Rough 11/24/2025 Corrections Issued ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 12/4/2025 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 12/4/2025 Corrections Issued HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 12/4/2025 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 12/23/2025 Conditional Approval HAMIK HARTOUNIAN
Green Building Rough 12/23/2025 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 12/23/2025 Partial Approval HAMIK HARTOUNIAN
Shower Pan 12/26/2025 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 1/9/2026 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 1/9/2026 Approved HAMIK HARTOUNIAN
HVAC-Rough 1/9/2026 Approved HAMIK HARTOUNIAN
Insulation 1/9/2026 Conditional Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 1/13/2026 Approved HAMIK HARTOUNIAN
Drywall Nailing 1/21/2026 Approved ALEX COLIN
Deputy Reinf. Concrete 3/27/2026 Conditional Approval HAMIK HARTOUNIAN
Special/Order Compliance 3/31/2026 Approved HAMIK HARTOUNIAN
Gas Test 7/10/2026 Approved HAMIK HARTOUNIAN
Sewer 7/10/2026 Not Ready for Inspection HAMIK HARTOUNIAN
Underground Mechanical 7/10/2026 Approved HAMIK HARTOUNIAN