1806 N MICHELTORENA ST 90026
Certificate Information: 1806 N MICHELTORENA ST 90026
- Application / Permit
- 23010-20000-02511
- Plan Check / Job No.
- B23VN07888
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 55' X 37'8" Two story sfd with habitable basement and attached two car garage, nfpa-13d fire sprinklerss required throughout, all work per engineering
- Permit Issued
- Issued on 7/15/2024
- Issuing Office
- Metro
- Current Status
- Issued on 7/15/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/22/2023 | RARES BODEA |
| Corrections Issued | 6/27/2023 | RARES BODEA |
| Quality Review Completed | 6/28/2023 | STEVEN KIM |
| Building Plans Picked Up | 7/11/2023 | APPLICANT |
| Applicant returned to address corrections | 4/17/2024 | RARES BODEA |
| Applicant returned to address corrections | 5/3/2024 | RARES BODEA |
| Applicant returned to address corrections | 6/4/2024 | RARES BODEA |
| Plan Check Approved | 6/18/2024 | RARES BODEA |
| Issued | 7/15/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/21/2023 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 7/21/2023 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 7/21/2023 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 7/21/2023 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 7/21/2023 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 7/21/2023 | TREVOR QUAN |
| Permit | Cleared | 7/21/2023 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 7/26/2023 | TREVOR QUAN |
| Trees in Parkway | Cleared | 9/12/2023 | ADALBERTO VERA |
| Low Impact Development | Cleared | 12/21/2023 | TRISH PARAS |
| Roof/Waste drainage to street | Cleared | 1/6/2024 | STEVEN JIN |
| Distance to fire station | Cleared | 2/29/2024 | JOHN CONNEALLY |
| Hydrant and Access approval | Cleared | 2/29/2024 | JOHN CONNEALLY |
| Work Adjacent to Public Way | Cleared | 4/22/2024 | JOSE RODRIGUEZ |
| Excavation more than 5-ft deep | Cleared | 5/3/2024 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 5/3/2024 | RARES BODEA |
| Grading Pre-Inspection | Cleared | 5/3/2024 | RARES BODEA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Oruncakciel,, Sayat; Lic. No.: C77182 | 15445 VENTURA BLVD 25 SHERMAN OAKS, CA 91403 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/18/2024 | Partial Inspection | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 11/14/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Piling/Pier/Caisson | 11/14/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Piling/Pier/Caisson | 11/18/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 1/24/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 3/24/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 3/26/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Reinforced Masonry Frame | 4/22/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 5/1/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 5/5/2025 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 5/28/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Underground Mechanical | 5/28/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Deputy Reinf. Concrete | 6/17/2025 | Conditional Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 6/20/2025 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 6/20/2025 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Deputy Other (see comments) | 7/31/2025 | Conditional Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2025 | No Access for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2025 | Partial Approval | WILLIAM SIERRA |
| Underground Mechanical | 9/26/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Underground Mechanical | 10/2/2025 | Partial Approval | FREDDIE RIVERA |
| Interior/Exterior Lathing | 12/18/2025 | Partial Approval | FREDDIE RIVERA |
| Interior/Exterior Lathing | 12/23/2025 | Partial Approval | HAMIK HARTOUNIAN |
| HVAC-Rough | 1/27/2026 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 1/27/2026 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 2/13/2026 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 2/13/2026 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 2/17/2026 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 2/17/2026 | Approved | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 2/17/2026 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 3/13/2026 | Approved | HAMIK HARTOUNIAN |
| Insulation | 3/20/2026 | Corrections Issued | FREDDIE RIVERA |
| Shower Pan | 3/26/2026 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 4/1/2026 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 4/17/2026 | Approved | GEM DE OCAMPO |