410 S EDINBURGH AVE 90048
Certificate Information: 410 S EDINBURGH AVE 90048
- Application / Permit
- 23010-20000-02501
- Plan Check / Job No.
- B23VN07851
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 21'4"X21'4" 2-STORY ADU WITH 1-CAR GARAGE ON PORTION OF 1ST FLOOR PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g) (NFPA 13 D FIRE SPRINKLERS REQUIRED THROUGHOUT) {ALL ELECTRIC BUILDING}
- Permit Issued
- Issued on 5/23/2024
- Issuing Office
- Metro
- Current Status
- Issued on 5/23/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/6/2023 | MARVEL DELACRUZ |
| Corrections Issued | 7/11/2023 | MARVEL DELACRUZ |
| Quality Review Completed | 7/14/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 7/20/2023 | APPLICANT |
| Applicant returned to address corrections | 4/26/2024 | MARVEL DELACRUZ |
| Plan Check Approved | 5/22/2024 | MARVEL DELACRUZ |
| Issued | 5/23/2024 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 11/13/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 11/13/2023 | RIDWAN HARDY |
| Address approval | Cleared | 12/5/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 12/6/2023 | JEANIE LAM |
| Permit | Cleared | 12/6/2023 | JEANIE LAM |
| Sewer availability | Cleared | 12/6/2023 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 1/19/2024 | LAVEON RIDER |
| Miscellaneous | Cleared | 1/23/2024 | NATHAN ROMINE |
| ZI | Cleared | 1/23/2024 | NATHAN ROMINE |
| Low Impact Development (LID) | Cleared | 4/17/2024 | PATRICK LOPEZ |
| Permit | Cleared | 5/1/2024 | CHRISTINA BRACO |
| Roof/Waste drainage to street | Cleared | 5/1/2024 | CHRISTINA BRACO |
Contact Information
| Architect | Mehdizadeh,, Ali; Lic. No.: C38086 | 5809 PARKMOR ROAD CALABASAS, CA 91302 |
| Contractor | Harari Construction Inc; Lic. No.: 1017539-B | 9719 OAKMORE ROAD LOS ANGELES, CA 90035 |
| Engineer | Brown,, Patrick John; Lic. No.: C45526 | 7 STARLING LAGUNA BEACH, CA 92656 |
| Engineer | Song,, Zhenyu Michael; Lic. No.: S5266 | 12631 IMPERIAL HWY F-230 SANTA FE SPRINGS, CA 90670 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/28/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| METHANE-Subgrade | 6/28/2024 | Corrections Issued | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 7/2/2024 | Approved | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2024 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2024 | Partial Approval | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 8/7/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2024 | Corrections Issued | MEL KHACHATOURIAN |
| HVAC-Rough | 8/7/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 8/7/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Special/Order Compliance | 8/7/2024 | Approved | DANIEL VERA |
| BUILDING-Rough-Frame | 8/15/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 8/15/2024 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Gas Test | 8/15/2024 | Approved | MEL KHACHATOURIAN |
| Green Building Rough | 8/15/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| HVAC-Rough | 8/15/2024 | Partial Approval | MEL KHACHATOURIAN |
| METHANE-Rough | 8/15/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 8/15/2024 | Partial Approval | MEL KHACHATOURIAN |
| Special/Order Compliance | 8/15/2024 | Not Ready for Inspection | DANIEL VERA |
| Verify Sprinkler Sign Off | 8/15/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 9/10/2024 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Rough | 9/10/2024 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 9/10/2024 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 9/13/2024 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 9/30/2024 | Not Ready for Inspection | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2024 | Not Ready for Inspection | SEAN HAUPT |
| METHANE-Rough | 9/30/2024 | Not Ready for Inspection | SEAN HAUPT |
| PLUMBING-Rough | 9/30/2024 | Corrections Issued | SEAN HAUPT |
| Underground Mechanical | 9/30/2024 | Corrections Issued | SEAN HAUPT |
| Verify Sprinkler Sign Off | 9/30/2024 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 10/7/2024 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2024 | Approved | MEL KHACHATOURIAN |
| Green Building Rough | 10/7/2024 | Approved | MEL KHACHATOURIAN |
| METHANE-Rough | 10/7/2024 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 10/7/2024 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 10/15/2024 | Approved | MEL KHACHATOURIAN |
| Insulation | 10/15/2024 | Partial Approval | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 10/15/2024 | Partial Approval | MEL KHACHATOURIAN |
| Shower Pan | 10/15/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Drywall Nailing | 10/22/2024 | Approved | MEL KHACHATOURIAN |
| Shower Pan | 10/22/2024 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 10/24/2024 | Partial Approval | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 11/4/2024 | Corrections Issued | SEAN HAUPT |
| ELECTRICAL-Final | 3/26/2025 | Corrections Issued | EVAN COOPER |
| HVAC-Final | 3/26/2025 | Corrections Issued | EVAN COOPER |
| PLUMBING-Final | 3/26/2025 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 4/8/2025 | Approved | EVAN COOPER |
| HVAC-Final | 4/8/2025 | Approved | EVAN COOPER |
| Final | 7/28/2025 | OK for TCO | EVAN COOPER |
| Footing/Foundation/Slab | 7/28/2025 | Approved | EVAN COOPER |
| Green Building Final | 7/28/2025 | Approved | EVAN COOPER |
| METHANE-Barrier | 7/28/2025 | Approved | EVAN COOPER |
| METHANE-Subgrade | 7/28/2025 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 7/28/2025 | SGSOV Approved | EVAN COOPER |
| Service/Power Release | 7/28/2025 | Approved | EVAN COOPER |
| Smoke Detectors | 7/28/2025 | Approved | EVAN COOPER |