10007 N FORBES AVE 91343
Certificate Information: 10007 N FORBES AVE 91343
- Application / Permit
- 23010-20000-02490
- Plan Check / Job No.
- B23VN07822
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY (34'-4"x17'-6"), 1200 SQFT DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)(d)
- Permit Issued
- Issued on 4/15/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/20/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/29/2023 | PETER MOSESIAN |
| Corrections Issued | 7/5/2023 | PETER MOSESIAN |
| Quality Review Completed | 7/12/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 7/18/2023 | APPLICANT |
| Plan Check Approved | 12/7/2023 | PETER MOSESIAN |
| Issued | 4/15/2024 | APPLICANT |
| CofO in Progress | 1/12/2026 | CHRISTOPHER ROJAS |
| Permit Finaled | 1/20/2026 | RUBEN SALAS |
| CofO Issued | 1/20/2026 | RUBEN SALAS |
| Permit Finaled | 1/20/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/3/2023 | MANUEL TEJADA |
| Address approval | Cleared | 8/31/2023 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/1/2023 | ROMAN GUTIERREZ |
| Construction near power lines | Cleared | 11/3/2023 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 11/20/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 12/6/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 12/6/2023 | CARLOS AGUILERA |
| Public Works-Highway Ded. | Cleared | 12/6/2023 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 2999 OVERLAND AVE STE 103 LOS ANGELES, CA 90064 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/11/2024 | Partial Approval | JAVIER RAMOS JR |
| Sewer | 9/11/2024 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 9/13/2024 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 9/13/2024 | Partial Inspection | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2024 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 10/21/2024 | Partial Approval | MATTHEW NELSON |
| Deputy Wood Construction | 10/21/2024 | Conditional Approval | ROBERT GOLD |
| Green Building Rough | 10/21/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 10/21/2024 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 11/1/2024 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 11/1/2024 | Partial Inspection | JAVIER RAMOS JR |
| Underground Mechanical | 11/1/2024 | Approved | JAVIER RAMOS JR |
| Wood Frame | 11/5/2024 | No Access for Inspection | RAUL OLAGI |
| BUILDING-Rough-Frame | 11/25/2024 | Partial Approval | JAVIER RAMOS JR |
| Green Building Rough | 11/25/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 11/25/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| Insulation | 11/25/2024 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 11/25/2024 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 11/25/2024 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 12/13/2024 | Approved | LOUIS ESCOTO |
| Insulation | 12/13/2024 | Approved | LOUIS ESCOTO |
| Interior/Exterior Lathing | 12/13/2024 | Not Ready for Inspection | LOUIS ESCOTO |
| BUILDING-Rough-Frame | 8/15/2025 | Approved | NICHOLAS TROWBRIDGE |
| Final | 8/15/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Final | 8/15/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 8/15/2025 | SGSOV Not Ready | NICHOLAS TROWBRIDGE |
| Service/Power Release | 8/15/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 8/15/2025 | Approved | NICHOLAS TROWBRIDGE |
| Verify Sprinkler Sign Off | 8/15/2025 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Final | 12/30/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 12/30/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 12/30/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 12/30/2025 | SGSOV Not Required | CHRISTOPHER ROJAS |
| Service/Power Release | 12/30/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 1/12/2026 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Green Building Final | 1/12/2026 | Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 1/12/2026 | Approved | CHRISTOPHER ROJAS |