10007 N FORBES AVE 91343

Certificate Information: 10007 N FORBES AVE 91343

Application / Permit
23010-20000-02490
Plan Check / Job No.
B23VN07822
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY (34'-4"x17'-6"), 1200 SQFT DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)(d)
Permit Issued
Issued on 4/15/2024
Issuing Office
Valley
Current Status
CofO Issued on 1/20/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/13/2023 APPLICANT
Assigned to Plan Check Engineer 6/29/2023 PETER MOSESIAN
Corrections Issued 7/5/2023 PETER MOSESIAN
Quality Review Completed 7/12/2023 OMID HEDAYAT
Building Plans Picked Up 7/18/2023 APPLICANT
Plan Check Approved 12/7/2023 PETER MOSESIAN
Issued 4/15/2024 APPLICANT
CofO in Progress 1/12/2026 CHRISTOPHER ROJAS
Permit Finaled 1/20/2026 RUBEN SALAS
CofO Issued 1/20/2026 RUBEN SALAS
Permit Finaled 1/20/2026 RUBEN SALAS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/3/2023 MANUEL TEJADA
Address approval Cleared 8/31/2023 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 9/1/2023 ROMAN GUTIERREZ
Construction near power lines Cleared 11/3/2023 RIDWAN HARDY
Low Impact Development (LID) Cleared 11/20/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 12/6/2023 LEE GUILBEAUX
Sewer availability Cleared 12/6/2023 CARLOS AGUILERA
Public Works-Highway Ded. Cleared 12/6/2023 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Erdelyi,, Peter Tibor; Lic. No.: C26962 2999 OVERLAND AVE STE 103      LOS ANGELES, CA 90064

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/11/2024 Partial Approval JAVIER RAMOS JR
Sewer 9/11/2024 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 9/13/2024 Approved JAVIER RAMOS JR
Underground Mechanical 9/13/2024 Partial Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 9/20/2024 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 10/21/2024 Partial Approval MATTHEW NELSON
Deputy Wood Construction 10/21/2024 Conditional Approval ROBERT GOLD
Green Building Rough 10/21/2024 Not Ready for Inspection MATTHEW NELSON
Verify Sprinkler Sign Off 10/21/2024 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Rough 11/1/2024 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 11/1/2024 Approved JAVIER RAMOS JR
HVAC-Rough 11/1/2024 Partial Inspection JAVIER RAMOS JR
Underground Mechanical 11/1/2024 Approved JAVIER RAMOS JR
Wood Frame 11/5/2024 No Access for Inspection RAUL OLAGI
BUILDING-Rough-Frame 11/25/2024 Partial Approval JAVIER RAMOS JR
Green Building Rough 11/25/2024 Approved JAVIER RAMOS JR
HVAC-Rough 11/25/2024 Not Ready for Inspection JAVIER RAMOS JR
Insulation 11/25/2024 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 11/25/2024 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 11/25/2024 Approved JAVIER RAMOS JR
Drywall Nailing 12/13/2024 Approved LOUIS ESCOTO
Insulation 12/13/2024 Approved LOUIS ESCOTO
Interior/Exterior Lathing 12/13/2024 Not Ready for Inspection LOUIS ESCOTO
BUILDING-Rough-Frame 8/15/2025 Approved NICHOLAS TROWBRIDGE
Final 8/15/2025 Corrections Issued NICHOLAS TROWBRIDGE
Green Building Final 8/15/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 8/15/2025 SGSOV Not Ready NICHOLAS TROWBRIDGE
Service/Power Release 8/15/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Smoke Detectors 8/15/2025 Approved NICHOLAS TROWBRIDGE
Verify Sprinkler Sign Off 8/15/2025 Approved NICHOLAS TROWBRIDGE
ELECTRICAL-Final 12/30/2025 Corrections Issued CHRISTOPHER ROJAS
Final 12/30/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 12/30/2025 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 12/30/2025 SGSOV Not Required CHRISTOPHER ROJAS
Service/Power Release 12/30/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Final 1/12/2026 OK to Issue CofO CHRISTOPHER ROJAS
Green Building Final 1/12/2026 Approved CHRISTOPHER ROJAS
Service/Power Release 1/12/2026 Approved CHRISTOPHER ROJAS