6963 N LURLINE AVE 91306

Certificate Information: 6963 N LURLINE AVE 91306

Application / Permit
23010-20000-02454
Plan Check / Job No.
B23VN07693
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: New 1-story Accessory Dwelling Unit (34'-6" x 25'-6") per LAMC 12.22 A.33(c)-(d)
Permit Issued
Issued on 12/27/2023
Issuing Office
Current Status
CofO Issued on 8/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/11/2023 APPLICANT
Assigned to Plan Check Engineer 6/16/2023 VAHAN JIVALAGIAN
Corrections Issued 6/29/2023 VAHAN JIVALAGIAN
Quality Review Completed 7/5/2023 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 7/12/2023 VAHAN JIVALAGIAN
Applicant returned to address corrections 11/15/2023 VAHAN JIVALAGIAN
Applicant returned to address corrections 11/29/2023 VAHAN JIVALAGIAN
Plan Check Approved 12/22/2023 VAHAN JIVALAGIAN
No Progress 12/22/2023 VAHAN JIVALAGIAN
Plan Check Approved 12/22/2023 VAHAN JIVALAGIAN
Issued 12/27/2023 APPLICANT
CofO in Progress 8/14/2024 ALEXANDER HANDY
Permit Finaled 8/19/2024 JOHN JANSON
CofO Issued 8/19/2024 JOHN JANSON
Permit Finaled 8/19/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/27/2023 LEE GUILBEAUX
ZI Cleared 7/6/2023 NOAH MCCOY
Low Impact Development (LID) Cleared 8/28/2023 MEGAN PINKUS
Roof/Waste drainage to street Cleared 8/31/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 9/19/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 9/19/2023 DAGOVERTO GUERRERO
Construction within easement Cleared 10/3/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 1/10/2024 Partial Approval ALEXANDER HANDY
PLUMBING-Rough 1/17/2024 Partial Approval HORACE FULTZ
Footing/Foundation/Slab 1/29/2024 Approved ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 2/20/2024 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 3/27/2024 Approved ALEXANDER HANDY
ELECTRICAL-Rough 3/27/2024 Approved ALEXANDER HANDY
Green Building Rough 3/27/2024 Approved ALEXANDER HANDY
HVAC-Rough 3/27/2024 Not Ready for Inspection ALEXANDER HANDY
Interior/Exterior Lathing 3/27/2024 Partial Approval ALEXANDER HANDY
PLUMBING-Rough 3/27/2024 Approved ALEXANDER HANDY
Verify Sprinkler Sign Off 3/27/2024 Approved ALEXANDER HANDY
Insulation 4/3/2024 Approved ALEXANDER HANDY
Shower Pan 4/3/2024 Approved ALEXANDER HANDY
Drywall Nailing 4/9/2024 Approved ALEXANDER HANDY
Interior/Exterior Lathing 4/9/2024 Approved ALEXANDER HANDY
Final 7/12/2024 Corrections Issued ALEXANDER HANDY
Green Building Final 7/12/2024 Not Ready for Inspection ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 7/12/2024 SGSOV No Gas ALEXANDER HANDY
Service/Power Release 7/12/2024 Approved ALEXANDER HANDY
Smoke Detectors 7/12/2024 Approved ALEXANDER HANDY
Final 7/29/2024 Not Ready for Inspection ALEXANDER HANDY
Green Building Final 7/29/2024 Approved ALEXANDER HANDY
ELECTRICAL-Final 8/13/2024 Approved ALEXANDER HANDY
Final 8/13/2024 OK to Issue CofO ALEXANDER HANDY
HVAC-Final 8/13/2024 Approved ALEXANDER HANDY
PLUMBING-Final 8/13/2024 Approved ALEXANDER HANDY
Service/Power Release 8/13/2024 Approved ALEXANDER HANDY