8126 N MOORCROFT AVE 91304

Certificate Information: 8126 N MOORCROFT AVE 91304

Application / Permit
23010-20000-02446
Plan Check / Job No.
B23VN07687
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 24'11" X 38' IRREGULARLY SHAPED DETACHED ACCESSORY DWELLING UNIT (860 SF) WITH 3' X 5' ATTACHED COVERED PORCH PER LAMC 12.22 A.33(c) and (d).
Permit Issued
Issued on 10/23/2023
Issuing Office
Current Status
CofO Issued on 9/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/23/2023 APPLICANT
Assigned to Plan Check Engineer 6/28/2023 ISIS ARGUETA
Corrections Issued 6/29/2023 ISIS ARGUETA
Applicant returned to address corrections 9/13/2023 MADISON ODELL
Applicant returned to address corrections 9/16/2023 MADISON ODELL
Applicant returned to address corrections 10/19/2023 MOHAMMAD ESMAILI
Plan Check Approved 10/21/2023 MOHAMMAD ESMAILI
Issued 10/23/2023 APPLICANT
CofO in Progress 8/28/2025 JEFFREY HARTLINE
Permit Finaled 9/6/2025 MICHAEL PELHAM
CofO Issued 9/6/2025 MICHAEL PELHAM
Permit Finaled 9/6/2025 MICHAEL PELHAM

Permit Application Clearance Information

ZA Case Cleared 7/11/2023 DAVID URITA
Address approval Cleared 7/28/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 8/22/2023 LEE GUILBEAUX
Sewer availability Cleared 8/22/2023 LEE GUILBEAUX
Low Impact Development (LID) Cleared 9/12/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 9/26/2023 LEE GUILBEAUX
Construction near power lines Cleared 10/14/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Chan,, Terence Kahing; Lic. No.: C48893 3579 E FOOTHILL BLVD   #206    PASADENA, CA 91107

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/14/2023 Approved JEFFREY HARTLINE
Pre-Inspection 11/14/2023 Approved JEFFREY HARTLINE
PLUMBING-Rough 12/26/2023 Conditional Approval CHRIS CHRISTENSEN
Underground Mechanical 12/26/2023 Partial Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 1/2/2024 Not Ready for Inspection CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 1/5/2024 Not Ready for Inspection KRISTEN CAUSEY
Footing/Foundation/Slab 1/5/2024 Not Ready for Inspection KRISTEN CAUSEY
Excavation/Setback/Form/Re-Bar 1/10/2024 Approved JEFFREY HARTLINE
ELECTRICAL-Rough 5/23/2024 No Access for Inspection JEFFREY HARTLINE
PLUMBING-Rough 5/23/2024 No Access for Inspection JEFFREY HARTLINE
ELECTRICAL-Rough 5/24/2024 Not Ready for Inspection JEFFREY HARTLINE
PLUMBING-Rough 5/24/2024 Not Ready for Inspection JEFFREY HARTLINE
BUILDING-Rough-Frame 6/5/2024 Not Ready for Inspection JEFFREY HARTLINE
ELECTRICAL-Rough 6/5/2024 Not Ready for Inspection JEFFREY HARTLINE
Green Building Rough 6/5/2024 Not Ready for Inspection JEFFREY HARTLINE
HVAC-Rough 6/5/2024 Not Ready for Inspection JEFFREY HARTLINE
PLUMBING-Rough 6/5/2024 Not Ready for Inspection JEFFREY HARTLINE
Verify Sprinkler Sign Off 6/5/2024 Not Ready for Inspection JEFFREY HARTLINE
ELECTRICAL-Rough 6/12/2024 Not Ready for Inspection JEFFREY HARTLINE
PLUMBING-Rough 6/12/2024 Not Ready for Inspection JEFFREY HARTLINE
ELECTRICAL-Rough 6/17/2024 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 6/17/2024 Partial Approval JEFFREY HARTLINE
PLUMBING-Rough 6/17/2024 Approved JEFFREY HARTLINE
Insulation 7/24/2024 Not Ready for Inspection CHRIS CHRISTENSEN
Insulation 7/25/2024 Conditional Approval ALEXANDER HANDY
BUILDING-Rough-Frame 7/29/2024 Approved JEFFREY HARTLINE
Green Building Rough 7/29/2024 Approved JEFFREY HARTLINE
HVAC-Rough 7/29/2024 Corrections Issued JEFFREY HARTLINE
Verify Sprinkler Sign Off 7/29/2024 Approved JEFFREY HARTLINE
HVAC-Rough 8/8/2024 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 8/8/2024 Partial Approval JEFFREY HARTLINE
Shower Pan 8/8/2024 Approved JEFFREY HARTLINE
Drywall Nailing 8/22/2024 Approved JEFFREY HARTLINE
Final 4/28/2025 Corrections Issued JEFFREY HARTLINE
Footing/Foundation/Slab 4/28/2025 Approved JEFFREY HARTLINE
Green Building Final 4/28/2025 Not Ready for Inspection JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 4/28/2025 SGSOV Not Required JEFFREY HARTLINE
Service/Power Release 4/28/2025 Not Ready for Inspection JEFFREY HARTLINE
Smoke Detectors 4/28/2025 Not Ready for Inspection JEFFREY HARTLINE
Final 6/25/2025 Corrections Issued JEFFREY HARTLINE
Green Building Final 6/25/2025 Not Ready for Inspection JEFFREY HARTLINE
Service/Power Release 6/25/2025 Not Ready for Inspection JEFFREY HARTLINE
Smoke Detectors 6/25/2025 Approved JEFFREY HARTLINE
Final 8/25/2025 Not Ready for Inspection JEFFREY HARTLINE
Green Building Final 8/25/2025 Approved JEFFREY HARTLINE
Service/Power Release 8/25/2025 Not Ready for Inspection JEFFREY HARTLINE
ELECTRICAL-Final 8/27/2025 Approved JEFFREY HARTLINE
Final 8/27/2025 OK to Issue CofO JEFFREY HARTLINE
HVAC-Final 8/27/2025 Approved JEFFREY HARTLINE
PLUMBING-Final 8/27/2025 Approved JEFFREY HARTLINE
Service/Power Release 8/27/2025 Approved JEFFREY HARTLINE