13102 N FELLOWS AVE 91342
Certificate Information: 13102 N FELLOWS AVE 91342
- Application / Permit
- 23010-20000-02439
- Plan Check / Job No.
- B23VN07668
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 28'-4" X 44'-6" ADU W/ ATTACHED 21'-0" X 10'-0" COVERED PATIO PER LAMC 12.22 A.33(c) and (d). WORK PER ENGINEERING.
- Permit Issued
- Issued on 7/24/2023
- Issuing Office
- Current Status
- CofO Issued on 9/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/14/2023 | SERGIO MUNIZ |
| Corrections Issued | 6/15/2023 | SERGIO MUNIZ |
| Building Plans Picked Up | 6/27/2023 | APPLICANT |
| Plan Check Approved | 7/21/2023 | ISIS ARGUETA |
| Plan Check Approved | 7/21/2023 | ISIS ARGUETA |
| Issued | 7/24/2023 | APPLICANT |
| CofO in Progress | 9/11/2024 | KEVIN BERBERYAN |
| CofO Issued | 9/24/2024 | DANIEL ORRANTE |
| Permit Finaled | 9/24/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/27/2023 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 6/28/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/28/2023 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 6/29/2023 | WALTER RAMIREZ |
| Low Impact Development (LID) | Cleared | 7/17/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 7/18/2023 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 7/18/2023 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/7/2023 | Corrections Issued | KEVIN BERBERYAN |
| Special/Order Compliance | 9/7/2023 | Partial Inspection | ROBERT GOLD |
| Underground Mechanical | 9/7/2023 | Corrections Issued | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 9/9/2023 | Approved | SEAN HAUPT |
| Underground Mechanical | 9/9/2023 | Approved | SEAN HAUPT |
| Underground Mechanical | 9/9/2023 | Off-Hour Fees Due | |
| Excavation/Setback/Form/Re-Bar | 9/12/2023 | Corrections Issued | ROBERT GOLD |
| Underground Mechanical | 9/12/2023 | Not Ready for Inspection | ROBERT GOLD |
| Footing/Foundation/Slab | 9/14/2023 | Approved | ROBERT GOLD |
| BUILDING-Rough-Frame | 10/10/2023 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 10/10/2023 | Corrections Issued | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2023 | Approved | KEVIN BERBERYAN |
| Gas Test | 10/10/2023 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 10/10/2023 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 10/10/2023 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 10/10/2023 | Conditional Approval | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 10/17/2023 | Approved | KEVIN BERBERYAN |
| Insulation | 10/17/2023 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 10/17/2023 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 11/1/2023 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 11/1/2023 | Approved | KEVIN BERBERYAN |
| Shower Pan | 11/1/2023 | Approved | KEVIN BERBERYAN |
| Final | 1/19/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 1/19/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 1/19/2024 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Service/Power Release | 1/19/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 1/19/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 1/25/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Final | 1/25/2024 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 1/25/2024 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Service/Power Release | 1/25/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 1/25/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 2/1/2024 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 2/1/2024 | SGSOV Not Ready | MISAEL ESPARZA |
| Service/Power Release | 2/1/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 2/6/2024 | Conditional Approval | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 2/6/2024 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 2/6/2024 | Approved | MISAEL ESPARZA |
| Final | 9/11/2024 | OK to Issue CofO | KEVIN BERBERYAN |