10519 N GREENBURN AVE 91040
Certificate Information: 10519 N GREENBURN AVE 91040
- Application / Permit
- 23010-20000-02430
- Plan Check / Job No.
- B23VN07636
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 28'-6" X 26'-5" ONE STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK DONE PER WFPP. see comments
- Permit Issued
- Issued on 5/29/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/14/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 6/15/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 6/16/2023 | APPLICANT |
| Applicant returned to address corrections | 7/12/2023 | RAMA DABADGE |
| Applicant returned to address corrections | 10/19/2023 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 10/27/2023 | ISIS ARGUETA |
| Applicant returned to address corrections | 11/16/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 11/22/2023 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 1/19/2024 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 5/10/2024 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 5/28/2024 | LUISANGEL VALENZUELA |
| Issued | 5/29/2024 | APPLICANT |
| CofO in Progress | 11/17/2025 | DAVID MATSON |
| Permit Finaled | 11/20/2025 | RUBEN SALAS |
| CofO Issued | 11/20/2025 | RUBEN SALAS |
| Permit Finaled | 11/20/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/20/2023 | TAL SHEMEN |
| Sewer availability | Cleared | 10/25/2023 | TAL SHEMEN |
| Address approval | Cleared | 10/27/2023 | EDGAR ALCARAZ |
| GPI Written Notices | Cleared | 11/16/2023 | ARTIN ZARUKIAN |
| Grading Pre-Inspection | Cleared | 11/16/2023 | ARTIN ZARUKIAN |
| Low Impact Development (LID) | Cleared | 5/8/2024 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 5/8/2024 | JOHN LIN |
| Hold | Cleared | 6/12/2024 | TERESA RIVAS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 5/31/2024 | Not Ready for Inspection | WILLIAM WREN |
| PLUMBING-Rough | 5/31/2024 | Partial Approval | WILLIAM WREN |
| Footing/Foundation/Slab | 6/14/2024 | Corrections Issued | WILLIAM WREN |
| Footing/Foundation/Slab | 6/24/2024 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2024 | Partial Approval | WILLIAM WREN |
| BUILDING-Rough-Frame | 7/26/2024 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 7/26/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Rough | 7/26/2024 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 7/26/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 7/26/2024 | Partial Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 8/1/2024 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 8/1/2024 | Approved | MATTHEW NELSON |
| HVAC-Rough | 8/1/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Interior/Exterior Lathing | 8/1/2024 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Rough | 8/1/2024 | Partial Approval | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 8/1/2024 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 8/6/2024 | Not Ready for Inspection | WILLIAM WREN |
| Gas Test | 8/6/2024 | Corrections Issued | WILLIAM WREN |
| Interior/Exterior Lathing | 8/6/2024 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 8/6/2024 | Approved | WILLIAM WREN |
| Insulation | 8/9/2024 | Corrections Issued | WILLIAM WREN |
| Insulation | 8/12/2024 | Corrections Issued | WILLIAM WREN |
| Drywall Nailing | 8/26/2024 | Corrections Issued | LOUIS ESCOTO |
| Drywall Nailing | 9/3/2024 | Not Ready for Inspection | WILLIAM WREN |
| BUILDING-Rough-Frame | 2/18/2025 | Approved | WILLIAM WREN |
| Drywall Nailing | 2/18/2025 | Approved | WILLIAM WREN |
| Final | 2/18/2025 | Corrections Issued | WILLIAM WREN |
| Green Building Final | 2/18/2025 | Not Ready for Inspection | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 2/18/2025 | SGSOV Not Required | WILLIAM WREN |
| Service/Power Release | 2/18/2025 | Not Ready for Inspection | WILLIAM WREN |
| Smoke Detectors | 2/18/2025 | Not Ready for Inspection | WILLIAM WREN |
| Verify Sprinkler Sign Off | 2/18/2025 | Approved | WILLIAM WREN |
| Final | 2/28/2025 | Corrections Issued | LOUIS ESCOTO |
| Green Building Final | 2/28/2025 | Not Ready for Inspection | LOUIS ESCOTO |
| Service/Power Release | 2/28/2025 | Not Ready for Inspection | LOUIS ESCOTO |
| Smoke Detectors | 2/28/2025 | Corrections Issued | LOUIS ESCOTO |
| PLUMBING-Final | 5/20/2025 | Not Ready for Inspection | WILLIAM WREN |
| Final | 9/24/2025 | OK to Issue CofO | WILLIAM WREN |
| Green Building Final | 9/24/2025 | Approved | WILLIAM WREN |
| Service/Power Release | 9/24/2025 | Not Required | WILLIAM WREN |
| Smoke Detectors | 9/24/2025 | Approved | WILLIAM WREN |