633 S BURLINGAME AVE 90049

Certificate Information: 633 S BURLINGAME AVE 90049

Application / Permit
23010-20000-02424
Plan Check / Job No.
B23VN07612
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW 18' X 14'-9" DETACHED CABANA . WORK DONE PER ENGINEER.
Permit Issued
Issued on 10/3/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/8/2023 APPLICANT
Assigned to Plan Check Engineer 6/14/2023 SERGIO MUNIZ
Corrections Issued 6/15/2023 SERGIO MUNIZ
Building Plans Picked Up 6/27/2023 APPLICANT
Plan Check Approved 9/21/2023 MIROOSH KHACHATOORIAN
Issued 10/3/2023 APPLICANT
CofO in Progress 7/13/2024 CHRISTOPHER WILSON
Permit Finaled 7/16/2024 DANIEL ORRANTE
CofO Issued 7/16/2024 DANIEL ORRANTE
Permit Finaled 7/16/2024 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/16/2023 JASON NG
Eng Process Fee Ord 176,300 Cleared 8/17/2023 JASON NG
Specific Plan Cleared 9/5/2023 JOSHUA JONES

Contact Information

Contractor Local Construction Remodeling; Lic. No.: 966738-B 14901 TUBA STREET      MISSION HILLS, CA 91345
Contractor Owner-Builder       ,
Engineer Motavvef,, Nasser; Lic. No.: C40977 15335 MORRISON ST 370      SHERMAN OAKS, CA 91403

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/12/2023 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 12/12/2023 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 12/26/2023 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 1/2/2024 Not Ready for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 1/5/2024 Not Ready for Inspection BEN MOLSTAD
Footing/Foundation/Slab 1/12/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/7/2024 Corrections Issued STEPHANIE SWANSON
BUILDING-Rough-Frame 3/20/2024 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 3/20/2024 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 3/20/2024 Approved CARLOS MATAMOROS
HVAC-Rough 3/20/2024 Approved CARLOS MATAMOROS
PLUMBING-Rough 3/20/2024 Approved CARLOS MATAMOROS
Verify Sprinkler Sign Off 3/20/2024 Approved CARLOS MATAMOROS
Insulation 4/1/2024 Conditional Approval ASHLEY THOMPSON
Interior/Exterior Lathing 4/1/2024 Partial Approval ASHLEY THOMPSON
Drywall Nailing 4/8/2024 Approved ASHLEY THOMPSON
Sewer 5/1/2024 Approved ARAM AVEDISIAN
Underground Mechanical 5/1/2024 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Final 7/2/2024 Corrections Issued KIRK SANDERS
HVAC-Final 7/2/2024 Approved KIRK SANDERS
PLUMBING-Final 7/2/2024 Approved KIRK SANDERS
ELECTRICAL-Final 7/5/2024 Approved EVAN COOPER
Final 7/10/2024 Corrections Issued KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 7/10/2024 SGSOV Approved KIRK SANDERS
Service/Power Release 7/10/2024 Approved KIRK SANDERS
Smoke Detectors 7/10/2024 Approved KIRK SANDERS
Final 7/12/2024 OK to Issue CofO CHRISTOPHER WILSON