15255 W TUBA ST 91345

Certificate Information: 15255 W TUBA ST 91345

Application / Permit
23010-20000-02416
Plan Check / Job No.
B23VN07575
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 47' x 15' TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENGINEERING
Permit Issued
Issued on 4/2/2024
Issuing Office
Valley
Current Status
CofO Issued on 6/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/8/2023 APPLICANT
Assigned to Plan Check Engineer 6/29/2023 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 7/6/2023 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 7/6/2023 OMID HEDAYAT
Building Plans Picked Up 7/7/2023 APPLICANT
Plan Check Approved 4/2/2024 SEWADA ZADOORAN MILAGARDI
Issued 4/2/2024 APPLICANT
CofO in Progress 10/20/2025 JENNIFER RABUCHIN
No Progress 10/22/2025 RAUL OLAGI
CofO in Progress 10/22/2025 RAUL OLAGI
CofO in Progress 10/22/2025 RAUL OLAGI
No Progress 3/11/2026 JOSE AVILA
CofO in Progress 3/11/2026 JOSE AVILA
CofO Issued 6/2/2026 RUBEN SALAS
Permit Finaled 6/2/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/12/2023 NIKKI ZULUETA
Miscellaneous Cleared 7/19/2023 NIKKI ZULUETA
Hydrant and Access approval Cleared 8/19/2023 JOHN CONNEALLY
Construction near power lines Cleared 9/22/2023 RIDWAN HARDY
Construction within easement Cleared 9/22/2023 RIDWAN HARDY
Low Impact Development (LID) Cleared 2/20/2024 SAMUEL LINN
Roof/Waste drainage to street Cleared 2/23/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 2/29/2024 CARLOS AGUILERA
Sewer availability Cleared 2/29/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Van, Valkenburg, John; Lic. No.: C74939 13259 KISMET AVE      SYLMAR, CA 91342

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/24/2024 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 5/24/2024 Partial Approval JENNIFER RABUCHIN
Pre-Inspection 5/24/2024 Partial Approval JENNIFER RABUCHIN
Sewer 5/24/2024 Approved JENNIFER RABUCHIN
Underground Mechanical 5/24/2024 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 6/12/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 9/10/2024 Corrections Issued JENNIFER RABUCHIN
Wood Frame 9/10/2024 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 10/7/2024 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 10/7/2024 Approved JENNIFER RABUCHIN
Green Building Rough 10/7/2024 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 10/7/2024 Approved JENNIFER RABUCHIN
Verify Sprinkler Sign Off 10/7/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 10/18/2024 Approved JENNIFER RABUCHIN
Grounding or Bonding 10/18/2024 Partial Approval JENNIFER RABUCHIN
Interior/Exterior Lathing 11/22/2024 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 12/6/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Insulation 12/6/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 12/11/2024 Approved JENNIFER RABUCHIN
Green Building Rough 12/11/2024 Approved JENNIFER RABUCHIN
HVAC-Rough 12/11/2024 Approved JENNIFER RABUCHIN
Insulation 12/11/2024 Approved JENNIFER RABUCHIN
Drywall Nailing 12/24/2024 Approved LOUIS ESCOTO
Interior/Exterior Lathing 12/24/2024 Approved LOUIS ESCOTO
Shower Pan 12/24/2024 Approved LOUIS ESCOTO
ELECTRICAL-Final 8/5/2025 Corrections Issued JENNIFER RABUCHIN
Final 8/5/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Final 8/5/2025 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 8/5/2025 SGSOV Not Required JENNIFER RABUCHIN
Service/Power Release 8/5/2025 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 8/5/2025 Approved JENNIFER RABUCHIN
Final 9/25/2025 Conditional Approval JENNIFER RABUCHIN
Service/Power Release 9/25/2025 Approved JENNIFER RABUCHIN
Final 10/9/2025 Corrections Issued JENNIFER RABUCHIN
Final 10/15/2025 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Final 10/17/2025 Approved JENNIFER RABUCHIN
Final 10/17/2025 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 10/17/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 10/17/2025 Approved JENNIFER RABUCHIN
Final 3/5/2026 Partial Approval JENNIFER RABUCHIN