8359 N DE GARMO AVE 91352
Certificate Information: 8359 N DE GARMO AVE 91352
- Application / Permit
- 23010-20000-02414
- Plan Check / Job No.
- B23VN07571
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 25' X 45' ONE STORY SFD PER SB 9 WITH ATTACHED 5' X 9' PORCH , NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 8/1/2024
- Issuing Office
- Valley
- Current Status
- Issued on 8/1/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/29/2023 | RARES BODEA |
| Corrections Issued | 7/5/2023 | RARES BODEA |
| Quality Review Completed | 7/7/2023 | STEVEN KIM |
| Building Plans Picked Up | 7/7/2023 | APPLICANT |
| Plan Check Approved | 8/1/2024 | RARES BODEA |
| Issued | 8/1/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/19/2023 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 11/3/2023 | GILBERT URREA |
| Eng Process Fee Ord 176,300 | Cleared | 1/17/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/17/2024 | LEE GUILBEAUX |
| Senate Bill 9 | Cleared | 7/8/2024 | ASHLEY RODARTE |
| Low Impact Development (LID) | Cleared | 7/18/2024 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 7/22/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 7/22/2024 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhang,, Xiaoran; Lic. No.: C78408 | 1675 COLBY AVE APT 4 WEST LOS ANGELES, CA 90025 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/16/2025 | Partial Approval | DAVID ANDERSON |
| Special/Order Compliance | 4/16/2025 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 5/21/2025 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2025 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 3/24/2026 | Approved | DAVID ANDERSON |
| HVAC-Rough | 3/24/2026 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 3/24/2026 | Partial Approval | DAVID ANDERSON |
| PLUMBING-Rough | 3/24/2026 | Approved | DAVID ANDERSON |
| Sewer | 4/3/2026 | Approved | DAVID ANDERSON |
| Underground Mechanical | 4/3/2026 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 4/14/2026 | Approved | DAVID ANDERSON |
| Green Building Rough | 4/14/2026 | Approved | DAVID ANDERSON |
| MERV13>=Rough | 4/14/2026 | Approved | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 4/14/2026 | Approved | DAVID ANDERSON |
| Drywall Nailing | 4/23/2026 | Approved | DAVID ANDERSON |
| Insulation | 4/23/2026 | Approved | DAVID ANDERSON |
| Shower Pan | 5/4/2026 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 5/18/2026 | Approved | DAVID ANDERSON |