600-602 W 53RD ST 90037

Certificate Information: 600-602 W 53RD ST 90037

Application / Permit
23010-20000-02398
Plan Check / Job No.
B23VN07521
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
EPLAN NEW 2-STORY DUPLEX WITH ATTACHED GARAGE
Permit Issued
Issued on 11/28/2023
Issuing Office
Current Status
CofO Issued on 8/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/8/2023 APPLICANT
Assigned to Plan Check Engineer 6/8/2023 SINA KHOSRAVI
Corrections Issued 6/11/2023 SINA KHOSRAVI
Quality Review Completed 6/16/2023 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 10/18/2023 SINA KHOSRAVI
Issued 11/28/2023 APPLICANT
CofO in Progress 8/1/2024 SABAS ALONSO
CofO Issued 8/5/2024 DEROLD HAUFF
Permit Finaled 8/5/2024 DEROLD HAUFF

Permit Application Clearance Information

Trees in Parkway Cleared 6/28/2023 ADALBERTO VERA
Address approval Cleared 7/2/2023 CINDY QI
Permit Cleared 7/2/2023 CINDY QI
Hydrant and Access approval Cleared 7/22/2023 JOHN CONNEALLY
Eng Process Fee Ord 176,300 Cleared 7/27/2023 CINDY QI
Sewer availability Cleared 7/27/2023 CINDY QI
SB8 RUD Cleared 8/29/2023 BLAKE BOULIGNY
Low Impact Development (LID) Cleared 9/22/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 9/28/2023 AMBER CAMPBELL

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/14/2023 Approved SABAS ALONSO
Footing/Foundation/Slab 12/14/2023 Approved SABAS ALONSO
Underground Mechanical 1/4/2024 Partial Approval SABAS ALONSO
Wood Frame 1/4/2024 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 1/5/2024 Partial Approval ALEJANDRO DE ARTOLA
Insulation 1/5/2024 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/11/2024 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 2/14/2024 Approved SABAS ALONSO
ELECTRICAL-Rough 2/29/2024 Approved BRENDAN MORELLI
PLUMBING-Rough 2/29/2024 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 3/1/2024 Approved JEFFREY MEAD
HVAC-Rough 3/1/2024 Corrections Issued JEFFREY MEAD
Verify Sprinkler Sign Off 3/1/2024 Approved JEFFREY MEAD
Insulation 3/6/2024 Approved JOSH MEISTER
Drywall Nailing 3/13/2024 Approved JOSH MEISTER
Interior/Exterior Lathing 3/13/2024 Approved JOSH MEISTER
ELECTRICAL-Final 5/15/2024 Corrections Issued SABAS ALONSO
ELECTRICAL-Final 5/21/2024 Corrections Issued SABAS ALONSO
ELECTRICAL-Final 5/24/2024 Partial Approval SABAS ALONSO
ELECTRICAL-Final 6/7/2024 Corrections Issued CRAIG DAVIS
Final 6/7/2024 Corrections Issued CRAIG DAVIS
HVAC-Final 6/7/2024 Corrections Issued CRAIG DAVIS
PLUMBING-Final 6/7/2024 Corrections Issued CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 6/7/2024 SGSOV Approved CRAIG DAVIS
Service/Power Release 6/7/2024 Partial Inspection CRAIG DAVIS
Smoke Detectors 6/7/2024 Corrections Issued CRAIG DAVIS
ELECTRICAL-Final 7/31/2024 Approved SABAS ALONSO
Final 7/31/2024 OK to Issue CofO SABAS ALONSO
HVAC-Final 7/31/2024 Approved SABAS ALONSO
PLUMBING-Final 7/31/2024 Approved SABAS ALONSO
Service/Power Release 7/31/2024 Approved SABAS ALONSO
Smoke Detectors 7/31/2024 Approved SABAS ALONSO