600-602 W 53RD ST 90037
Certificate Information: 600-602 W 53RD ST 90037
- Application / Permit
- 23010-20000-02398
- Plan Check / Job No.
- B23VN07521
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- EPLAN NEW 2-STORY DUPLEX WITH ATTACHED GARAGE
- Permit Issued
- Issued on 11/28/2023
- Issuing Office
- Current Status
- CofO Issued on 8/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2023 | SINA KHOSRAVI |
| Corrections Issued | 6/11/2023 | SINA KHOSRAVI |
| Quality Review Completed | 6/16/2023 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 10/18/2023 | SINA KHOSRAVI |
| Issued | 11/28/2023 | APPLICANT |
| CofO in Progress | 8/1/2024 | SABAS ALONSO |
| CofO Issued | 8/5/2024 | DEROLD HAUFF |
| Permit Finaled | 8/5/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 6/28/2023 | ADALBERTO VERA |
| Address approval | Cleared | 7/2/2023 | CINDY QI |
| Permit | Cleared | 7/2/2023 | CINDY QI |
| Hydrant and Access approval | Cleared | 7/22/2023 | JOHN CONNEALLY |
| Eng Process Fee Ord 176,300 | Cleared | 7/27/2023 | CINDY QI |
| Sewer availability | Cleared | 7/27/2023 | CINDY QI |
| SB8 RUD | Cleared | 8/29/2023 | BLAKE BOULIGNY |
| Low Impact Development (LID) | Cleared | 9/22/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 9/28/2023 | AMBER CAMPBELL |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: NA81695 | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/14/2023 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 12/14/2023 | Approved | SABAS ALONSO |
| Underground Mechanical | 1/4/2024 | Partial Approval | SABAS ALONSO |
| Wood Frame | 1/4/2024 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Insulation | 1/5/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2024 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 2/29/2024 | Approved | BRENDAN MORELLI |
| PLUMBING-Rough | 2/29/2024 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 3/1/2024 | Approved | JEFFREY MEAD |
| HVAC-Rough | 3/1/2024 | Corrections Issued | JEFFREY MEAD |
| Verify Sprinkler Sign Off | 3/1/2024 | Approved | JEFFREY MEAD |
| Insulation | 3/6/2024 | Approved | JOSH MEISTER |
| Drywall Nailing | 3/13/2024 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 3/13/2024 | Approved | JOSH MEISTER |
| ELECTRICAL-Final | 5/15/2024 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Final | 5/21/2024 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Final | 5/24/2024 | Partial Approval | SABAS ALONSO |
| ELECTRICAL-Final | 6/7/2024 | Corrections Issued | CRAIG DAVIS |
| Final | 6/7/2024 | Corrections Issued | CRAIG DAVIS |
| HVAC-Final | 6/7/2024 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Final | 6/7/2024 | Corrections Issued | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 6/7/2024 | SGSOV Approved | CRAIG DAVIS |
| Service/Power Release | 6/7/2024 | Partial Inspection | CRAIG DAVIS |
| Smoke Detectors | 6/7/2024 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Final | 7/31/2024 | Approved | SABAS ALONSO |
| Final | 7/31/2024 | OK to Issue CofO | SABAS ALONSO |
| HVAC-Final | 7/31/2024 | Approved | SABAS ALONSO |
| PLUMBING-Final | 7/31/2024 | Approved | SABAS ALONSO |
| Service/Power Release | 7/31/2024 | Approved | SABAS ALONSO |
| Smoke Detectors | 7/31/2024 | Approved | SABAS ALONSO |