4828 S MCKINLEY AVE 90011
Certificate Information: 4828 S MCKINLEY AVE 90011
- Application / Permit
- 23010-20000-02396
- Plan Check / Job No.
- B23VN07519
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- EPLAN: NEW 2-STORY DUPLEX WITH ATTACHED GARAGE
- Permit Issued
- Issued on 11/20/2023
- Issuing Office
- Current Status
- CofO Issued on 1/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2023 | TSE MING HUANG |
| Corrections Issued | 6/10/2023 | TSE MING HUANG |
| Quality Review Completed | 6/13/2023 | EUGENE BARBEAU |
| Plan Check Approved | 11/1/2023 | TSE MING HUANG |
| Plan Check Approved | 11/17/2023 | TSE MING HUANG |
| Plan Check Approved | 11/17/2023 | TSE MING HUANG |
| Issued | 11/20/2023 | APPLICANT |
| CofO in Progress | 1/8/2025 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 1/9/2025 | DEROLD HAUFF |
| CofO Issued | 1/9/2025 | DEROLD HAUFF |
| Permit Finaled | 1/9/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/27/2023 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 6/30/2023 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 7/24/2023 | JOHN CONNEALLY |
| Low Impact Development (LID) | Cleared | 9/19/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 9/20/2023 | WALLIE JONG |
| Sewer availability | Cleared | 9/20/2023 | WALLIE JONG |
| SB8 RUD | Cleared | 10/5/2023 | ALYSSA FLORES |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
| Engineer | Madero,, Fidencio; Lic. No.: NA81695 | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/28/2023 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 12/28/2023 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 1/10/2024 | Approved | ALEJANDRO DE ARTOLA |
| Wood Frame | 1/10/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Insulation | 1/11/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 10/15/2024 | Approved | BRENDAN MORELLI |
| PLUMBING-Rough | 10/15/2024 | Corrections Issued | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 10/16/2024 | Partial Approval | MICHAEL LEWIS |
| ELECTRICAL-Rough | 10/16/2024 | Approved | MICHAEL LEWIS |
| Green Building Rough | 10/16/2024 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 10/16/2024 | Approved | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 10/16/2024 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 10/17/2024 | Approved | MICHAEL LEWIS |
| Insulation | 10/17/2024 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 10/23/2024 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 10/23/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 12/16/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 12/19/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 12/31/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 12/31/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 12/31/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 12/31/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 12/31/2024 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 12/31/2024 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 12/31/2024 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 12/31/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 1/7/2025 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Gas Test | 1/7/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 1/7/2025 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 1/7/2025 | Approved | ALEJANDRO DE ARTOLA |