9150 N COLUMBUS AVE 91343
Certificate Information: 9150 N COLUMBUS AVE 91343
- Application / Permit
- 23010-20000-02388
- Plan Check / Job No.
- B23VN07456
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* NEW 31'-5" X 28'-8" IRREGULAR SHAPED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 9/5/2024
- Issuing Office
- Current Status
- CofO Issued on 2/3/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/6/2023 | SELLA BENYAMIN |
| Corrections Issued | 7/13/2023 | SELLA BENYAMIN |
| Quality Review Completed | 7/26/2023 | STEVEN KIM |
| Applicant returned to address corrections | 10/17/2023 | SELLA BENYAMIN |
| Applicant returned to address corrections | 10/31/2023 | SELLA BENYAMIN |
| Applicant returned to address corrections | 1/30/2024 | SELLA BENYAMIN |
| Plan Check Approved | 4/5/2024 | SELLA BENYAMIN |
| Issued | 9/5/2024 | APPLICANT |
| CofO in Progress | 1/2/2026 | VINCENT HANLEY |
| Permit Finaled | 2/3/2026 | RUBEN SALAS |
| Permit Finaled | 2/3/2026 | RUBEN SALAS |
| CofO Issued | 2/3/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/19/2023 | RYAN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 7/24/2023 | RYAN KIM |
| Sewer availability | Cleared | 7/24/2023 | RYAN KIM |
| ZA Case | Cleared | 2/26/2024 | MATHEW QUAN |
| Low Impact Development (LID) | Cleared | 2/28/2024 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 2/29/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | The American Dream Builders Inc; Lic. No.: 1109663-B | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: C93079 | 15445 VENTURA BLVD #63 SHERMAN OAKS, CA 91403 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/17/2024 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Rough | 10/7/2024 | Partial Approval | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 10/15/2024 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 10/15/2024 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 10/18/2024 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 11/6/2024 | Corrections Issued | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2024 | Corrections Issued | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 11/6/2024 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 11/26/2024 | Not Ready for Inspection | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 11/26/2024 | Not Ready for Inspection | VINCENT HANLEY |
| Deputy Wood Construction | 12/2/2024 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2024 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 12/5/2024 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 2/3/2025 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Rough | 2/3/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Rough | 2/3/2025 | Corrections Issued | MICHEL ABAJAN |
| PLUMBING-Rough | 2/3/2025 | Corrections Issued | MICHEL ABAJAN |
| Sewer | 2/12/2025 | Approved | VINCENT HANLEY |
| Rough-Elec/Plmb/HVAC | 2/18/2025 | Approved | VINCENT HANLEY |
| Insulation | 3/4/2025 | Corrections Issued | VINCENT HANLEY |
| Interior/Exterior Lathing | 3/4/2025 | Not Ready for Inspection | VINCENT HANLEY |
| Interior/Exterior Lathing | 3/5/2025 | Partial Approval | VINCENT HANLEY |
| Drywall Nailing | 3/25/2025 | Corrections Issued | WILLIAM WREN |
| Drywall Nailing | 3/28/2025 | Approved | VINCENT HANLEY |
| Insulation | 3/28/2025 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 4/14/2025 | Partial Approval | MICHAEL CORTEZ |
| Underground Mechanical | 9/3/2025 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 10/21/2025 | Approved | VINCENT HANLEY |
| Final | 10/21/2025 | Corrections Issued | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 10/21/2025 | SGSOV Not Required | VINCENT HANLEY |
| Service/Power Release | 10/21/2025 | Corrections Issued | VINCENT HANLEY |
| Smoke Detectors | 10/21/2025 | Corrections Issued | VINCENT HANLEY |
| Service/Power Release | 10/29/2025 | No Access for Inspection | VINCENT HANLEY |
| Final | 12/15/2025 | Corrections Issued | VINCENT HANLEY |
| Service/Power Release | 12/15/2025 | Approved | VINCENT HANLEY |
| Smoke Detectors | 12/15/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 12/23/2025 | Corrections Issued | VINCENT HANLEY |
| Final | 12/23/2025 | Corrections Issued | VINCENT HANLEY |
| HVAC-Final | 12/23/2025 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Final | 12/23/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 12/30/2025 | Approved | VINCENT HANLEY |
| Final | 12/30/2025 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 12/30/2025 | Approved | VINCENT HANLEY |