4524 N MAMMOTH AVE 91423

Certificate Information: 4524 N MAMMOTH AVE 91423

Application / Permit
23010-20000-02370
Plan Check / Job No.
B23VN07421
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 35' X 29'-9" ONE STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENGINEERING NFPA 13D REQUIRED THROUGHOUT
Permit Issued
Issued on 8/14/2024
Issuing Office
Valley
Current Status
CofO Issued on 11/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/6/2023 APPLICANT
Assigned to Plan Check Engineer 6/8/2023 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 6/13/2023 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 6/14/2023 OMID HEDAYAT
Building Plans Picked Up 7/3/2023 APPLICANT
Applicant returned to address corrections 4/3/2024 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 8/9/2024 SEWADA ZADOORAN MILAGARDI
Issued 8/14/2024 APPLICANT
CofO in Progress 7/28/2025 KEVIN BERBERYAN
No Progress 8/1/2025 RAUL OLAGI
CofO in Progress 8/1/2025 RAUL OLAGI
CofO in Progress 11/6/2025 KEVIN BERBERYAN
Permit Finaled 11/18/2025 RUBEN SALAS
CofO Issued 11/18/2025 RUBEN SALAS
Permit Finaled 11/18/2025 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 1/30/2024 RIDWAN HARDY
Construction within easement Cleared 1/30/2024 RIDWAN HARDY
ZI Cleared 2/26/2024 DALIA MOKAYED
Low Impact Development (LID) Cleared 2/27/2024 SAMUEL LINN
Address approval Cleared 3/6/2024 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 3/15/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 3/15/2024 CARLOS AGUILERA
Sewer availability Cleared 3/15/2024 CARLOS AGUILERA
Hydrant and Access approval Cleared 5/5/2024 JOHN CONNEALLY

Contact Information

Architect Heeb,, Derek M; Lic. No.: C32338 406 BROADWAY 222C      SANTA MONICA, CA 90401
Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/21/2024 Partial Inspection MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 8/28/2024 Corrections Issued MISAEL ESPARZA
Pre-Inspection 8/28/2024 Partial Inspection MISAEL ESPARZA
PLUMBING-Rough 9/3/2024 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 9/4/2024 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 9/4/2024 Partial Inspection MISAEL ESPARZA
Sewer 9/4/2024 Approved MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 9/5/2024 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/1/2024 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 10/7/2024 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/10/2024 Partial Approval MISAEL ESPARZA
HVAC-Rough 10/10/2024 Corrections Issued MISAEL ESPARZA
Insulation 10/11/2024 Partial Inspection MISAEL ESPARZA
ELECTRICAL-Rough 11/8/2024 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 11/8/2024 Partial Approval MISAEL ESPARZA
HVAC-Rough 11/8/2024 Corrections Issued MISAEL ESPARZA
Underground Mechanical 11/8/2024 Partial Approval MISAEL ESPARZA
Interior/Exterior Lathing 11/14/2024 Partial Approval MISAEL ESPARZA
Verify Sprinkler Sign Off 11/14/2024 Approved MISAEL ESPARZA
ELECTRICAL-Rough 11/18/2024 Approved MISAEL ESPARZA
HVAC-Rough 11/18/2024 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 11/18/2024 Approved MISAEL ESPARZA
HVAC-Rough 11/25/2024 Not Ready for Inspection MISAEL ESPARZA
Masonry Wall/Backfill 11/25/2024 Partial Inspection MISAEL ESPARZA
Wood Frame 11/25/2024 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 12/2/2024 Approved MISAEL ESPARZA
Green Building Rough 12/2/2024 Approved MISAEL ESPARZA
HVAC-Rough 12/2/2024 Approved MISAEL ESPARZA
MERV13>=Rough 12/2/2024 Approved MISAEL ESPARZA
Wood Frame 12/2/2024 Approved MISAEL ESPARZA
Insulation 12/6/2024 Approved MISAEL ESPARZA
Drywall Nailing 12/16/2024 Approved MICHAEL CORTEZ
ELECTRICAL-Rough 1/7/2025 Partial Inspection MISAEL ESPARZA
Service/Power Release 1/7/2025 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Final 2/12/2025 Corrections Issued MISAEL ESPARZA
Service/Power Release 2/12/2025 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Final 2/25/2025 Corrections Issued MISAEL ESPARZA
HVAC-Final 2/25/2025 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 2/25/2025 Approved MISAEL ESPARZA
ELECTRICAL-Final 6/23/2025 Corrections Issued MISAEL ESPARZA
Final 7/22/2025 OK to Issue CofO KEVIN BERBERYAN
Footing/Foundation/Slab 7/22/2025 Approved KEVIN BERBERYAN
Green Building Final 7/22/2025 Approved KEVIN BERBERYAN
MERV13>=Final 7/22/2025 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 7/22/2025 SGSOV No Gas KEVIN BERBERYAN
Service/Power Release 7/22/2025 Approved KEVIN BERBERYAN
Smoke Detectors 7/22/2025 Approved KEVIN BERBERYAN
Special/Order Compliance 8/6/2025 Corrections Issued KEVIN BERBERYAN
Final 11/6/2025 OK to Issue CofO KEVIN BERBERYAN