12614 N KENNY DR 91344
Certificate Information: 12614 N KENNY DR 91344
- Application / Permit
- 23010-20000-02348
- Plan Check / Job No.
- B23VN07323
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 1-STORY (17'-6"x25'-2"), 440 SQFT ADU PER CA GOVT CODE 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)(d)(g)
- Permit Issued
- Issued on 1/9/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2023 | PETER MOSESIAN |
| Corrections Issued | 6/10/2023 | PETER MOSESIAN |
| Quality Review Completed | 6/14/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 6/20/2023 | APPLICANT |
| Plan Check Approved | 7/14/2023 | PETER MOSESIAN |
| Issued | 1/9/2024 | APPLICANT |
| CofO in Progress | 3/17/2025 | JAVIER RAMOS JR |
| Permit Finaled | 4/10/2025 | RUBEN SALAS |
| CofO Issued | 4/10/2025 | RUBEN SALAS |
| Permit Finaled | 4/10/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/21/2023 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 6/21/2023 | LEE GUILBEAUX |
| Street Frontage | Cleared | 6/21/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/22/2023 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 6/26/2023 | LEE GUILBEAUX |
| Construction within easement | Cleared | 6/29/2023 | WALTER RAMIREZ |
| ZA Case | Cleared | 6/29/2023 | ASHLEY RODARTE |
| ZA Case | Cleared | 6/29/2023 | ASHLEY RODARTE |
| Grading Pre-Inspection | Cleared | 7/10/2023 | ALEXANDER HELFER |
Contact Information
| Contractor | Framing Square Construction; Lic. No.: 574861-B | 4082 DEBORAH STREET SIMI VALLEY, CA 93063 |
| Engineer | Reith,, David Lee; Lic. No.: C72122 | 1319 FEATHER AVE THOUSAND OAKS, CA 91360 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/31/2024 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 2/27/2024 | Approved | JOHN COLEMAN |
| Underground Mechanical | 2/27/2024 | Approved | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2024 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2024 | Partial Approval | JOHN COLEMAN |
| PLUMBING-Rough | 4/10/2024 | Partial Approval | JOHN COLEMAN |
| Special/Order Compliance | 4/10/2024 | Corrections Issued | JOHN COLEMAN |
| Deputy Wood Construction | 5/10/2024 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2024 | Approved | JAVIER RAMOS JR |
| Special/Order Compliance | 5/10/2024 | Corrections Issued | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 6/4/2024 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 6/4/2024 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 6/4/2024 | Corrections Issued | RAUL OLAGI |
| Interior/Exterior Lathing | 6/4/2024 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 6/4/2024 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 6/12/2024 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 6/12/2024 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 6/12/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 6/12/2024 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 6/12/2024 | Approved | JAVIER RAMOS JR |
| Insulation | 6/24/2024 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 6/28/2024 | Approved | JAVIER RAMOS JR |
| Sewer | 2/27/2025 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 2/27/2025 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 3/11/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 3/11/2025 | Approved | JAVIER RAMOS JR |
| Final | 3/11/2025 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 3/11/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Final | 3/11/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 3/11/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 3/11/2025 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 3/11/2025 | Approved | JAVIER RAMOS JR |
| Final | 3/17/2025 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 3/17/2025 | Approved | JAVIER RAMOS JR |