12614 N KENNY DR 91344

Certificate Information: 12614 N KENNY DR 91344

Application / Permit
23010-20000-02348
Plan Check / Job No.
B23VN07323
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 1-STORY (17'-6"x25'-2"), 440 SQFT ADU PER CA GOVT CODE 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)(d)(g)
Permit Issued
Issued on 1/9/2024
Issuing Office
Valley
Current Status
CofO Issued on 4/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/5/2023 APPLICANT
Assigned to Plan Check Engineer 6/8/2023 PETER MOSESIAN
Corrections Issued 6/10/2023 PETER MOSESIAN
Quality Review Completed 6/14/2023 OMID HEDAYAT
Building Plans Picked Up 6/20/2023 APPLICANT
Plan Check Approved 7/14/2023 PETER MOSESIAN
Issued 1/9/2024 APPLICANT
CofO in Progress 3/17/2025 JAVIER RAMOS JR
Permit Finaled 4/10/2025 RUBEN SALAS
CofO Issued 4/10/2025 RUBEN SALAS
Permit Finaled 4/10/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/21/2023 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 6/21/2023 LEE GUILBEAUX
Street Frontage Cleared 6/21/2023 LEE GUILBEAUX
Sewer availability Cleared 6/22/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 6/26/2023 LEE GUILBEAUX
Construction within easement Cleared 6/29/2023 WALTER RAMIREZ
ZA Case Cleared 6/29/2023 ASHLEY RODARTE
ZA Case Cleared 6/29/2023 ASHLEY RODARTE
Grading Pre-Inspection Cleared 7/10/2023 ALEXANDER HELFER

Contact Information

Contractor Framing Square Construction; Lic. No.: 574861-B 4082 DEBORAH STREET      SIMI VALLEY, CA 93063
Engineer Reith,, David Lee; Lic. No.: C72122 1319 FEATHER AVE      THOUSAND OAKS, CA 91360

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/31/2024 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 2/27/2024 Approved JOHN COLEMAN
Underground Mechanical 2/27/2024 Approved JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 3/28/2024 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/10/2024 Partial Approval JOHN COLEMAN
PLUMBING-Rough 4/10/2024 Partial Approval JOHN COLEMAN
Special/Order Compliance 4/10/2024 Corrections Issued JOHN COLEMAN
Deputy Wood Construction 5/10/2024 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 5/10/2024 Approved JAVIER RAMOS JR
Special/Order Compliance 5/10/2024 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 6/4/2024 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 6/4/2024 Corrections Issued RAUL OLAGI
HVAC-Rough 6/4/2024 Corrections Issued RAUL OLAGI
Interior/Exterior Lathing 6/4/2024 Partial Approval RAUL OLAGI
PLUMBING-Rough 6/4/2024 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 6/12/2024 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 6/12/2024 Approved JAVIER RAMOS JR
Green Building Rough 6/12/2024 Approved JAVIER RAMOS JR
HVAC-Rough 6/12/2024 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 6/12/2024 Approved JAVIER RAMOS JR
Insulation 6/24/2024 Approved JAVIER RAMOS JR
Drywall Nailing 6/28/2024 Approved JAVIER RAMOS JR
Sewer 2/27/2025 Approved JAVIER RAMOS JR
Underground Mechanical 2/27/2025 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 3/11/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Final 3/11/2025 Approved JAVIER RAMOS JR
Final 3/11/2025 Corrections Issued JAVIER RAMOS JR
Green Building Final 3/11/2025 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 3/11/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 3/11/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 3/11/2025 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 3/11/2025 Approved JAVIER RAMOS JR
Final 3/17/2025 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 3/17/2025 Approved JAVIER RAMOS JR