12745 W DAVENTRY ST 91331

Certificate Information: 12745 W DAVENTRY ST 91331

Application / Permit
23010-20000-02336
Plan Check / Job No.
B23VN07286
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan New detached structure with storage room and 1 car garage on first floor and SB9 unit on second floor. SB9 per CA Gov. Code 65852.21 "COMPLY WITH DEPARTMENT ORDER effective date 12/26/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 4/5/2024
Issuing Office
Current Status
CofO Issued on 12/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/4/2023 APPLICANT
Assigned to Plan Check Engineer 6/22/2023 MARCELA FRANQUEZ
Corrections Issued 6/29/2023 MARCELA FRANQUEZ
Quality Review Completed 7/7/2023 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 9/25/2023 MARCELA FRANQUEZ
Plan Check Approved 4/2/2024 MARCELA FRANQUEZ
Issued 4/5/2024 APPLICANT
Permit Finaled 12/5/2025 DAVID JAMES
CofO Issued 12/5/2025 DAVID JAMES
Permit Finaled 12/5/2025 DAVID JAMES

Permit Application Clearance Information

Address approval Cleared 8/3/2023 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 8/4/2023 ROMAN GUTIERREZ
Sewer availability Cleared 8/4/2023 ROMAN GUTIERREZ
Low Impact Development (LID) Cleared 8/23/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 8/26/2023 CARLOS AGUILERA
Senate Bill 9 Cleared 1/25/2024 ALEX VELA
Hydrant and Access approval Cleared 3/9/2024 GILBERT URREA
Clean Up Green Up Cleared 3/26/2024 ALEX VELA
ZI Cleared 3/26/2024 ALEX VELA

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: NA53080       ,

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIO CUEVAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/29/2024 Approved RAUL VASQUEZ
Footing/Foundation/Slab 5/29/2024 Approved RAUL VASQUEZ
PLUMBING-Rough 5/29/2024 Not Ready for Inspection RAUL VASQUEZ
Pre-Inspection 5/29/2024 Approved RAUL VASQUEZ
Underground Mechanical 5/29/2024 Approved RAUL VASQUEZ
Floor/Roof Diaphrgm/Shear Wall 6/18/2024 Approved RAUL VASQUEZ
Floor/Roof Diaphrgm/Shear Wall 7/5/2024 Approved ARA SINANIAN
BUILDING-Rough-Frame 7/16/2024 Corrections Issued RAUL VASQUEZ
ELECTRICAL-Rough 7/16/2024 Corrections Issued RAUL VASQUEZ
Green Building Rough 7/16/2024 Not Ready for Inspection RAUL VASQUEZ
HVAC-Rough 7/16/2024 Not Ready for Inspection RAUL VASQUEZ
MERV13>=Rough 7/16/2024 Not Ready for Inspection RAUL VASQUEZ
PLUMBING-Rough 7/16/2024 Corrections Issued RAUL VASQUEZ
Verify Sprinkler Sign Off 7/16/2024 Not Ready for Inspection RAUL VASQUEZ
BUILDING-Rough-Frame 7/19/2024 Partial Approval MARIO CUEVAS
Deputy Wood Construction 7/19/2024 Approved MARIO CUEVAS
ELECTRICAL-Rough 7/19/2024 Approved MARIO CUEVAS
Green Building Rough 7/19/2024 Approved MARIO CUEVAS
HVAC-Rough 7/19/2024 Not Ready for Inspection MARIO CUEVAS
MERV13>=Rough 7/19/2024 Not Ready for Inspection MARIO CUEVAS
PLUMBING-Rough 7/19/2024 Approved MARIO CUEVAS
Verify Sprinkler Sign Off 7/19/2024 Not Ready for Inspection MARIO CUEVAS
Insulation 7/23/2024 Not Ready for Inspection MARIO CUEVAS
Interior/Exterior Lathing 7/23/2024 Not Ready for Inspection MARIO CUEVAS
Insulation 7/25/2024 Approved ARA SINANIAN
Interior/Exterior Lathing 7/25/2024 Not Ready for Inspection ARA SINANIAN
Drywall Nailing 7/31/2024 Approved ARA SINANIAN
Interior/Exterior Lathing 7/31/2024 Approved ARA SINANIAN
Final 10/8/2024 Corrections Issued RAUL VASQUEZ
HVAC-Final 10/8/2024 Approved RAUL VASQUEZ
PLUMBING-Final 10/8/2024 Approved RAUL VASQUEZ
BUILDING-Rough-Frame 10/16/2024 Corrections Issued RAUL VASQUEZ
Final 10/16/2024 Not Ready for Inspection RAUL VASQUEZ
Green Building Final 10/16/2024 Approved RAUL VASQUEZ
MERV13>=Final 10/16/2024 Not Ready for Inspection RAUL VASQUEZ
MERV13>=Rough 10/16/2024 Not Ready for Inspection RAUL VASQUEZ
SGSOV-Seismic Gas S/O Valve 10/16/2024 SGSOV Approved RAUL VASQUEZ
Service/Power Release 10/16/2024 Not Ready for Inspection RAUL VASQUEZ
Smoke Detectors 10/16/2024 Approved RAUL VASQUEZ
Verify Sprinkler Sign Off 10/16/2024 Not Ready for Inspection RAUL VASQUEZ
HVAC-Rough 10/18/2024 Approved MARK VAN SLOOTEN
BUILDING-Rough-Frame 2/4/2025 Not Ready for Inspection RAUL VASQUEZ
Final 2/4/2025 Not Ready for Inspection RAUL VASQUEZ
MERV13>=Final 2/4/2025 Not Ready for Inspection RAUL VASQUEZ
MERV13>=Rough 2/4/2025 Not Ready for Inspection RAUL VASQUEZ
Service/Power Release 2/4/2025 Not Ready for Inspection RAUL VASQUEZ
Verify Sprinkler Sign Off 2/4/2025 Not Ready for Inspection RAUL VASQUEZ
BUILDING-Rough-Frame 4/30/2025 Not Required RAUL VASQUEZ
Final 4/30/2025 Not Required RAUL VASQUEZ
MERV13>=Final 4/30/2025 Not Required RAUL VASQUEZ
MERV13>=Rough 4/30/2025 Not Required RAUL VASQUEZ
Service/Power Release 4/30/2025 Not Required RAUL VASQUEZ
Verify Sprinkler Sign Off 4/30/2025 Not Required RAUL VASQUEZ
Service/Power Release 6/4/2025 Not Ready for Inspection RAUL VASQUEZ
BUILDING-Rough-Frame 8/12/2025 Approved MARK VAN SLOOTEN
Final 8/12/2025 Conditional Approval MARK VAN SLOOTEN
MERV13>=Final 8/12/2025 Approved MARK VAN SLOOTEN
MERV13>=Rough 8/12/2025 Approved MARK VAN SLOOTEN
Service/Power Release 8/12/2025 Approved MARK VAN SLOOTEN
Verify Sprinkler Sign Off 8/12/2025 Approved MARK VAN SLOOTEN