22843 W DOLOROSA ST 91367
Certificate Information: 22843 W DOLOROSA ST 91367
- Application / Permit
- 23010-20000-02318
- Plan Check / Job No.
- B23VN07257
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 1-STORY (52'-0"x35'-2"), 1198 SQFT ADU W/ATTACHED (146 SQFT) PATIO COVER PER LAMC 12.22 A.33 (c)(d)
- Permit Issued
- Issued on 9/20/2023
- Issuing Office
- Current Status
- CofO Issued on 4/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/2/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2023 | PETER MOSESIAN |
| Corrections Issued | 6/10/2023 | PETER MOSESIAN |
| Quality Review Completed | 6/14/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 6/16/2023 | APPLICANT |
| Plan Check Approved | 9/20/2023 | PETER MOSESIAN |
| Issued | 9/20/2023 | APPLICANT |
| CofO in Progress | 5/3/2024 | TROY SANDERS |
| No Progress | 1/17/2025 | HENRY KIM |
| CofO in Progress | 1/17/2025 | HENRY KIM |
| Permit Finaled | 4/22/2025 | JOHN JANSON |
| CofO Issued | 4/22/2025 | JOHN JANSON |
| Permit Finaled | 4/22/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/22/2023 | DAGOVERTO GUERRERO |
| Low Impact Development (LID) | Cleared | 7/12/2023 | SARAH YOUSSEF |
| Hydrant and Access approval | Cleared | 7/24/2023 | JOHN CONNEALLY |
| Grading Pre-Inspection | Cleared | 7/31/2023 | SERGIO VALENZUELA |
| Eng Process Fee Ord 176,300 | Cleared | 8/1/2023 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 8/1/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 8/1/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rahman,, Moksudur; Lic. No.: C69263 | 14616 MCKENDREE AVE CHINO, CA 91708 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/22/2023 | Approved | MORRIS JACKSON |
| Footing/Foundation/Slab | 9/27/2023 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 10/30/2023 | Not Ready for Inspection | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2023 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 10/30/2023 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 11/9/2023 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 11/9/2023 | Approved | TROY SANDERS |
| Green Building Rough | 11/9/2023 | Approved | TROY SANDERS |
| HVAC-Rough | 11/9/2023 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 11/9/2023 | Partial Approval | TROY SANDERS |
| Shower Pan | 11/9/2023 | Approved | TROY SANDERS |
| Verify Sprinkler Sign Off | 11/9/2023 | Approved | TROY SANDERS |
| Drywall Nailing | 11/21/2023 | Approved | TROY SANDERS |
| Insulation | 11/21/2023 | Approved | TROY SANDERS |
| Wood Frame | 11/21/2023 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 4/17/2024 | SGSOV Not Ready | TROY SANDERS |
| Final | 4/26/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Green Building Final | 4/26/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| SGSOV-Seismic Gas S/O Valve | 4/26/2024 | SGSOV Not Ready | GEVORK IPCHYAN |
| Service/Power Release | 4/26/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Smoke Detectors | 4/26/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Final | 5/2/2024 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 5/2/2024 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 5/2/2024 | SGSOV Approved | TROY SANDERS |
| Service/Power Release | 5/2/2024 | Approved | TROY SANDERS |
| Smoke Detectors | 5/2/2024 | Approved | TROY SANDERS |
| Special/Order Compliance | 1/9/2025 | Corrections Issued | TROY SANDERS |